Monthly State Let Construction Report For Amarillo District As Of Feb 11, 2016 Page 3 Of 4

Last Update: Thursday, February 11, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPOTTER
Highway IH 40
From AT SL335 (LAKESIDE)
To .
CSJ 0275-01-168
Proj ID NH 1502(349)
Work Type CONSTRUCT TURNAROUNDS
 
0.340 2519584.25 538800.27 2918542.47 99.9
CountyRANDALL
Highway SL 335
From 0.13 MILES EAST OF GEORGIA ST.
To 0.26 MILES WEST OF FM 1541
CSJ 2635-02-028
Proj ID STP 2013(605)
Work Type CONVERT NON - FREEWAY TO FREEWAY
 
0.808 17821897.20 499519.01 5996365.96 33.6
Work Order 07-31-15
Work Began 08-10-15
Work Completed  
Time Computed 08-10-15
Contract Working Days 460
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 26
Contractor(s)
WEBBER, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-028
TRUMBLE CRANE & RIGGING(0.07%)
DUSTIN ALLEN, INC. (1.07%)
L. A. FULLER & SONS CONSTRUCTION, LTD. ( 22.76%)
WILLIS ELECTRIC CO., LP(1.80%)
OSCAR ORDUNO, INC. (3.65%)
BARRICADES UNLIMITED (0.65%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.67%)
INDUS CONSTRUCTION, L.P. (1.34%)
MCL CONTRACTING, LLC (0.13%)
BREDA COMPANY, INC.(3.57%)
ALAMO BROTHERS CONCRETE(0.42%)
Contract # 04153057
Totals 20341481.45 1038319.28 8914908.43 43.8

CountyCARSON
Highway IH 40
From 3.0 MI EAST OF POTTER CO. LINE
To 3.7 MI WEST OF CONWAY
CSJ 0275-02-069
Proj ID IM 0401(208)
Work Type REHAB EXISTING ROADWAY
 
7.759 5177809.06 0.00 4980934.32 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-15-13
Work Began 10-28-13
Work Completed 01-26-15
Time Computed 01-31-13
Contract Working Days 85
Addl Days Granted 130
Working Days Charged 334
Percent Time Used 155
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-02-069
AMARILLO RMT ENTERPRISE(0.78%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.05%)
O. TREVINO CONSTRUCTION, LLC (7.18%)
TEX OP CONSTRUCTION, LP(1.36%)
WEST TEXAS RUMBLE STRIP(0.11%)
W.O.E. CONSTRUCTION(0.00%)
Contract # 11123206
Totals 5177809.06 0.00 4980934.32 100.0

CountyCARSON
Highway IH 40
From 3.2 MI WEST OF CONWAY
To 1.6 MI EAST OF CONWAY
CSJ 0275-03-062
Proj ID IM 0401(211)
Work Type REHAB EXISTING ROADWAY
 
4.876 3604723.24 0.00 3641833.57 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-11-14
Work Began 04-28-14
Work Completed 01-26-15
Time Computed 04-27-14
Contract Working Days 75
Addl Days Granted 44
Working Days Charged 130
Percent Time Used 109
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-03-062
BARRICADES UNLIMITED-USE NEW NUMBER 24847 ON NEW SUBCONTRACT (1.10%)
HJC FARMS, INC.(0.95%)
TEX OP CONSTRUCTION, LP(1.58%)
WEST TEXAS RUMBLE STRIP(0.14%)
O. TREVINO CONSTRUCTION, LLC ( 10.62%)
BARRICADES UNLIMITED (0.00%)
Contract # 02143205
Totals 3604723.24 0.00 3641833.57 100.0

CountyGRAY
Highway IH 40
From ALANREED
To DONLEY COUNTY LINE
CSJ 0275-11-077
Proj ID NH 1502(079)
Work Type OVERLAY AND MINOR BRIDGE MAINTENANC
 
9.571 3565812.59 0.00 21000.00 0.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-15-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-11-077
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153223
Totals 3565812.59 0.00 21000.00 0.5

CountyLIPSCOMB
Highway SH 15
From FM 2172 IN DARROUZETT
To FM 1455
CSJ 0355-01-047
Proj ID STP 2015(639)
Work Type OVERLAY
 
