Monthly State Let Construction Report For Amarillo District As Of May 15, 2013 Page 2 Of 2

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-144
Proj ID STP 2013(376)
Work Type THERMOPLASTIC STRIPING
 
0.100 1074590.66 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-23-13
Work Began 00-00-00
Work Completed  
Time Computed 05-14-13
Contract Working Days 54
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-144
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133025
Totals 1074590.66 0.00 0.00 0.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS IN AMARILLO
To (ON SYSTEM)
CSJ 0904-00-148
Proj ID STP 2012(052)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2062945.48 72108.10 1261150.27 65.0
Work Order 01-03-12
Work Began 01-23-12
Work Completed  
Time Computed 01-19-12
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 277
Percent Time Used 158
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-148
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(5.28%)
RAY ELECTRIC COMPANY (7.14%)
SECRET GARDENER(0.00%)
SPEEDY PAVING(2.25%)
Contract # 10113013
Totals 2062945.48 72108.10 1261150.27 65.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-149
Proj ID STP 2012(092)
Work Type CRACK SEAL
 
195.587 651808.43 0.00 616085.35 97.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-05-11
Work Began 01-10-12
Work Completed  
Time Computed 01-02-12
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 93
Percent Time Used 143
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-149
TEXAS BARRICADE & SIGNS, INC.(2.53%)
Contract # 11113014
Totals 651808.43 0.00 616085.35 97.1

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To (ON SYSTEM)
CSJ 0904-00-154
Proj ID STP 2013(085)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2916208.80 158906.79 930735.56 31.9
Work Order 12-04-12
Work Began 01-08-13
Work Completed  
Time Computed 12-20-12
Contract Working Days 206
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 38
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-154
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(6.11%)
CLASSIC TEJAS CONSTRUCTION, INC. ( 14.48%)
Contract # 10123029
Totals 2916208.80 158906.79 930735.56 31.9

CountyPOTTER
Highway VA
From ON GRAND ST AND SE 3RD AVE
To AT BNSF RR
CSJ 0904-02-035
Proj ID STP 2010(401)ES
Work Type CONSTRUCT RR OVERPASS
 
0.442 5073269.94 103589.25 4758518.42 95.5
Work Order 05-26-10
Work Began 07-27-10
Work Completed  
Time Computed 06-11-10
Contract Working Days 400
Addl Days Granted 26
Working Days Charged 505
Percent Time Used 118
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-02-035
HIGHWAY TECHNOLOGIES, INC. (0.38%)
J.V. CONCRETE CONSTRUCTION (2.80%)
J & M ELECTRIC (1.66%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.44%)
SITESAFE PRODUCTS TEXAS(0.69%)
SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.22%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.51%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.15%)
DUSTROL, INC. (ROANOKE)(0.49%)
NORTH TEXAS REBAR, LLC (0.19%)
T-BAR FENCE, INC.(1.12%)
ARTEX ELECTRIC, INC. (1.04%)
HJC FARMS, INC.(0.47%)
WEBBER BARRIER SERVICES, INC.(1.42%)
HOLMES CONSTRUCTION CO., L.P.(0.29%)
PRIMATE CONSTRUCTION, INC. (0.48%)
SOUTHEAST GRINDING & GROOVING, LLC (0.58%)
L. A. FULLER & SONS CONSTRUCTION, LTD. (0.08%)
Contract # 04103005
Totals 5073269.94 103589.25 4758518.42 95.5

CountyHEMPHILL
Highway CR
From ON CR 20 AND GAGEBY CREEK
To .
CSJ 0904-03-012
Proj ID BR 2011(439)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.060 386684.00 30740.00 335717.00 93.0
CountyHEMPHILL
Highway CR
From AT CR EE & DRAW CREEK
To .
CSJ 0904-03-016
Proj ID BR 2011(435)
Work Type REPLACE BRIDGE & APPR
 
0.130 581809.50 0.00 574715.50 98.7
CountyROBERTS
Highway CR
From AT NO NAME CREEK
To .
CSJ 0904-10-002
Proj ID BR 2011(675)
Work Type REPLACE BRIDGE & APPROACHES
 
0.028 279183.00 67815.00 253340.32 90.7
Work Order 06-18-12
Work Began 08-13-12
Work Completed  
Time Computed 07-04-12
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 163
Percent Time Used 127
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-03-012
HIGHWAY TECHNOLOGIES, INC. (0.47%)
LANCO TURF & SEEDING, INC. (2.39%)
Contract # 05123029
Totals 1247676.50 98555.00 1163772.82 95.1

CountyARMSTRONG
Highway VA
From US 287 AT GOODNIGHT TEXAS
To .
CSJ 0904-06-009
Proj ID STP 2011(261)TE
Work Type CONSTRUCTION OF VISITOR'S CENTER
 
0.001 615000.00 18450.00 645473.00 99.9
Work Order 09-17-12
Work Began 10-01-12
Work Completed  
Time Computed 10-03-12
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 86
Contractor(s)
PIONEER GENERAL CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-06-009
HOLMES CONSTRUCTION CO., L.P.(0.00%)
Contract # 08123212
Totals 615000.00 18450.00 645473.00 99.9

CountyHUTCHINSON
Highway CR
From PLEMONS RD & CANADIAN RIVER PLEMONS
To .
CSJ 0904-07-011
Proj ID BR 2008(471)
Work Type REPLACE BRIDGE & APPROACHES
 
