Monthly State Let Construction Report For Amarillo District As Of Apr 11, 2014 Page 2 Of 3

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDALLAM
Highway US 54
From DALHART CURB & GUTTER
To CHAMBERLIN
CSJ 0238-03-052
Proj ID C 238-3-52
Work Type REHAB EXIST RDWY & ADD PASSING LNS
 
23.304 6417952.72 0.00 5732785.26 91.9
Work Order 08-20-12
Work Began 09-10-12
Work Completed  
Time Computed 09-05-12
Contract Working Days 172
Addl Days Granted 0
Working Days Charged 323
Percent Time Used 187
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-03-052
BARRICADES UNLIMITED-USE NEW NUMBER 24847 ON NEW SUBCONTRACT (2.73%)
DUSTROL, INC.(0.34%)
E. DIAZ TRUCKING (3.00%)
Contract # 06123007
Totals 6417952.72 0.00 5732785.26 91.9

CountySHERMAN
Highway US 54
From DALLAM COUNTY LINE
To US 287
CSJ 0238-05-039
Proj ID NH 2014(226)
Work Type REHAB EXIST RDWY & ADD PASSING LANE
 
6.141 3184352.73 0.00 23124.00 0.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-08-14
Work Began 00-00-00
Work Completed  
Time Computed 03-18-14
Contract Working Days 92
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0238-05-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11133218
Totals 3184352.73 0.00 23124.00 0.7

CountySHERMAN
Highway US 54
From COUNTY ROAD G
To OKLAHOMA STATE LINE
CSJ 0238-06-026
Proj ID NH 1102(367)
Work Type REHAB EXISTING RDWY & PASSING LANES
 
9.953 3252696.71 9714.50 3220515.06 99.9
Work Order 08-15-11
Work Began 09-19-11
Work Completed  
Time Computed 08-31-11
Contract Working Days 110
Addl Days Granted 0
Working Days Charged 193
Percent Time Used 175
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0238-06-026
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(2.00%)
HOLMES CONSTRUCTION CO., L.P.(6.96%)
DUSTROL, INC.(4.25%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.27%)
LANCO TURF & SEEDING, INC. (0.10%)
Contract # 07113066
Totals 3252696.71 9714.50 3220515.06 99.9

CountyCARSON
Highway IH 40
From 3.0 MI EAST OF POTTER CO. LINE
To 3.7 MI WEST OF CONWAY
CSJ 0275-02-069
Proj ID IM 0401(208)
Work Type REHAB EXISTING ROADWAY
 
7.759 5177809.06 67119.71 1227961.98 25.6
Work Order 01-15-13
Work Began 10-28-13
Work Completed  
Time Computed 01-31-13
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 174
Percent Time Used 204
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-02-069
AMARILLO RMT ENTERPRISE(0.78%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.05%)
O. TREVINO CONSTRUCTION, LLC (7.18%)
TEX OP CONSTRUCTION, LP(1.36%)
WEST TEXAS RUMBLE STRIP(0.11%)
Contract # 11123206
Totals 5177809.06 67119.71 1227961.98 25.6

CountyCARSON
Highway IH 40
From 3.2 MI WEST OF CONWAY
To 1.6 MI EAST OF CONWAY
CSJ 0275-03-062
Proj ID IM 0401(211)
Work Type REHAB EXISTING ROADWAY
 
4.876 3604723.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0275-03-062
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143205
Totals 3604723.24 0.00 0.00 0.0

CountyOCHILTREE
Highway SH 15
From US 83
To LIPSCOMB COUNTY LINE
CSJ 0355-03-028
Proj ID STP 2013(442)
Work Type OVERLAY
 
15.205 3838624.15 38171.56 4014488.94 99.9
CountyOCHILTREE
Highway SH 15
From PERRYTON C&G
To LIPSCOMB COUNTY LINE
CSJ 0355-03-029
Proj ID STP 2013(442)
Work Type OVERLAY
 
14.665 1443103.90 0.00 1350594.12 93.5
Work Order 05-23-13
Work Began 08-28-13
Work Completed  
Time Computed 06-08-13
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 79
Percent Time Used 96
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0355-03-028
DUSTROL, INC.(0.34%)
FLAT LINE, INC.(0.95%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(4.59%)
J C DIAZ TRUCKING(3.54%)
BARRICADES UNLIMITED (0.30%)
Contract # 03133013
Totals 5281728.05 38171.56 5365083.06 99.9

CountyHUTCHINSON
Highway SH 136
From AT ROCK CREEK
To .
CSJ 0356-01-091
Proj ID BR 2013(375)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.151 2716537.03 195074.26 1707449.56 62.8
Work Order 05-06-13
Work Began 07-30-13
Work Completed  
Time Computed 05-22-13
Contract Working Days 241
Addl Days Granted 0
Working Days Charged 161
Percent Time Used 66
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0356-01-091
SCOTT DERR PAINTING CO, LLC(0.44%)
MCL CONTRACTING, LLC (0.93%)
RUNNING HORSE CONSTRUCTION, INC. (2.30%)
TEX OP CONSTRUCTION, LP(0.58%)
SHINN & GREGORY, INC.( 10.12%)
PRIMATE CONSTRUCTION, INC. (0.28%)
LANCO TURF & SEEDING, INC. (0.27%)
HJC FARMS, INC.(2.03%)
DUSTROL, INC.(0.19%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(2.43%)
AOC ENVIRONMENTAL, INC.(1.90%)
Contract # 02133215
Totals 2716537.03 195074.26 1707449.56 62.8