6.099 1996781.26 0.00 1990602.58 99.6
CountyLIPSCOMB
Highway SH 15
From OCHILTREE COUNTY LINE
To FM 2172 IN DARROUZETT
CSJ 0355-02-030
Proj ID STP 2015(639)
Work Type OVERLAY
 
12.620 2960757.17 0.00 2990306.83 99.9
CountyOCHILTREE
Highway SH 15
From HANSFORD COUNTY LINE
To US 83 IN PERRYTON
CSJ 0355-04-039
Proj ID STP 2015(587)
Work Type RESTORATION OF EXISTING ROADWAY
 
18.117 8770353.11 0.00 8572127.12 97.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-06-15
Work Began 06-02-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 122
Addl Days Granted 5
Working Days Charged 116
Percent Time Used 91
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0355-04-039
BARRICADES UNLIMITED (1.57%)
DUSTROL, INC.(0.60%)
HJC FARMS, INC.(0.90%)
O. TREVINO CONSTRUCTION, LLC (0.79%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.09%)
TEXAS ALTERNATIVE GRASSER, INC.(0.09%)
J C DIAZ TRUCKING(0.00%)
Contract # 01153026
Totals 13727891.54 0.00 13553036.53 98.7

CountyOCHILTREE
Highway SH 15
From US 83
To LIPSCOMB COUNTY LINE
CSJ 0355-03-028
Proj ID STP 2013(442)
Work Type OVERLAY
 
15.205 3838624.15 0.00 4024531.77 100.0
CountyOCHILTREE
Highway SH 15
From PERRYTON C&G
To LIPSCOMB COUNTY LINE
CSJ 0355-03-029
Proj ID STP 2013(442)
Work Type OVERLAY
 
14.665 1443103.90 0.00 1350594.12 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-23-13
Work Began 08-28-13
Work Completed 02-24-14
Time Computed 06-08-13
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 96
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0355-03-028
DUSTROL, INC.(0.34%)
FLAT LINE, INC.(0.95%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(4.59%)
J C DIAZ TRUCKING(3.54%)
BARRICADES UNLIMITED (0.30%)
Contract # 03133013
Totals 5281728.05 0.00 5375125.89 100.0

CountyHUTCHINSON
Highway SH 136
From AT ROCK CREEK
To .
CSJ 0356-01-091
Proj ID BR 2013(375)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.151 2716537.03 102050.00 2841915.08 100.0
Work Order 05-06-13
Work Began 07-30-13
Work Completed 05-19-15
Time Computed 05-22-13
Contract Working Days 241
Addl Days Granted 130
Working Days Charged 411
Percent Time Used 110
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0356-01-091
SCOTT DERR PAINTING CO, LLC(0.44%)
MCL CONTRACTING, LLC (0.93%)
RUNNING HORSE CONSTRUCTION, INC. (2.30%)
TEX OP CONSTRUCTION, LP(0.58%)
SHINN & GREGORY, INC.( 10.12%)
PRIMATE CONSTRUCTION, INC. (0.28%)
LANCO TURF & SEEDING, INC. (0.27%)
HJC FARMS, INC.(2.03%)
DUSTROL, INC.(0.19%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(2.43%)
AOC ENVIRONMENTAL, INC.(1.90%)
Contract # 02133215
Totals 2716537.03 102050.00 2841915.08 100.0

CountyCARSON
Highway SH 207
From FM 293
To HUTCHINSON COUNTY LINE
CSJ 0356-02-043
Proj ID STP 2014(866)
Work Type RESTORATION OF EXISTING ROADWAY
 
19.102 8607481.82 0.00 4061180.15 47.1
Work Order 09-30-14
Work Began 10-22-14
Work Completed  
Time Computed 10-16-14
Contract Working Days 110
Addl Days Granted 9
Working Days Charged 81
Percent Time Used 68
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0356-02-043
BARRICADES UNLIMITED (1.16%)
E. DIAZ TRUCKING (4.32%)
DUSTROL, INC.(1.37%)
RICE ENVIRONMENTAL SERVICES(1.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.77%)
WEST TEXAS RUMBLE STRIP(0.32%)
Contract # 07143211
Totals 8607481.82 0.00 4061180.15 47.1

CountyGRAY
Highway SH 152
From US 60
To WHEELER COUNTY LINE
CSJ 0397-01-043
Proj ID STP 2015(472)
Work Type OVERLAY
 
