Monthly State Let Construction Report For Amarillo District As Of May 15, 2013 Page 1 Of 2

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyOCHILTREE
Highway US 83
From 6TH AVE
To 13TH AVE
CSJ 0030-02-042
Proj ID STP 2011(262)TE
Work Type PERRYTON MAIN ST ENHANCEMENT II
 
0.494 1347836.50 2258.72 760080.58 56.3
Work Order 04-26-12
Work Began 05-14-12
Work Completed  
Time Computed 05-12-12
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 144
Percent Time Used 96
Contractor(s)
B&B SOLVENT, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-042
B & G ELECTRIC ( 55.08%)
Contract # 02123231
Totals 1347836.50 2258.72 760080.58 56.3

CountyOCHILTREE
Highway US 83 ETC
From SH 15
To 1 MILE SOUTH OF LP 143
CSJ 0030-02-043
Proj ID STP 2013(084)
Work Type SEAL COAT
 
347.995 10212987.82 395372.85 1475781.84 14.4
Work Order 11-14-12
Work Began 00-00-00
Work Completed  
Time Computed 05-15-13
Contract Working Days 76
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-02-043
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10123204
Totals 10212987.82 395372.85 1475781.84 14.4

CountyOCHILTREE
Highway US 83
From WOLF CREEK BRIDGE
To 1.4 MILES N OF NORTHUP CREEK
CSJ 0030-03-023
Proj ID STP 2011(209)ES
Work Type REHABILITATE EXISTING ROADWAY
 
6.535 5839756.54 50828.24 5471688.41 97.6
Work Order 12-06-10
Work Began 01-25-11
Work Completed  
Time Computed 12-22-10
Contract Working Days 259
Addl Days Granted 0
Working Days Charged 471
Percent Time Used 181
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0030-03-023
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(1.70%)
CUTRELL TRUCKING COMPANY, INC. (4.54%)
JONA CONTRACTING, INC. (0.74%)
TEXAS ALTERNATIVE GRASSER, INC.(0.86%)
G. B. & G TRANSPORT, LLP (1.38%)
E. DIAZ TRUCKING (0.00%)
Contract # 10103004
Totals 5839756.54 50828.24 5471688.41 97.6

CountyOCHILTREE
Highway US 83
From 1.4 MILES N OF NORTHUP CREEK
To LIPSCOMB COUNTY LINE
CSJ 0030-03-025
Proj ID STP 1102(341)
Work Type REHABILITATE EXISTING ROADWAY
 
11.232 11848782.75 436431.49 5826869.95 50.1
Work Order 08-19-11
Work Began 09-06-11
Work Completed  
Time Computed 09-04-11
Contract Working Days 300
Addl Days Granted 0
Working Days Charged 384
Percent Time Used 128
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0030-03-025
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(1.96%)
CUTRELL TRUCKING COMPANY, INC. (3.86%)
G. B. & G TRANSPORT, LLP (3.78%)
J. V. CONSTRUCTION (2.53%)
TEXAS ALTERNATIVE GRASSER, INC.(0.97%)
COLORADO DOUBLE D CONSTRUCTION LLC (1.25%)
E. DIAZ TRUCKING (0.00%)
Contract # 06113248
Totals 11848782.75 436431.49 5826869.95 50.1

CountyHEMPHILL
Highway US 83
From LIPSCOMB COUNTY LINE
To HORSE CREEK
CSJ 0030-05-062
Proj ID STP 2013(003)
Work Type REHAB EXISTING RDWY
 
6.267 4019598.98 238045.25 270169.25 6.7
Work Order 11-09-12
Work Began 00-00-00
Work Completed  
Time Computed 11-25-12
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 25
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0030-05-062
KOSS CONSTRUCTION COMPANY( 24.72%)
O. TREVINO CONSTRUCTION, LLC (5.11%)
AMARILLO RMT ENTERPRISE(0.54%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(2.57%)
Contract # 09123220
Totals 4019598.98 238045.25 270169.25 6.7

CountyHEMPHILL
Highway US 83
From 1.66 MILES SOUTH OF FM 277
To WHEELER COUNTY LINE
CSJ 0030-07-017
Proj ID STP 2013(236)
Work Type REHAB EXISTING ROADWAY
 
