Monthly State Let Construction Report For Amarillo District As Of Sep 15, 2016 Page 2 Of 2

Last Update: Thursday, September 15, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHANSFORD
Highway SH 15
From SH 136 IN GURVER
To SH 207 IN SPEARMAN
CSJ 0308-02-029
Proj ID STP 1602(139)
Work Type RESTORATION OF EXISTING ROADWAY
 
19.900 9135715.42 0.00 53625.00 0.5
Work Order 07-28-16
Work Began 00-00-00
Work Completed  
Time Computed 08-26-16
Contract Working Days 210
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0308-02-029
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163030
Totals 9135715.42 0.00 53625.00 0.5

CountyLIPSCOMB
Highway SH 15
From FM 2172 IN DARROUZETT
To FM 1455
CSJ 0355-01-047
Proj ID STP 2015(639)
Work Type OVERLAY
 
6.099 1996781.26 0.00 2019106.50 99.9
CountyLIPSCOMB
Highway SH 15
From OCHILTREE COUNTY LINE
To FM 2172 IN DARROUZETT
CSJ 0355-02-030
Proj ID STP 2015(639)
Work Type OVERLAY
 
12.620 2960757.17 0.00 3031568.18 99.9
CountyOCHILTREE
Highway SH 15
From HANSFORD COUNTY LINE
To US 83 IN PERRYTON
CSJ 0355-04-039
Proj ID STP 2015(587)
Work Type RESTORATION OF EXISTING ROADWAY
 
18.117 8770353.11 0.00 8703031.35 99.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-06-15
Work Began 06-02-15
Work Completed  
Time Computed 06-01-15
Contract Working Days 122
Addl Days Granted 5
Working Days Charged 120
Percent Time Used 94
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0355-04-039
BARRICADES UNLIMITED (1.57%)
DUSTROL, INC.(0.60%)
HJC FARMS, INC.(0.90%)
O. TREVINO CONSTRUCTION, LLC (0.79%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.09%)
TEXAS ALTERNATIVE GRASSER, INC.(0.09%)
J C DIAZ TRUCKING(0.00%)
Contract # 01153026
Totals 13727891.54 0.00 13753706.03 99.9

CountyLIPSCOMB
Highway SH 15
From FM 1455
To OKLAHOMA STATE LINE
CSJ 0355-01-048
Proj ID STP 1602(191)
Work Type OVERLAY
 
12.362 4980635.65 0.00 0.00 0.0
CountyLIPSCOMB
Highway SH 15
From OCHILTREE COUNTY LINE
To 1000' EAST OF COUNTY ROAD 4
CSJ 0355-02-031
Proj ID STP 1602(191)
Work Type OVERLAY
 
3.118 986876.40 0.00 0.00 0.0
CountyLIPSCOMB
Highway SH 23
From FM 377
To 11.05 MILES NORTH OF US 83
CSJ 1337-01-023
Proj ID STP 1602(191)
Work Type OVERLAY
 
10.063 2183107.75 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-05-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 77
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0355-01-048
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06163023
Totals 8150619.80 0.00 0.00 0.0

CountyCARSON
Highway SH 207
From FM 293
To HUTCHINSON COUNTY LINE
CSJ 0356-02-043
Proj ID STP 2014(866)
Work Type RESTORATION OF EXISTING ROADWAY
 
19.102 8607481.82 129943.30 8626061.01 99.9
Work Order 09-30-14
Work Began 10-22-14
Work Completed  
Time Computed 10-16-14
Contract Working Days 110
Addl Days Granted 9
Working Days Charged 145
Percent Time Used 121
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0356-02-043
BARRICADES UNLIMITED (1.16%)
E. DIAZ TRUCKING (4.32%)
DUSTROL, INC.(1.37%)
RICE ENVIRONMENTAL SERVICES(1.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.77%)
WEST TEXAS RUMBLE STRIP(0.32%)
Contract # 07143211
Totals 8607481.82 129943.30 8626061.01 99.9

CountyGRAY
Highway SH 152
From US 60
To WHEELER COUNTY LINE
CSJ 0397-01-043
Proj ID STP 2015(472)
Work Type OVERLAY
 
17.735 6779225.71 175897.01 6556993.70 97.1
Work Order 02-11-15
Work Began 09-22-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 151
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0397-01-043
BARRICADES UNLIMITED (1.88%)
DUSTROL, INC.(0.41%)
HJC FARMS, INC.(4.71%)
Contract # 01153208
Totals 6779225.71 175897.01 6556993.70 97.1

CountyROBERTS
Highway SH 70
From NORTH CANADIAN RIVER BRIDGE
To OCHILTREE COUNTY LINE
CSJ 0490-04-037
Proj ID STP 2014(579)
Work Type REHABILITATE EXISTING ROADWAY
 
