Monthly State Let Construction Report For Amarillo District As Of Jan 11, 2017 Page 2 Of 2

Last Update: Thursday, January 12, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDALLAM
HighwayFM 1727
FromFM 3310
To7 MI WEST OF FM 3489
CSJ0794-01-018
Proj IDSTP 1502(296)HES
Work TypeWIDEN ROADWAY FOR SAFETY
 
11.3626170063.742989581.6448.7
Work Order07-16-15
Work Began02-24-16
Work Completed
Time Computed01-11-16
Contract Working Days114
Addl Days Granted8
Working Days Charged139
Percent Time Used113
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0794-01-018
BARRICADES UNLIMITED (0.73)
LANCO TURF & SEEDING, INC. (0.30)
COWBELL TRAFFIC SERVICES, INC. (0.40)
HJC FARMS, INC. (1.37)
E. DIAZ TRUCKING (2.28)
Contract #06153218
Totals6170063.74221109.002989581.6448.7

CountyPOTTER
HighwayVA
FromAT VARIOUS LOCATIONS IN AMARILLO
To.
CSJ0904-00-160
Proj IDSTP 2015(649)
Work TypeCONSTRUCT CURB RAMPS
 
0.0012895601.552906263.7599.9
Work Order05-08-15
Work Began07-06-15
Work Completed
Time Computed05-24-15
Contract Working Days274
Addl Days Granted0
Working Days Charged300
Percent Time Used109
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-160
ONE WAY CONCRETE (56.56)
BTA SERVICES, LTD. (1.91)
W.A. ROBBINS CONSTRUCTION CO., INC. (6.35)
QLVS, INC. DBA PHASE 3 ELECTRIC (1.30)
PAVEMENT MARKINGS INC. (2.36)
Contract #03153026
Totals2895601.5560324.092906263.7599.9

CountyPOTTER
HighwayVA
FromAT VARIOUS LOCATIONS IN AMA DISTRIC
To.
CSJ0904-00-161
Proj IDSTP 2016(150)
Work TypeCONSTUCT CURB RAMPS
 
0.0011946236.071692311.6786.9
Work Order12-10-15
Work Began02-24-16
Work Completed
Time Computed12-11-15
Contract Working Days210
Addl Days Granted3
Working Days Charged127
Percent Time Used59
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-161
CLASSIC TEJAS CONSTRUCTION, INC. (5.30)
BARRICADES UNLIMITED (8.52)
Contract #10153022
Totals1946236.073000.001692311.6786.9

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-162
Proj IDSTP 2017(002)
Work TypeCRACK SEAL
 
172.430369998.68344707.9793.1
Work Order11-03-16
Work Began00-00-00
Work Completed
Time Computed12-05-16
Contract Working Days74
Addl Days Granted0
Working Days Charged9
Percent Time Used12
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-162
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163009
Totals369998.68344707.97344707.9793.1

CountyPOTTER
HighwayCR
FromON DEWEY AVE AT WEST AMARILLO CREEK
To.
CSJ0904-02-037
Proj IDBR 2014(554)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.0411220116.751349099.5399.9
Work Order06-22-16
Work Began06-28-16
Work Completed
Time Computed06-28-16
Contract Working Days56
Addl Days Granted24
Working Days Charged95
Percent Time Used118
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-02-037
BARRICADES UNLIMITED (0.31)
L. A. FULLER & SONS CONSTRUCTION, LTD. (1.87)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (13.83)
SOUTH TEXAS PAINTING COMPANY (0.62)
WOLFE CONSTRUCTION GROUP, INC. (0.27)
MCL CONTRACTING, LLC (0.77)
Contract #04163235
Totals1220116.7521135.201349099.5399.9

CountyHEMPHILL
HighwayPW
FromGENE HOWE WILDLIFE MANAGEMENT AREA
To.
CSJ0904-03-017
Proj IDC 904-3-17
Work TypeREHAB EXISTING RDWY
 
4.477938346.79843150.3789.8
Work Order09-22-15
Work Began06-06-16
Work Completed
Time Computed10-21-15
Contract Working Days57
Addl Days Granted0
Working Days Charged49
Percent Time Used85
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-03-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08153063
Totals938346.790.00843150.3789.8

CountyPOTTER
HighwayRM 1061
FromFM 2381
To7.5 MILES NORTH OF FM 2381
CSJ1245-02-043
Proj IDSTP 1502(299)HES
Work TypeWIDEN ROADWAY FOR SAFETY
 
10.5397907537.757115751.5289.9
CountyPOTTER
HighwayRM 1061
From10.50 MILES NORTH OF FM 2381
ToOLDHAM COUNTY LINE
CSJ1245-02-044
Proj IDSTP 1502(355)
Work TypeADD PASSING LANES FOR SAFETY
 
12.8372230786.342071383.2492.8
Work Order08-20-15
Work Began02-03-16
Work Completed
Time Computed08-03-15
Contract Working Days234
Addl Days Granted4
Working Days Charged183
Percent Time Used76
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1245-02-043
BARRICADES UNLIMITED (1.85)
HJC FARMS, INC. (1.25)
W.S. CONSTRUCTION COMPANY (9.93)
WILLIS ELECTRIC CO., LP (0.46)
Contract #06153245
Totals10138324.09156813.579187134.7690.6

CountyHEMPHILL
HighwayRM 2654
FromSH 33
ToFM 277
CSJ2612-01-011
Proj IDSSW 2612-1-11
Work TypeSAFETY WIDENING OF ROADWAY
 
8.2155653751.980.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days272
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2612-01-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07163219
Totals5653751.980.000.000.0

CountyRANDALL
HighwayLP 335
FromIH 27, E
ToBNSF RR
CSJ2635-02-022
Proj IDDMO 2012(189)
Work TypeADDITIONAL 2 LANES AND BRIDGES
 
3.00032232646.8616507992.0751.2
Work Order03-04-14
Work Began11-03-14
Work Completed
Time Computed03-20-14
Contract Working Days645
Addl Days Granted0
Working Days Charged81
Percent Time Used12
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-022
ALAMO BROTHERS CONCRETE (4.52)
BARRICADES UNLIMITED (1.36)
LONE STAR PRODUCTS (FLOWER MOUND) (0.00)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.73)
MCL CONTRACTING, LLC (0.04)
PENHALL COMPANY (AUSTIN) (0.02)
WILLIS ELECTRIC CO., LP (2.97)
Contract #12133202
Totals32232646.86289464.5216507992.0751.2

page 1 | page 2