3.671 1972769.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-06-13
Work Began 00-00-00
Work Completed  
Time Computed 03-22-13
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0030-07-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12123020
Totals 1972769.95 0.00 0.00 0.0

CountyPOTTER
Highway US 87
From AT LP 335 (ST FRANCIS AVE)
To .
CSJ 0041-07-097
Proj ID BR 2012(362)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.126 2245899.16 232864.90 2000466.78 89.0
CountyPOTTER
Highway US 87
From AT WILLOW CREEK DR
To .
CSJ 0041-07-098
Proj ID BR 2012(362)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.099 1135322.53 2407.00 105183.98 9.2
CountyPOTTER
Highway US 87
From AT CHERRY AVE
To .
CSJ 0041-07-099
Proj ID BR 2012(362)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.102 1164718.11 121452.01 1178129.20 99.9
CountyPOTTER
Highway US 87
From AT FM 1719
To .
CSJ 0041-07-101
Proj ID BR 2012(362)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.093 1115502.85 46468.95 431822.57 38.7
Work Order 04-17-12
Work Began 06-04-12
Work Completed  
Time Computed 05-03-12
Contract Working Days 556
Addl Days Granted 0
Working Days Charged 227
Percent Time Used 40
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-097
HOLMES CONSTRUCTION CO., L.P.(7.77%)
HOUSTON SAWING & DRILLING(0.19%)
LANCO TURF & SEEDING, INC. (0.08%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.80%)
RAY ELECTRIC COMPANY (0.15%)
SCOTT DERR PAINTING CO (0.62%)
SHINN & GREGORY, INC.(1.50%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(1.57%)
DUSTIN ALLEN, INC. (2.49%)
Contract # 03123209
Totals 5661442.65 403192.86 3715602.53 65.6

CountyPOTTER
Highway US 87
From AT MOBLEY AVE
To .
CSJ 0041-07-100
Proj ID BR 2013(374)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.001 1688123.28 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-19-13
Work Began 00-00-00
Work Completed  
Time Computed 05-05-13
Contract Working Days 86
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0041-07-100
HIGHWAY TECHNOLOGIES, INC. (0.58%)
L. A. FULLER & SONS CONSTRUCTION, LTD. (3.06%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.13%)
SCOTT DERR PAINTING CO (0.41%)
VANN/ELLI, INC.(7.15%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(0.57%)
Contract # 02133224
Totals 1688123.28 0.00 0.00 0.0

CountyARMSTRONG
Highway US 287
From 0.3 MI WEST OF CLAUDE CITY LIMITS
To 0.037 MI EAST OF TRICE ST
CSJ 0042-03-040
Proj ID NH 2012(544)
Work Type REHAB EXISTING ROADWAY
 
1.461 6066806.51 163774.53 2554372.98 42.1
CountyARMSTRONG
Highway US 287
From 0.037 MI EAST OF TRICE ST
To 0.146 MI EAST OF FM 1151
CSJ 0042-04-039
Proj ID NH 2012(544)
Work Type REHAB EXISTING ROADWAY
 
1.179 3713109.66 178612.29 1299671.56 35.0
Work Order 07-03-12
Work Began 08-02-12
Work Completed  
Time Computed 07-19-12
Contract Working Days 386
Addl Days Granted 0
Working Days Charged 184
Percent Time Used 47
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-03-040
ALAMO BROTHERS CONCRETE(7.64%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(2.45%)
DUSTROL, INC.(0.05%)
WILLIS ELECTRIC CO., LP(0.53%)
TEX OP CONSTRUCTION, LP(1.53%)
Contract # 05123203
Totals 9779916.17 342386.82 3854044.54 39.4

CountyRANDALL
Highway US 87
From SPUR 48 (RUSSELL LONG BLVD)
To 300 FT NORTH OF RR UNDERPASS
CSJ 0067-01-077
Proj ID STP 2011(263)TE
Work Type CANYON US 87 GATEWAY ENHANCEMENT
 
0.145 837902.85 637.50 830726.76 99.0
CountyRANDALL
Highway US 87
From SPUR 48 (RUSSELL LONG BLVD)
To 300 FT NORTH OF RR UNDERPASS
CSJ 0067-01-078
Proj ID NH 1102(298)
Work Type IMPROVE INTERSECTION AND DRAINAGE
 