CountyHARTLEY
Highway US 87
From EAST OF US 385 INTERCHANGE
To MOORE COUNTY LINE
CSJ 0425-01-019
Proj ID C 425-1-19
Work Type REHAB EXISTING RDWY & PASSING LANES
 
22.251 21250815.26 619198.01 5353493.14 25.1
Work Order 10-24-12
Work Began 11-19-12
Work Completed  
Time Computed 11-09-12
Contract Working Days 370
Addl Days Granted 0
Working Days Charged 318
Percent Time Used 85
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0425-01-019
HIGHWAY TECHNOLOGIES, INC. (0.14%)
TEXAS ALTERNATIVE GRASSER, INC.(0.02%)
DUSTROL, INC.(1.94%)
HOLMES CONSTRUCTION CO., L.P.( 10.19%)
HJC FARMS, INC.(0.95%)
BALLOU PAVEMENT SOLUTIONS INC. ( 14.78%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.51%)
BRUSH EATERS, INC. (0.12%)
KOSS CONSTRUCTION COMPANY( 14.78%)
WILLIS ELECTRIC CO., LP(0.09%)
Contract # 08123002
Totals 21250815.26 619198.01 5353493.14 25.1

CountyROBERTS
Highway SH 70
From NORTH CANADIAN RIVER BRIDGE
To OCHILTREE COUNTY LINE
CSJ 0490-04-037
Proj ID STP 2014(579)
Work Type REHABILITATE EXISTING ROADWAY
 
5.848 5139086.58 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143003
Totals 5139086.58 0.00 0.00 0.0

CountyRANDALL
Highway PR 5
From AT WATER CROSS 1,2,6 AND BURNT DRAW
To IN PALO DURO CANYON STATE PARK
CSJ 0534-01-019
Proj ID C 534-1-19
Work Type REPLACE CONCRETE WATER CROSSINGS
 
0.576 3956849.00 511117.26 1841545.44 46.5
Work Order 11-04-13
Work Began 11-04-13
Work Completed  
Time Computed 11-20-13
Contract Working Days 235
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 39
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0534-01-019
ENVIRONMENTAL SAFETY SERVICES, INC.(3.98%)
HOLMES CONSTRUCTION CO., L.P.( 27.09%)
LANCO TURF & SEEDING, INC. (0.52%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.27%)
ALTUS TRAFFIC MANAGEMENT LLC (0.59%)
MH CIVIL CONSTRUCTORS, INC.(0.24%)
BARRICADES UNLIMITED (0.29%)
DAVIS CONSTRUCTION, INC. ( 27.81%)
AMARILLO RMT ENTERPRISE(1.81%)
Contract # 09133228
Totals 3956849.00 511117.26 1841545.44 46.5

CountyLIPSCOMB
Highway SH 305
From SP 188
To LIPSCOMB COUNTY LINE
CSJ 0582-02-018
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 6255144.40 0.00 0.00 0.0
CountyHEMPHILL
Highway SH 305
From LIPSCOMB COUNTY LINE
To US 60
CSJ 0582-03-014
Proj ID STP 2014(312)
Work Type RESTORATION OF EXISTING ROAD
 
12.325 1439611.54 0.00 0.00 0.0
Work Order 11-14-13
Work Began 00-00-00
Work Completed  
Time Computed 11-30-13
Contract Working Days 130
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0582-02-018
BARRICADES UNLIMITED (1.55%)
HJC FARMS, INC.(0.88%)
SCR CONSTRUCTION CO., INC. (2.06%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.46%)
TEX OP CONSTRUCTION, LP(0.27%)
Contract # 10133018
Totals 7694755.94 0.00 0.00 0.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS IN AMARILLO
To (ON SYSTEM)
CSJ 0904-00-148
Proj ID STP 2012(052)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2062945.48 17830.84 1631530.97 90.1
Work Order 01-03-12
Work Began 01-23-12
Work Completed  
Time Computed 01-19-12
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 459
Percent Time Used 262
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-148
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(5.28%)
RAY ELECTRIC COMPANY (7.14%)
SECRET GARDENER(1.63%)
SPEEDY PAVING(2.25%)
Contract # 10113013
Totals 2062945.48 17830.84 1631530.97 90.1

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-152
Proj ID STP 2014(003)
Work Type CRACK SEAL
 
201.631 286787.20 0.00 286020.51 99.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-03-14
Work Began 01-06-14
Work Completed  
Time Computed 01-19-14
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 11
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-152
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09133029
Totals 286787.20 0.00 286020.51 99.7

