Monthly State Let Construction Report For Amarillo District As Of Nov 9, 2016 Page 2 Of 2

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyROBERTS
Highway SH 70
From NORTH CANADIAN RIVER BRIDGE
To OCHILTREE COUNTY LINE
CSJ 0490-04-037
Proj ID STP 2014(579)
Work Type REHABILITATE EXISTING ROADWAY
 
5.848 5139086.58 48800.00 4930298.17 98.0
Work Order 06-18-14
Work Began 12-10-14
Work Completed  
Time Computed 09-02-14
Contract Working Days 197
Addl Days Granted 27
Working Days Charged 321
Percent Time Used 143
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
BARRICADES UNLIMITED (0.99%)
HJC FARMS, INC.(3.77%)
HUDSON, INC. (0.81%)
TEXAS ALTERNATIVE GRASSER, INC.(0.43%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.84%)
WEST TEXAS RUMBLE STRIP(0.08%)
W.S. CONSTRUCTION COMPANY(5.84%)
E. DIAZ TRUCKING (2.85%)
Contract # 04143003
Totals 5139086.58 48800.00 4930298.17 98.0

CountyMOORE
Highway SH 152
From DUMAS CITY LIMITS
To HUTCHINSON COUNTY LINE
CSJ 0557-01-028
Proj ID STP 2016(683)
Work Type RESTORATION
 
47.263 15561610.53 2780843.82 8927284.27 57.3
Work Order 05-24-16
Work Began 07-06-16
Work Completed  
Time Computed 06-23-16
Contract Working Days 130
Addl Days Granted 20
Working Days Charged 87
Percent Time Used 58
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0557-01-028
BARRICADES UNLIMITED (0.84%)
DUSTROL, INC.(2.04%)
W.S. CONSTRUCTION COMPANY(1.58%)
CF TRUCKING, LLC (1.46%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.11%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.15%)
HJC FARMS, INC.(0.21%)
Contract # 02163003
Totals 15561610.53 2780843.82 8927284.27 57.3

CountyDALLAM
Highway FM 1727
From FM 3310
To 7 MI WEST OF FM 3489
CSJ 0794-01-018
Proj ID STP 1502(296)HES
Work Type WIDEN ROADWAY FOR SAFETY
 
11.362 6170063.74 58550.21 2530247.46 41.3
Work Order 07-16-15
Work Began 02-24-16
Work Completed  
Time Computed 01-11-16
Contract Working Days 114
Addl Days Granted 8
Working Days Charged 139
Percent Time Used 113
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0794-01-018
BARRICADES UNLIMITED (0.73%)
LANCO TURF & SEEDING, INC. (0.30%)
COWBELL TRAFFIC SERVICES, INC. (0.40%)
HJC FARMS, INC.(1.37%)
E. DIAZ TRUCKING (2.28%)
Contract # 06153218
Totals 6170063.74 58550.21 2530247.46 41.3

CountyPOTTER
Highway VA
From AT VARIOUS LOCATIONS IN AMARILLO
To .
CSJ 0904-00-160
Proj ID STP 2015(649)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2895601.55 106314.34 2539646.14 88.4
Work Order 05-08-15
Work Began 07-06-15
Work Completed  
Time Computed 05-24-15
Contract Working Days 274
Addl Days Granted 0
Working Days Charged 301
Percent Time Used 109
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-160
ONE WAY CONCRETE ( 56.56%)
BTA SERVICES, LTD. (1.91%)
W.A. ROBBINS CONSTRUCTION CO., INC.(6.35%)
QLVS, INC. DBA PHASE 3 ELECTRIC(1.30%)
PAVEMENT MARKINGS INC. (2.36%)
Contract # 03153026
Totals 2895601.55 106314.34 2539646.14 88.4

CountyPOTTER
Highway VA
From AT VARIOUS LOCATIONS IN AMA DISTRIC
To .
CSJ 0904-00-161
Proj ID STP 2016(150)
Work Type CONSTUCT CURB RAMPS
 
0.001 1946236.07 7300.50 1686311.67 86.6
Work Order 12-10-15
Work Began 02-24-16
Work Completed  
Time Computed 12-11-15
Contract Working Days 210
Addl Days Granted 3
Working Days Charged 127
Percent Time Used 59
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-161
CLASSIC TEJAS CONSTRUCTION, INC. (5.30%)
BARRICADES UNLIMITED (8.52%)
Contract # 10153022
Totals 1946236.07 7300.50 1686311.67 86.6