0.145 118627.40 0.00 136148.00 99.9
Work Order 09-30-11
Work Began 11-15-11
Work Completed  
Time Computed 10-16-11
Contract Working Days 110
Addl Days Granted 82
Working Days Charged 195
Percent Time Used 101
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0067-01-077
A-1 SERVICES (0.08%)
ALAMO BROTHERS CONCRETE( 18.43%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(1.95%)
RAY ELECTRIC COMPANY (8.03%)
CONCRETE PAVER SYSTEMS, INC. ( 18.41%)
SECRET GARDENER( 14.39%)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC(2.02%)
Contract # 08113216
Totals 956530.25 637.50 966874.76 99.9

CountyDEAF SMITH
Highway US 60
From RANDALL COUNTY LINE
To HEREFORD CITY LIMITS
CSJ 0168-07-042
Proj ID NH 2013(311)
Work Type REHAB EXISTING RDWY WB LANES
 
13.103 3419940.93 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-15-13
Work Began 00-00-00
Work Completed  
Time Computed 03-31-13
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-07-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133217
Totals 3419940.93 0.00 0.00 0.0

CountyRANDALL
Highway US 60
From AT US 87 & US 60 CONNECTOR IN CANYO
To .
CSJ 0168-08-062
Proj ID BR 2012(477)
Work Type REPLACE BRIDGE & APPROACHES
 
0.098 1009919.88 1524.51 1178087.77 99.9
Work Order 06-21-12
Work Began 08-28-12
Work Completed  
Time Computed 07-07-12
Contract Working Days 75
Addl Days Granted 19
Working Days Charged 86
Percent Time Used 91
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0168-08-062
ATS DRILLING, INC. (8.41%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(1.07%)
J.L. STEEL REINFORCING, LLC(0.89%)
SCOTT DERR PAINTING CO, LLC(0.08%)
DUSTROL, INC.(1.40%)
HJC FARMS, INC.(2.39%)
HOLMES CONSTRUCTION CO., L.P.(9.34%)
HOUSTON SAWING & DRILLING(0.18%)
TEXAS ALTERNATIVE GRASSER, INC.(0.96%)
S & S BRIDGE PAINTING, INC.(1.40%)
Contract # 05123242
Totals 1009919.88 1524.51 1178087.77 99.9

CountyRANDALL
Highway US 60
From DEAF SMITH COUNTY LINE
To US 87
CSJ 0168-08-068
Proj ID NH 2013(088)
Work Type OVERLAY
 
14.789 7931426.33 443516.50 477116.50 6.0
Work Order 01-03-13
Work Began 00-00-00
Work Completed  
Time Computed 01-19-13
Contract Working Days 220
Addl Days Granted 0
Working Days Charged 72
Percent Time Used 32
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0168-08-068
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10123227
Totals 7931426.33 443516.50 477116.50 6.0

CountyDALLAM
Highway US 54
From DALHART CURB & GUTTER
To CHAMBERLIN
CSJ 0238-03-052
Proj ID C 238-3-52
Work Type REHAB EXIST RDWY & ADD PASSING LNS
 
23.304 6417952.72 178732.95 2273813.10 35.4
Work Order 08-20-12
Work Began 09-10-12
Work Completed  
Time Computed 09-05-12
Contract Working Days 172
Addl Days Granted 0
Working Days Charged 159
Percent Time Used 92
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-03-052
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(2.67%)
DUSTROL, INC.(0.34%)
Contract # 06123007
Totals 6417952.72 178732.95 2273813.10 35.4

CountySHERMAN
Highway US 54
From COUNTY ROAD G
To OKLAHOMA STATE LINE
CSJ 0238-06-026
Proj ID NH 1102(367)
Work Type REHAB EXISTING RDWY & PASSING LANES
 
9.953 3252696.71 0.00 3199800.07 99.9
Work Order 08-15-11
Work Began 09-19-11
Work Completed  
Time Computed 08-31-11
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 193
Percent Time Used 175
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0238-06-026
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(2.00%)
HOLMES CONSTRUCTION CO., L.P.(6.96%)
DUSTROL, INC.(4.25%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.27%)
LANCO TURF & SEEDING, INC. (0.10%)
Contract # 07113066
Totals 3252696.71 0.00 3199800.07 99.9