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-153
Proj ID STP 2014(389)G
Work Type THERMOPLASTIC STRIPING
 
442.233 1171697.78 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-10-14
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
VIZCAINO, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-153
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143220
Totals 1171697.78 0.00 0.00 0.0

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To (ON SYSTEM)
CSJ 0904-00-154
Proj ID STP 2013(085)
Work Type STATEWIDE CURB RAMP PROGRAM
 
0.100 2916208.80 0.00 2219466.85 76.1
Work Order 12-04-12
Work Began 01-08-13
Work Completed  
Time Computed 12-20-12
Contract Working Days 206
Addl Days Granted 0
Working Days Charged 204
Percent Time Used 99
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-154
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(6.11%)
CLASSIC TEJAS CONSTRUCTION, INC. ( 14.49%)
Contract # 10123029
Totals 2916208.80 0.00 2219466.85 76.1

CountyHUTCHINSON
Highway CS
From ON ROOSEVELT ST. FROM SH 136
To SH 207
CSJ 0904-07-012
Proj ID STP 2013(490)
Work Type REHAB EXISTING ROADWAY
 
0.769 1870540.00 48640.57 682840.75 36.5
Work Order 07-31-13
Work Began 09-03-13
Work Completed  
Time Computed 08-16-13
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 121
Percent Time Used 97
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-07-012
RAY ELECTRIC COMPANY (1.71%)
ALAMO BROTHERS CONCRETE( 26.42%)
A-1 SERVICES (0.26%)
BARRICADES UNLIMITED (3.15%)
TEX OP CONSTRUCTION, LP(0.61%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
Contract # 06133015
Totals 1870540.00 48640.57 682840.75 36.5

CountyRANDALL
Highway CS
From ON FARMERS AVE, FROM WESTERN ST
To GEORGIA ST
CSJ 0904-11-053
Proj ID STP 2013(143)
Work Type REHAB EXISTING ROADWAY
 
0.996 1400000.00 0.00 822728.30 60.0
Work Order 01-04-13
Work Began 06-03-13
Work Completed  
Time Computed 05-06-13
Contract Working Days 83
Addl Days Granted 10
Working Days Charged 119
Percent Time Used 127
Contractor(s)
L. A. FULLER & SONS CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0904-11-053
A-1 SERVICES (0.18%)
ALAMO BROTHERS CONCRETE(8.38%)
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.12%)
TEXAS ALTERNATIVE GRASSER, INC.(0.65%)
Contract # 11123019
Totals 1400000.00 0.00 822728.30 60.0

CountyLIPSCOMB
Highway SH 23
From FM 377
To 11.05 MI N OF US 83
CSJ 1337-01-022
Proj ID C 1337-1-22
Work Type REHAB & WIDEN EXISTING RDWY
 
10.063 5502012.06 138989.05 2311368.04 42.0
Work Order 11-19-12
Work Began 01-09-13
Work Completed  
Time Computed 12-05-12
Contract Working Days 250
Addl Days Granted 94
Working Days Charged 233
Percent Time Used 67
Contractor(s)
MITCHELL ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1337-01-022
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.68%)
HJC FARMS, INC.(1.81%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.18%)
B&B SOLVENT, LTD.( 48.75%)
RICE CONSTRUCTION( 19.87%)
Contract # 07123220
Totals 5502012.06 138989.05 2311368.04 42.0

CountyLIPSCOMB
Highway SH 23
From 11.05 MI N OF US 83
To US 83
CSJ 1337-02-010
Proj ID STP 2013(086)
Work Type REHAB & WIDEN EXISTING RDWY
 
11.050 6406551.08 313701.97 3977763.22 62.5
Work Order 01-03-13
Work Began 01-07-13
Work Completed  
Time Computed 01-19-13
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 219
Percent Time Used 115
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1337-02-010
AMARILLO RMT ENTERPRISE(2.63%)
CUTRELL TRUCKING COMPANY, INC. (3.97%)
TEXAS ENVIRONMENTAL MANAGEMENT, INC(0.80%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(2.04%)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (0.32%)
Contract # 10123014
Totals 6406551.08 313701.97 3977763.22 62.5

CountyDALLAM
Highway SS 17
From US 87
To US 385
CSJ 1702-03-001
Proj ID STP 2011(992)
Work Type NEW LOCATION 2 LANE RDWY
 
1.866 1621574.25 0.00 1844975.60 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-14-11
Work Began 02-06-12
Work Completed  
Time Computed 02-28-12
Contract Working Days 150
Addl Days Granted 17
Working Days Charged 174
Percent Time Used 104
Contractor(s)
HOLMES CONSTRUCTION CO., L.P.
SUBCONTRACTOR(S) FOR CCSJ: 1702-03-001
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(3.37%)
SECRET GARDENER(0.94%)
Contract # 05113008
Totals 1621574.25 0.00 1844975.60 99.9

page 1 | page 2 | page 3