Monthly State Let Construction Report For Amarillo District As Of Apr 10, 2015 Page 3 Of 3

Last Update: Friday, April 10, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyRANDALL
Highway PR 5
From AT WATER CROSS 1,2,6 AND BURNT DRAW
To IN PALO DURO CANYON STATE PARK
CSJ 0534-01-019
Proj ID C 534-1-19
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.576 3956849.00 0.00 3602508.35 93.7
Work Order 11-04-13
Work Began 11-04-13
Work Completed  
Time Computed 11-20-13
Contract Working Days 235
Addl Days Granted 0
Working Days Charged 270
Percent Time Used 114
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-019
ENVIRONMENTAL SAFETY SERVICES, INC.(3.98%)
HOLMES CONSTRUCTION CO., L.P.( 27.09%)
LANCO TURF & SEEDING, INC. (0.52%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.27%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
MH CIVIL CONSTRUCTORS, INC.(0.24%)
BARRICADES UNLIMITED (0.29%)
DAVIS CONSTRUCTION, INC. ( 27.81%)
AMARILLO RMT ENTERPRISE(1.81%)
Contract # 09133228
Totals 3956849.00 0.00 3602508.35 93.7

CountyRANDALL
Highway PR 5
From AT WATER CROSSINGS 3,4 AND 5
To WITHIN PALO DURO CANYON STATE PARK
CSJ 0534-01-020
Proj ID C 534-1-20
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.385 3768710.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 230
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153034
Totals 3768710.10 0.00 0.00 0.0

CountyLIPSCOMB
Highway SH 305
From SP 188
To LIPSCOMB COUNTY LINE
CSJ 0582-02-018
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 6255144.40 37800.00 6453541.73 99.9
CountyHEMPHILL
Highway SH 305
From LIPSCOMB COUNTY LINE
To US 60
CSJ 0582-03-014
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 1439611.54 0.00 1566706.77 99.9
Work Order 11-14-13
Work Began 04-15-14
Work Completed  
Time Computed 11-30-13
Contract Working Days 130
Addl Days Granted 5
Working Days Charged 133
Percent Time Used 98
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0582-02-018
BARRICADES UNLIMITED (1.55%)
HJC FARMS, INC.(0.88%)
SCR CONSTRUCTION CO., INC. (2.06%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(0.27%)
Contract # 10133018
Totals 7694755.94 37800.00 8020248.50 99.9

CountySHERMAN
Highway SH 15
From US 287
To CR 7 IN STRATFORD
CSJ 0790-03-023
Proj ID STP 2015(456)
Work Type NEW LOCATION 2 LANE RDWY
 
0.405 1836726.42 174836.05 174836.05 9.5
CountySHERMAN
Highway SH 15
From CR 7 IN STRATFORD
To CR 9
CSJ 0790-03-025
Proj ID STP 2015(456)
Work Type RESTORATION OF PAVEMENT STRUCTURE
 
1.883 917220.31 0.00 0.00 0.0
Work Order 03-06-15
Work Began 00-00-00
Work Completed  
Time Computed 05-06-15
Contract Working Days 105
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 12
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0790-03-023
BARRICADES UNLIMITED (1.96%)
ALAMO BROTHERS CONCRETE(6.81%)
Contract # 01153029
Totals 2753946.73 174836.05 174836.05 6.3

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To (ON SYSTEM)
CSJ 0904-00-154
Proj ID STP 2013(085)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2916208.80 7500.00 2254834.69 100.0
Work Order 12-04-12
Work Began 01-08-13
Work Completed 10-27-14
Time Computed 12-20-12
Contract Working Days 206
Addl Days Granted 2
Working Days Charged 208
Percent Time Used 100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-154
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(6.11%)
CLASSIC TEJAS CONSTRUCTION, INC. ( 14.49%)
Contract # 10123029
Totals 2916208.80 7500.00 2254834.69 100.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-155
Proj ID STP 2015(588)
Work Type THERMOPLASTIC STRIPING
 