CountyPOTTER
Highway VA
From VARIOUS LOCATIONS DISTRICTWIDE
To .
CSJ 0904-00-162
Proj ID STP 2017(002)
Work Type CRACK SEAL
 
172.430 369998.68 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-03-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 74
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-162
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09163009
Totals 369998.68 0.00 0.00 0.0

CountyPOTTER
Highway CR
From ON DEWEY AVE AT WEST AMARILLO CREEK
To .
CSJ 0904-02-037
Proj ID BR 2014(554)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.041 1220116.75 543504.45 1200787.60 98.4
Work Order 06-22-16
Work Began 06-28-16
Work Completed  
Time Computed 06-28-16
Contract Working Days 56
Addl Days Granted 24
Working Days Charged 72
Percent Time Used 90
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-02-037
BARRICADES UNLIMITED (0.31%)
L. A. FULLER & SONS CONSTRUCTION, LTD. (1.87%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 13.83%)
SOUTH TEXAS PAINTING COMPANY (0.62%)
WOLFE CONSTRUCTION GROUP, INC. (0.27%)
MCL CONTRACTING, LLC (0.77%)
Contract # 04163235
Totals 1220116.75 543504.45 1200787.60 98.4

CountyHEMPHILL
Highway PW
From GENE HOWE WILDLIFE MANAGEMENT AREA
To .
CSJ 0904-03-017
Proj ID C 904-3-17
Work Type REHAB EXISTING RDWY
 
4.477 938346.79 0.08 842416.65 89.7
Work Order 09-22-15
Work Began 06-06-16
Work Completed  
Time Computed 10-21-15
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 49
Percent Time Used 85
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-03-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153063
Totals 938346.79 0.08 842416.65 89.7

CountyPOTTER
Highway RM 1061
From FM 2381
To 7.5 MILES NORTH OF FM 2381
CSJ 1245-02-043
Proj ID STP 1502(299)HES
Work Type WIDEN ROADWAY FOR SAFETY
 
10.539 7907537.75 281507.00 6727053.30 85.0
CountyPOTTER
Highway RM 1061
From 10.50 MILES NORTH OF FM 2381
To OLDHAM COUNTY LINE
CSJ 1245-02-044
Proj ID STP 1502(355)
Work Type ADD PASSING LANES FOR SAFETY
 
12.837 2230786.34 528396.00 1861809.91 83.4
Work Order 08-20-15
Work Began 02-03-16
Work Completed  
Time Computed 08-03-15
Contract Working Days 234
Addl Days Granted 4
Working Days Charged 168
Percent Time Used 70
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1245-02-043
BARRICADES UNLIMITED (1.85%)
HJC FARMS, INC.(1.25%)
W.S. CONSTRUCTION COMPANY(9.93%)
WILLIS ELECTRIC CO., LP(0.46%)
Contract # 06153245
Totals 10138324.09 809903.00 8588863.21 84.7

CountyHEMPHILL
Highway RM 2654
From SH 33
To FM 277
CSJ 2612-01-011
Proj ID SSW 2612-1-11
Work Type SAFETY WIDENING OF ROADWAY
 
8.215 5653751.98 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-16-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 272
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2612-01-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07163219
Totals 5653751.98 0.00 0.00 0.0

CountyRANDALL
Highway LP 335
From IH 27, E
To BNSF RR
CSJ 2635-02-022
Proj ID DMO 2012(189)
Work Type ADDITIONAL 2 LANES AND BRIDGES
 
3.000 32232646.86 534792.14 15489162.03 48.0
Work Order 03-04-14
Work Began 11-03-14
Work Completed  
Time Computed 03-20-14
Contract Working Days 645
Addl Days Granted 0
Working Days Charged 81
Percent Time Used 12
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-022
ALAMO BROTHERS CONCRETE(4.52%)
BARRICADES UNLIMITED (1.36%)
LONE STAR PRODUCTS (FLOWER MOUND)(0.00%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.73%)
MCL CONTRACTING, LLC (0.04%)
PENHALL COMPANY (AUSTIN) (0.02%)
WILLIS ELECTRIC CO., LP(2.97%)
Contract # 12133202
Totals 32232646.86 534792.14 15489162.03 48.0

page 1 | page 2