17.735 6779225.71 0.00 3123999.64 46.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-11-15
Work Began 09-22-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 51
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0397-01-043
BARRICADES UNLIMITED (1.88%)
DUSTROL, INC.(0.41%)
HJC FARMS, INC.(4.71%)
Contract # 01153208
Totals 6779225.71 0.00 3123999.64 46.0

CountyHARTLEY
Highway US 87
From EAST OF US 385 INTERCHANGE
To MOORE COUNTY LINE
CSJ 0425-01-019
Proj ID C 425-1-19
Work Type REHAB EXISTING RDWY & PASSING LANES
 
22.251 21250815.26 320952.00 19376681.72 100.0
Work Order 10-24-12
Work Began 11-19-12
Work Completed 11-13-15
Time Computed 11-09-12
Contract Working Days 370
Addl Days Granted 136
Working Days Charged 529
Percent Time Used 104
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0425-01-019
HIGHWAY TECHNOLOGIES, INC. (0.14%)
TEXAS ALTERNATIVE GRASSER, INC.(0.02%)
DUSTROL, INC.(1.94%)
HOLMES CONSTRUCTION CO., L.P.( 10.19%)
HJC FARMS, INC.(0.95%)
BALLOU PAVEMENT SOLUTIONS INC. ( 14.78%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.51%)
BRUSH EATERS, INC. (0.12%)
KOSS CONSTRUCTION COMPANY( 14.78%)
WILLIS ELECTRIC CO., LP(0.09%)
Contract # 08123002
Totals 21250815.26 320952.00 19376681.72 100.0

CountyROBERTS
Highway SH 70
From NORTH CANADIAN RIVER BRIDGE
To OCHILTREE COUNTY LINE
CSJ 0490-04-037
Proj ID STP 2014(579)
Work Type REHABILITATE EXISTING ROADWAY
 
5.848 5139086.58 0.00 1767021.25 34.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-18-14
Work Began 12-10-14
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 220
Percent Time Used 111
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
BARRICADES UNLIMITED (0.99%)
HJC FARMS, INC.(3.77%)
HUDSON, INC. (0.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.84%)
WEST TEXAS RUMBLE STRIP(0.08%)
W.S. CONSTRUCTION COMPANY(5.84%)
E. DIAZ TRUCKING (2.85%)
Contract # 04143003
Totals 5139086.58 0.00 1767021.25 34.8

CountyRANDALL
Highway PR 5
From AT WATER CROSS 1,2,6 AND BURNT DRAW
To IN PALO DURO CANYON STATE PARK
CSJ 0534-01-019
Proj ID C 534-1-19
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.576 3956849.00 0.00 3883594.32 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-04-13
Work Began 11-04-13
Work Completed 09-15-15
Time Computed 11-20-13
Contract Working Days 235
Addl Days Granted 23
Working Days Charged 282
Percent Time Used 109
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-019
ENVIRONMENTAL SAFETY SERVICES, INC.(3.98%)
HOLMES CONSTRUCTION CO., L.P.( 27.09%)
LANCO TURF & SEEDING, INC. (0.52%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.27%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
MH CIVIL CONSTRUCTORS, INC.(0.24%)
BARRICADES UNLIMITED (0.29%)
DAVIS CONSTRUCTION, INC. ( 27.81%)
AMARILLO RMT ENTERPRISE(1.81%)
Contract # 09133228
Totals 3956849.00 0.00 3883594.32 100.0

CountyRANDALL
Highway PR 5
From AT WATER CROSSINGS 3,4 AND 5
To WITHIN PALO DURO CANYON STATE PARK
CSJ 0534-01-020
Proj ID C 534-1-20
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.385 3768710.10 274572.88 2735695.05 72.5
Work Order 05-15-15
Work Began 06-08-15
Work Completed  
Time Computed 05-31-15
Contract Working Days 230
Addl Days Granted 10
Working Days Charged 141
Percent Time Used 58
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-020
ALTUS TRAFFIC MANAGEMENT LLC (1.58%)
WOLFE CONSTRUCTION GROUP, INC. (0.56%)
HUDSON, INC. (0.48%)
AMARILLO RMT ENTERPRISES, LLC(1.81%)
LONE STAR CONSTRUCTION (3.84%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.49%)
MCL CONTRACTING, LLC (0.26%)
Contract # 04153034
Totals 3768710.10 274572.88 2735695.05 72.5