0.679 3192061.68 0.00 3166191.49 99.1
Work Order 09-06-11
Work Began 10-03-11
Work Completed  
Time Computed 09-22-11
Contract Working Days 325
Addl Days Granted 0
Working Days Charged 287
Percent Time Used 88
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-07-011
WESTERN FENCE CO.(1.39%)
S & S BRIDGE PAINTING, INC.(0.28%)
HOUSTON SAWING & DRILLING(0.37%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(0.32%)
WEBBER-BALKE FOUNDATION COMPANY, INC.(9.38%)
AMARILLO RMT ENTERPRISE(0.29%)
Contract # 08113029
Totals 3192061.68 0.00 3166191.49 99.1

CountyRANDALL
Highway PW
From IN PALO DURO CANYON STATE PARK
To .
CSJ 0904-11-049
Proj ID C 904-11-49
Work Type CONSTRUCT NEW CAMP LOOP AND PARKING
 
0.001 394526.70 0.00 239437.52 61.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-21-12
Work Began 11-05-12
Work Completed  
Time Computed 10-21-12
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 63
Percent Time Used 105
Contractor(s)
HOLMES CONSTRUCTION CO., L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-11-049
HIGHWAY TECHNOLOGIES, INC. (0.31%)
ALAMO BROTHERS CONCRETE(7.37%)
EWING CABLE(1.52%)
BRUSH EATERS, INC. (1.90%)
WEST TEXAS UTILITY CONTRACTORS, INC. (0.45%)
TEXAS ALTERNATIVE GRASSER, INC.(1.20%)
Contract # 07123024
Totals 394526.70 0.00 239437.52 61.1

CountyRANDALL
Highway CS
From ON FARMERS AVE, FROM WESTERN ST
To GEORGIA ST
CSJ 0904-11-053
Proj ID STP 2013(143)
Work Type REHAB EXISTING ROADWAY
 
0.996 1400000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-04-13
Work Began 00-00-00
Work Completed  
Time Computed 05-06-13
Contract Working Days 83
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-11-053
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11123019
Totals 1400000.00 0.00 0.00 0.0

CountyLIPSCOMB
Highway SH 23
From FM 377
To 11.05 MI N OF US 83
CSJ 1337-01-022
Proj ID C 1337-1-22
Work Type REHAB & WIDEN EXISTING RDWY
 
10.063 5502012.06 64700.42 455112.98 8.2
Work Order 11-19-12
Work Began 01-09-13
Work Completed  
Time Computed 12-05-12
Contract Working Days 250
Addl Days Granted 0
Working Days Charged 73
Percent Time Used 29
Contractor(s)
MITCHELL ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1337-01-022
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.68%)
HJC FARMS, INC.(1.81%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.18%)
B&B SOLVENT, LTD.( 42.44%)
Contract # 07123220
Totals 5502012.06 64700.42 455112.98 8.2

CountyLIPSCOMB
Highway SH 23
From 11.05 MI N OF US 83
To US 83
CSJ 1337-02-010
Proj ID STP 2013(086)
Work Type REHAB & WIDEN EXISTING RDWY
 
11.050 6406551.08 312550.77 906503.58 14.1
Work Order 01-03-13
Work Began 01-07-13
Work Completed  
Time Computed 01-19-13
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1337-02-010
AMARILLO RMT ENTERPRISE(2.63%)
CUTRELL TRUCKING COMPANY, INC. (3.97%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.80%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(2.04%)
Contract # 10123014
Totals 6406551.08 312550.77 906503.58 14.1

CountyDALLAM
Highway SS 17
From US 87
To US 385
CSJ 1702-03-001
Proj ID STP 2011(992)
Work Type NEW LOCATION 2 LANE RDWY
 
1.866 1621574.25 0.00 1669784.29 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-14-11
Work Began 02-06-12
Work Completed  
Time Computed 02-28-12
Contract Working Days 150
Addl Days Granted 17
Working Days Charged 174
Percent Time Used 104
Contractor(s)
HOLMES CONSTRUCTION CO., L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1702-03-001
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(3.37%)
SECRET GARDENER(0.94%)
Contract # 05113008
Totals 1621574.25 0.00 1669784.29 99.9

CountyPOTTER
Highway LP 335
From HESTER ROAD
To NORTH COULTER ST
CSJ 2635-04-025
Proj ID STP 2012(139)
Work Type CONSTRUCT FUTURE I / C CONNECTORS
 
0.846 4172496.27 174043.45 3679445.25 88.1
Work Order 01-11-12
Work Began 01-16-12
Work Completed  
Time Computed 01-27-12
Contract Working Days 337
Addl Days Granted 0
Working Days Charged 294
Percent Time Used 87
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2635-04-025
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(0.34%)
L. A. FULLER & SONS CONSTRUCTION, LTD. ( 24.63%)
NORTH TEXAS REBAR, LLC (0.75%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.01%)
NORTH TEXAS REBAR, LLC (0.22%)
ALAMO BROTHERS CONCRETE(2.85%)
RAY ELECTRIC COMPANY (0.40%)
AMARILLO RMT ENTERPRISE(0.37%)
FARR FOUNDATION, INC.(4.29%)
TEXAS ALTERNATIVE GRASSER, INC.(0.47%)
SCOTT DERR PAINTING CO, LLC(0.31%)
Contract # 12113023
Totals 4172496.27 174043.45 3679445.25 88.1

page 1 | page 2