0.001 2103735.09 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153017
Totals 2103735.09 0.00 0.00 0.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-156
Proj ID STP 2015(056)
Work Type CRACK SEAL
 
282.864 646972.39 150707.11 634627.29 99.9
Work Order 10-28-14
Work Began 11-17-14
Work Completed  
Time Computed 11-10-14
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 95
Percent Time Used 133
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-156
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143033
Totals 646972.39 150707.11 634627.29 99.9

CountyPOTTER
Highway VA
From AT VARIOUS LOCATIONS IN AMARILLO
To .
CSJ 0904-00-160
Proj ID STP 2015(649)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2895601.55 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 274
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-160
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03153026
Totals 2895601.55 0.00 0.00 0.0

CountyHUTCHINSON
Highway CS
From ON ROOSEVELT ST. FROM SH 136
To SH 207
CSJ 0904-07-012
Proj ID STP 2013(490)
Work Type REHAB EXISTING ROADWAY
 
0.769 1870540.00 20290.75 1227097.11 74.1
Work Order 07-31-13
Work Began 09-03-13
Work Completed  
Time Computed 08-16-13
Contract Working Days 124
Addl Days Granted 4
Working Days Charged 332
Percent Time Used 259
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-07-012
RAY ELECTRIC COMPANY (1.71%)
ALAMO BROTHERS CONCRETE( 26.42%)
A-1 SERVICES (0.26%)
BARRICADES UNLIMITED (3.15%)
TEX OP CONSTRUCTION, LP(0.61%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
Contract # 06133015
Totals 1870540.00 20290.75 1227097.11 74.1

CountyRANDALL
Highway CS
From ON FARMERS AVE, FROM WESTERN ST
To GEORGIA ST
CSJ 0904-11-053
Proj ID STP 2013(143)
Work Type REHAB EXISTING ROADWAY
 
0.996 1400000.00 0.00 1378618.18 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-04-13
Work Began 06-03-13
Work Completed  
Time Computed 06-10-13
Contract Working Days 83
Addl Days Granted 10
Working Days Charged 196
Percent Time Used 210
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-11-053
A-1 SERVICES (0.18%)
ALAMO BROTHERS CONCRETE(8.38%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.65%)
Contract # 11123019
Totals 1400000.00 0.00 1378618.18 99.9

CountyRANDALL
Highway CS
From ON 58TH AVE, FROM GEORGIA ST
To WASHINGTON ST
CSJ 0904-11-054
Proj ID STP 2014(606)
Work Type REHAB EXISTING ROADWAY
 
0.971 1999859.05 166874.83 934186.15 46.7
Work Order 07-29-14
Work Began 08-18-14
Work Completed  
Time Computed 08-14-14
Contract Working Days 142
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 85
Contractor(s)
HOLMES CONSTRUCTION CO., L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-11-054
ALAMO BROTHERS CONCRETE(7.50%)
BARRICADES UNLIMITED (2.85%)
Contract # 05143028
Totals 1999859.05 166874.83 934186.15 46.7

CountyRANDALL
Highway VA
From US 60 AT CANYON TEXAS
To .
CSJ 0904-11-057
Proj ID STP 2014(107)TE
Work Type TRANSPORTATION ENHANCEMENT
 
0.001 613923.87 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JR TRI-STATE GENERAL CONTRACTING GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-11-057
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153234
Totals 613923.87 0.00 0.00 0.0

CountyGRAY
Highway CR
From ON SEMINOLE RD
To AT SOUTH FORK GRAPEVINE CREEK
CSJ 0904-13-022
Proj ID BR 2012(728)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.167 382540.00 41964.39 369244.39 96.5
Work Order 09-15-14
Work Began 10-20-14
Work Completed  
Time Computed 10-01-14
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 98
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-13-022
BARRICADES UNLIMITED (1.17%)
LANCO TURF & SEEDING, INC. (1.58%)
Contract # 08143019
Totals 382540.00 41964.39 369244.39 96.5