CountyCARSON
Highway IH 40
From 3.0 MI EAST OF POTTER CO. LINE
To 3.7 MI WEST OF CONWAY
CSJ 0275-02-069
Proj ID IM 0401(208)
Work Type REHAB EXISTING ROADWAY
 
7.759 5177809.06 0.00 28877.40 0.5
Work Order 01-15-13
Work Began 00-00-00
Work Completed  
Time Computed 01-31-13
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 14
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-02-069
AMARILLO RMT ENTERPRISE(0.78%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.05%)
O. TREVINO CONSTRUCTION, LLC (7.18%)
TEX OP CONSTRUCTION, LP(1.36%)
WEST TEXAS RUMBLE STRIP(0.11%)
Contract # 11123206
Totals 5177809.06 0.00 28877.40 0.5

CountyCARSON
Highway IH 40
From 2.0 MILES WEST OF GROOM
To GRAY COUNTY LINE
CSJ 0275-04-048
Proj ID IM 0401(206)
Work Type REHAB EXISTING ROADWAY
 
4.297 3773636.82 10431.00 3810621.05 99.9
CountyGRAY
Highway IH 40
From CARSON COUNTY LINE
To 2.0 MILES EAST OF GROOM
CSJ 0275-05-042
Proj ID IM 0401(206)
Work Type REHAB EXISTING ROADWAY
 
1.258 973863.80 0.00 1218770.24 99.9
Work Order 04-17-12
Work Began 04-19-12
Work Completed  
Time Computed 05-03-12
Contract Working Days 256
Addl Days Granted 0
Working Days Charged 229
Percent Time Used 89
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0275-04-048
WINDING ROAD CONSTRUCTION, INC.( 30.42%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(1.75%)
DUSTROL, INC.(0.57%)
RAY ELECTRIC COMPANY (0.30%)
TEXAS ALTERNATIVE GRASSER, INC.(0.38%)
INTERSTATE IMPROVEMENT, INC. (1.76%)
RPV CONSTRUCTION (1.63%)
Contract # 03123004
Totals 4747500.62 10431.00 5029391.29 99.9

CountyOCHILTREE
Highway SH 15
From US 83
To LIPSCOMB COUNTY LINE
CSJ 0355-03-028
Proj ID STP 2013(442)
Work Type OVERLAY
 
15.205 3838624.15 0.00 0.00 0.0
CountyOCHILTREE
Highway SH 15
From PERRYTON C&G
To LIPSCOMB COUNTY LINE
CSJ 0355-03-029
Proj ID STP 2013(442)
Work Type OVERLAY
 
14.665 1443103.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0355-03-028
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133013
Totals 5281728.05 0.00 0.00 0.0

CountyHUTCHINSON
Highway SH 136
From AT ROCK CREEK
To .
CSJ 0356-01-091
Proj ID BR 2013(375)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.151 2716537.03 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-06-13
Work Began 00-00-00
Work Completed  
Time Computed 05-22-13
Contract Working Days 241
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0356-01-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133215
Totals 2716537.03 0.00 0.00 0.0

CountyHARTLEY
Highway US 87
From EAST OF US 385 INTERCHANGE
To MOORE COUNTY LINE
CSJ 0425-01-019
Proj ID C 425-1-19
Work Type REHAB EXISTING RDWY & PASSING LANES
 
22.251 21250815.26 32942.15 1799602.58 8.4
Work Order 10-24-12
Work Began 11-19-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 370
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 28
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0425-01-019
HIGHWAY TECHNOLOGIES, INC. (0.28%)
TEXAS ALTERNATIVE GRASSER, INC.(0.02%)
DUSTROL, INC.(1.94%)
HOLMES CONSTRUCTION CO., L.P.( 10.19%)
HJC FARMS, INC.(0.95%)
BALLOU PAVEMENT SOLUTIONS INC. ( 14.78%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(1.34%)
BRUSH EATERS, INC. (0.12%)
KOSS CONSTRUCTION COMPANY( 14.78%)
Contract # 08123002
Totals 21250815.26 32942.15 1799602.58 8.4