5.848 5139086.58 95027.41 4684906.07 92.5
Work Order 06-18-14
Work Began 12-10-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 197
Addl Days Granted 27
Working Days Charged 289
Percent Time Used 129
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
BARRICADES UNLIMITED (0.99%)
HJC FARMS, INC.(3.77%)
HUDSON, INC. (0.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.84%)
WEST TEXAS RUMBLE STRIP(0.08%)
W.S. CONSTRUCTION COMPANY(5.84%)
E. DIAZ TRUCKING (2.85%)
Contract # 04143003
Totals 5139086.58 95027.41 4684906.07 92.5

CountyRANDALL
Highway PR 5
From AT WATER CROSSINGS 3,4 AND 5
To WITHIN PALO DURO CANYON STATE PARK
CSJ 0534-01-020
Proj ID C 534-1-20
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.385 3768710.10 1770.00 3811123.70 99.9
Work Order 05-15-15
Work Began 06-08-15
Work Completed  
Time Computed 05-31-15
Contract Working Days 230
Addl Days Granted 10
Working Days Charged 235
Percent Time Used 97
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-020
ALTUS TRAFFIC MANAGEMENT LLC (1.58%)
WOLFE CONSTRUCTION GROUP, INC. (0.56%)
HUDSON, INC. (0.48%)
AMARILLO RMT ENTERPRISES, LLC(1.81%)
LONE STAR CONSTRUCTION (3.84%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.49%)
MCL CONTRACTING, LLC (0.26%)
L. A. FULLER & SONS CONSTRUCTION, LTD. (4.38%)
GSI HIGHWAY PRODUCTS (1.86%)
Contract # 04153034
Totals 3768710.10 1770.00 3811123.70 99.9

CountyMOORE
Highway SH 152
From DUMAS CITY LIMITS
To HUTCHINSON COUNTY LINE
CSJ 0557-01-028
Proj ID STP 2016(683)
Work Type RESTORATION
 
47.263 15561610.53 1767352.87 3611176.17 23.2
Work Order 05-24-16
Work Began 07-06-16
Work Completed  
Time Computed 06-23-16
Contract Working Days 130
Addl Days Granted 20
Working Days Charged 43
Percent Time Used 28
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0557-01-028
BARRICADES UNLIMITED (0.84%)
DUSTROL, INC.(2.04%)
W.S. CONSTRUCTION COMPANY(1.58%)
CF TRUCKING, LLC (1.46%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.11%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.15%)
HJC FARMS, INC.(0.21%)
Contract # 02163003
Totals 15561610.53 1767352.87 3611176.17 23.2

CountyDALLAM
Highway FM 1727
From FM 3310
To 7 MI WEST OF FM 3489
CSJ 0794-01-018
Proj ID STP 1502(296)HES
Work Type WIDEN ROADWAY FOR SAFETY
 
11.362 6170063.74 259388.10 2471684.75 40.3
Work Order 07-16-15
Work Began 02-24-16
Work Completed  
Time Computed 01-11-16
Contract Working Days 114
Addl Days Granted 8
Working Days Charged 139
Percent Time Used 113
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0794-01-018
BARRICADES UNLIMITED (0.73%)
LANCO TURF & SEEDING, INC. (0.30%)
COWBELL TRAFFIC SERVICES, INC. (0.40%)
HJC FARMS, INC.(1.37%)
E. DIAZ TRUCKING (2.28%)
Contract # 06153218
Totals 6170063.74 259388.10 2471684.75 40.3

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-155
Proj ID STP 2015(588)
Work Type THERMOPLASTIC STRIPING
 
0.001 2103735.09 0.00 1933309.49 91.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-13-15
Work Began 06-16-15
Work Completed  
Time Computed 06-16-15
Contract Working Days 71
Addl Days Granted 0
Working Days Charged 71
Percent Time Used 100
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-155
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02153017
Totals 2103735.09 0.00 1933309.49 91.8

CountyPOTTER
Highway VA
From AT VARIOUS LOCATIONS IN AMARILLO
To .
CSJ 0904-00-160
Proj ID STP 2015(649)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2895601.55 152861.12 2433331.80 84.2
Work Order 05-08-15
Work Began 07-06-15
Work Completed  
Time Computed 05-24-15
Contract Working Days 274
Addl Days Granted 0
Working Days Charged 281
Percent Time Used 102
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-160
ONE WAY CONCRETE ( 56.56%)
BTA SERVICES, LTD. (1.91%)
W.A. ROBBINS CONSTRUCTION CO., INC.(6.35%)
QLVS, INC. DBA PHASE 3 ELECTRIC(1.30%)
Contract # 03153026
Totals 2895601.55 152861.12 2433331.80 84.2

CountyPOTTER
Highway VA
From AT VARIOUS LOCATIONS IN AMA DISTRIC
To .
CSJ 0904-00-161
Proj ID STP 2016(150)
Work Type CONSTUCT CURB RAMPS
 
0.001 1946236.07 187947.20 1536095.45 78.9
Work Order 12-10-15
Work Began 02-24-16
Work Completed  
Time Computed 12-11-15
Contract Working Days 210
Addl Days Granted 3
Working Days Charged 114
Percent Time Used 53
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-161
CLASSIC TEJAS CONSTRUCTION, INC. (5.30%)
BARRICADES UNLIMITED (8.52%)
Contract # 10153022
Totals 1946236.07 187947.20 1536095.45 78.9