CountyLIPSCOMB
Highway SH 23
From FM 377
To 11.05 MI N OF US 83
CSJ 1337-01-022
Proj ID C 1337-1-22
Work Type REHAB & WIDEN EXISTING RDWY
 
10.063 5502012.06 316185.38 4365984.26 79.4
Work Order 11-19-12
Work Began 01-09-13
Work Completed  
Time Computed 12-05-12
Contract Working Days 250
Addl Days Granted 166
Working Days Charged 419
Percent Time Used 100
Contractor(s)
MITCHELL ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1337-01-022
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.68%)
HJC FARMS, INC.(1.81%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.18%)
B&B SOLVENT, LTD.( 64.57%)
RICE CONSTRUCTION( 19.87%)
Contract # 07123220
Totals 5502012.06 316185.38 4365984.26 79.4

CountyLIPSCOMB
Highway SH 23
From 11.05 MI N OF US 83
To US 83
CSJ 1337-02-010
Proj ID STP 2013(086)
Work Type REHAB & WIDEN EXISTING RDWY
 
11.050 6406551.08 78570.50 6143963.13 98.0
Work Order 01-03-13
Work Began 01-07-13
Work Completed  
Time Computed 01-19-13
Contract Working Days 190
Addl Days Granted 40
Working Days Charged 350
Percent Time Used 152
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1337-02-010
AMARILLO RMT ENTERPRISE(2.63%)
CUTRELL TRUCKING COMPANY, INC. (3.97%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.80%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(2.04%)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (0.32%)
Contract # 10123014
Totals 6406551.08 78570.50 6143963.13 98.0

CountyDALLAM
Highway SS 17
From US 87
To US 385
CSJ 1702-03-001
Proj ID STP 2011(992)
Work Type NEW LOCATION 2 LANE RDWY
 
1.866 1621574.25 0.00 1853975.60 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-14-11
Work Began 02-06-12
Work Completed  
Time Computed 02-28-12
Contract Working Days 150
Addl Days Granted 17
Working Days Charged 174
Percent Time Used 104
Contractor(s)
HOLMES CONSTRUCTION CO., L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1702-03-001
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(3.37%)
SECRET GARDENER(0.94%)
Contract # 05113008
Totals 1621574.25 0.00 1853975.60 99.9

CountyLIPSCOMB
Highway RM 2248
From AT NORTH FORK KIOWA CREEK
To .
CSJ 2078-02-007
Proj ID BR 2012(478)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.227 1605360.30 0.00 1629740.77 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-14-14
Work Began 03-04-14
Work Completed  
Time Computed 03-02-14
Contract Working Days 205
Addl Days Granted 0
Working Days Charged 173
Percent Time Used 84
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2078-02-007
ALAMO BROTHERS CONCRETE(2.24%)
BARRICADES UNLIMITED (1.94%)
E. DIAZ TRUCKING (0.00%)
HJC FARMS, INC.(1.99%)
SHINN & GREGORY, INC.(5.73%)
Contract # 11133011
Totals 1605360.30 0.00 1629740.77 99.9

CountyRANDALL
Highway LP 335
From IH 27, E
To BNSF RR
CSJ 2635-02-022
Proj ID DMO 2012(189)
Work Type ADDITIONAL 2 LANES AND BRIDGES
 
3.000 32232646.86 675526.47 7394981.93 22.9
Work Order 03-04-14
Work Began 11-03-14
Work Completed  
Time Computed 03-20-14
Contract Working Days 645
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 4
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-022
ALAMO BROTHERS CONCRETE(4.52%)
BARRICADES UNLIMITED (1.36%)
LONE STAR PRODUCTS (FLOWER MOUND)(0.00%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.73%)
MCL CONTRACTING, LLC (0.04%)
PENHALL COMPANY (AUSTIN) (0.02%)
WILLIS ELECTRIC CO., LP(2.97%)
Contract # 12133202
Totals 32232646.86 675526.47 7394981.93 22.9

page 1 | page 2 | page 3