CountyMOORE
Highway SH 152
From DUMAS CITY LIMITS
To HUTCHINSON COUNTY LINE
CSJ 0557-01-028
Proj ID STP 2016(683)
Work Type RESTORATION
 
47.263 15561610.53 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0557-01-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163003
Totals 15561610.53 0.00 0.00 0.0

CountyLIPSCOMB
Highway SH 305
From SP 188
To LIPSCOMB COUNTY LINE
CSJ 0582-02-018
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 6255144.40 0.00 6469334.09 100.0
CountyHEMPHILL
Highway SH 305
From LIPSCOMB COUNTY LINE
To US 60
CSJ 0582-03-014
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 1439611.54 0.00 1566712.33 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-14-13
Work Began 04-15-14
Work Completed 02-12-15
Time Computed 11-30-13
Contract Working Days 130
Addl Days Granted 5
Working Days Charged 133
Percent Time Used 98
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0582-02-018
BARRICADES UNLIMITED (1.55%)
HJC FARMS, INC.(0.88%)
SCR CONSTRUCTION CO., INC. (2.06%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(0.27%)
Contract # 10133018
Totals 7694755.94 0.00 8036046.42 100.0

CountySHERMAN
Highway SH 15
From US 287
To CR 7 IN STRATFORD
CSJ 0790-03-023
Proj ID STP 2015(456)
Work Type NEW LOCATION 2 LANE RDWY
 
0.405 1836726.42 185172.81 1957856.75 99.9
CountySHERMAN
Highway SH 15
From CR 7 IN STRATFORD
To CR 9
CSJ 0790-03-025
Proj ID STP 2015(456)
Work Type RESTORATION OF PAVEMENT STRUCTURE
 
1.883 917220.31 2077.56 1103509.88 99.9
Work Order 03-06-15
Work Began 03-19-15
Work Completed  
Time Computed 05-06-15
Contract Working Days 105
Addl Days Granted 50
Working Days Charged 104
Percent Time Used 67
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0790-03-023
BARRICADES UNLIMITED (1.96%)
ALAMO BROTHERS CONCRETE(6.81%)
Contract # 01153029
Totals 2753946.73 187250.37 3061366.63 99.9

CountyDALLAM
Highway FM 1727
From FM 3310
To 7 MI WEST OF FM 3489
CSJ 0794-01-018
Proj ID STP 1502(296)HES
Work Type WIDEN ROADWAY FOR SAFETY
 
11.362 6170063.74 529604.00 529604.00 8.5
Work Order 07-16-15
Work Began 00-00-00
Work Completed  
Time Computed 04-15-16
Contract Working Days 114
Addl Days Granted 0
Working Days Charged 14
Percent Time Used 12
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0794-01-018
BARRICADES UNLIMITED (0.73%)
LANCO TURF & SEEDING, INC. (0.30%)
COWBELL TRAFFIC SERVICES, INC. (0.40%)
HJC FARMS, INC.(1.37%)
E. DIAZ TRUCKING (2.28%)
Contract # 06153218
Totals 6170063.74 529604.00 529604.00 8.5

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To (ON SYSTEM)
CSJ 0904-00-154
Proj ID STP 2013(085)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2916208.80 0.00 2254834.69 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-04-12
Work Began 01-08-13
Work Completed 10-27-14
Time Computed 12-20-12
Contract Working Days 206
Addl Days Granted 2
Working Days Charged 208
Percent Time Used 100
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-154
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(6.11%)
CLASSIC TEJAS CONSTRUCTION, INC. ( 14.49%)
Contract # 10123029
Totals 2916208.80 0.00 2254834.69 100.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-155
Proj ID STP 2015(588)
Work Type THERMOPLASTIC STRIPING
 
0.001 2103735.09 8408.54 1914709.49 91.0
Work Order 03-13-15
Work Began 06-16-15
Work Completed  
Time Computed 06-16-15
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 71
Percent Time Used 100
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153017
Totals 2103735.09 8408.54 1914709.49 91.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-156
Proj ID STP 2015(056)
Work Type CRACK SEAL
 
282.864 646972.39 0.00 634627.32 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-28-14
Work Began 11-17-14
Work Completed 04-06-15
Time Computed 11-10-14
Contract Working Days 71
Addl Days Granted 11
Working Days Charged 95
Percent Time Used 115
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-156
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09143033
Totals 646972.39 0.00 634627.32 100.0

page 1 | page 2 | page 3 | page 4