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-162
Proj ID STP 2017(002)
Work Type CRACK SEAL
 
172.430 369998.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-162
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09163009
Totals 369998.68 0.00 0.00 0.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS
To DISTRICTWIDE
CSJ 0904-00-168
Proj ID NH 2016(013)
Work Type ITS MAINTENANCE
 
0.100 225675.00 0.00 224175.00 99.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-15
Work Began 05-03-16
Work Completed  
Time Computed 11-02-15
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 35
Contractor(s)
MICA CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-168
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153225
Totals 225675.00 0.00 224175.00 99.3

CountyPOTTER
Highway CR
From ON DEWEY AVE AT WEST AMARILLO CREEK
To .
CSJ 0904-02-037
Proj ID BR 2014(554)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.041 1220116.75 181065.84 429701.64 35.2
Work Order 06-22-16
Work Began 06-28-16
Work Completed  
Time Computed 06-28-16
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 37
Percent Time Used 66
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-02-037
BARRICADES UNLIMITED (0.31%)
L. A. FULLER & SONS CONSTRUCTION, LTD. (1.87%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 13.83%)
SOUTH TEXAS PAINTING COMPANY (0.62%)
WOLFE CONSTRUCTION GROUP, INC. (0.27%)
MCL CONTRACTING, LLC (0.77%)
Contract # 04163235
Totals 1220116.75 181065.84 429701.64 35.2

CountyHEMPHILL
Highway PW
From GENE HOWE WILDLIFE MANAGEMENT AREA
To .
CSJ 0904-03-017
Proj ID C 904-3-17
Work Type REHAB EXISTING RDWY
 
4.477 938346.79 782017.07 842416.56 89.7
Work Order 09-22-15
Work Began 06-06-16
Work Completed  
Time Computed 10-21-15
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 43
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-03-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153063
Totals 938346.79 782017.07 842416.56 89.7

CountyPOTTER
Highway RM 1061
From FM 2381
To 7.5 MILES NORTH OF FM 2381
CSJ 1245-02-043
Proj ID STP 1502(299)HES
Work Type WIDEN ROADWAY FOR SAFETY
 
10.539 7907537.75 1148826.18 6352623.80 80.3
CountyPOTTER
Highway RM 1061
From 10.50 MILES NORTH OF FM 2381
To OLDHAM COUNTY LINE
CSJ 1245-02-044
Proj ID STP 1502(355)
Work Type ADD PASSING LANES FOR SAFETY
 
12.837 2230786.34 154136.90 936815.98 41.9
Work Order 08-20-15
Work Began 02-03-16
Work Completed  
Time Computed 08-03-15
Contract Working Days 234
Addl Days Granted 0
Working Days Charged 129
Percent Time Used 55
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1245-02-043
BARRICADES UNLIMITED (1.85%)
HJC FARMS, INC.(1.25%)
W.S. CONSTRUCTION COMPANY(9.93%)
WILLIS ELECTRIC CO., LP(0.46%)
Contract # 06153245
Totals 10138324.09 1302963.08 7289439.78 71.8

CountyDALLAM
Highway SS 17
From US 87
To US 385
CSJ 1702-03-001
Proj ID STP 2011(992)
Work Type NEW LOCATION 2 LANE RDWY
 
1.866 1621574.25 0.00 1853975.60 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-14-11
Work Began 02-06-12
Work Completed  
Time Computed 02-28-12
Contract Working Days 150
Addl Days Granted 17
Working Days Charged 174
Percent Time Used 104
Contractor(s)
HOLMES CONSTRUCTION CO., L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1702-03-001
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(3.37%)
SECRET GARDENER(0.94%)
Contract # 05113008
Totals 1621574.25 0.00 1853975.60 99.9

CountyHEMPHILL
Highway RM 2654
From SH 33
To FM 277
CSJ 2612-01-011
Proj ID SSW 2612-1-11
Work Type SAFETY WIDENING OF ROADWAY
 
8.215 5653751.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 272
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2612-01-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163219
Totals 5653751.98 0.00 0.00 0.0

CountyRANDALL
Highway LP 335
From IH 27, E
To BNSF RR
CSJ 2635-02-022
Proj ID DMO 2012(189)
Work Type ADDITIONAL 2 LANES AND BRIDGES
 
3.000 32232646.86 402356.14 14629361.29 45.3
Work Order 03-04-14
Work Began 11-03-14
Work Completed  
Time Computed 03-20-14
Contract Working Days 645
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 12
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-022
ALAMO BROTHERS CONCRETE(4.52%)
BARRICADES UNLIMITED (1.36%)
LONE STAR PRODUCTS (FLOWER MOUND)(0.00%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.73%)
MCL CONTRACTING, LLC (0.04%)
PENHALL COMPANY (AUSTIN) (0.02%)
WILLIS ELECTRIC CO., LP(2.97%)
Contract # 12133202
Totals 32232646.86 402356.14 14629361.29 45.3

page 1 | page 2