Monthly State Let Construction Report For Amarillo District As Of Apr 10, 2017 Page 2 Of 2

Last Update: Monday, April 10, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyROBERTS
HighwaySH 70
FromNORTH CANADIAN RIVER BRIDGE
ToOCHILTREE COUNTY LINE
CSJ0490-04-037
Proj IDSTP 2014(579)
Work TypeREHABILITATE EXISTING ROADWAY
 
5.8485139086.585051467.6599.9
Work Order06-18-14
Work Began12-10-14
Work Completed
Time Computed09-02-14
Contract Working Days197
Addl Days Granted27
Working Days Charged321
Percent Time Used143
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0490-04-037
BARRICADES UNLIMITED (0.99)
HJC FARMS, INC. (3.77)
HUDSON, INC. (0.81)
TEXAS ALTERNATIVE GRASSER, INC. (0.43)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.84)
WEST TEXAS RUMBLE STRIP (0.08)
W.S. CONSTRUCTION COMPANY (5.84)
E. DIAZ TRUCKING (2.85)
Contract #04143003
Totals5139086.583430.005051467.6599.9

CountyMOORE
HighwaySH 152
FromDUMAS CITY LIMITS
ToHUTCHINSON COUNTY LINE
CSJ0557-01-028
Proj IDSTP 2016(683)
Work TypeRESTORATION
 
47.26315561610.539148975.8258.7
Work Order05-24-16
Work Began07-06-16
Work Completed
Time Computed06-23-16
Contract Working Days130
Addl Days Granted20
Working Days Charged87
Percent Time Used58
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0557-01-028
BARRICADES UNLIMITED (0.84)
DUSTROL, INC. (2.04)
W.S. CONSTRUCTION COMPANY (1.58)
CF TRUCKING, LLC (1.46)
SURFACE PREPARATION TECHNOLOGIES, LLC (0.11)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.15)
HJC FARMS, INC. (0.21)
VANCE BROTHERS, INC. (5.72)
Contract #02163003
Totals15561610.5343492.759148975.8258.7

CountyDALLAM
HighwayFM 1727
FromFM 3310
To7 MI WEST OF FM 3489
CSJ0794-01-018
Proj IDSTP 1502(296)HES
Work TypeWIDEN ROADWAY FOR SAFETY
 
11.3626170063.743279204.9753.4
Work Order07-16-15
Work Began02-24-16
Work Completed
Time Computed01-11-16
Contract Working Days114
Addl Days Granted8
Working Days Charged139
Percent Time Used113
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0794-01-018
BARRICADES UNLIMITED (0.73)
LANCO TURF & SEEDING, INC. (0.30)
COWBELL TRAFFIC SERVICES, INC. (0.40)
HJC FARMS, INC. (1.37)
E. DIAZ TRUCKING (2.28)
Contract #06153218
Totals6170063.7456351.903279204.9753.4

CountyPOTTER
HighwayVA
FromAT VARIOUS LOCATIONS IN AMARILLO
To.
CSJ0904-00-160
Proj IDSTP 2015(649)
Work TypeCONSTRUCT CURB RAMPS
 
0.0012895601.552954451.7599.9
Work Order05-08-15
Work Began07-06-15
Work Completed
Time Computed05-24-15
Contract Working Days274
Addl Days Granted14
Working Days Charged300
Percent Time Used104
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-160
ONE WAY CONCRETE (56.56)
BTA SERVICES, LTD. (1.91)
W.A. ROBBINS CONSTRUCTION CO., INC. (6.35)
QLVS, INC. DBA PHASE 3 ELECTRIC (1.30)
PAVEMENT MARKINGS INC. (2.36)
Contract #03153026
Totals2895601.5524133.002954451.7599.9

CountyPOTTER
HighwayVA
FromAT VARIOUS LOCATIONS IN AMA DISTRIC
To.
CSJ0904-00-161
Proj IDSTP 2016(150)
Work TypeCONSTUCT CURB RAMPS
 
0.0011946236.071715416.3788.1
Work Order12-10-15
Work Began02-24-16
Work Completed
Time Computed12-11-15
Contract Working Days210
Addl Days Granted3
Working Days Charged127
Percent Time Used59
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-161
CLASSIC TEJAS CONSTRUCTION, INC. (5.30)
BARRICADES UNLIMITED (8.52)
Contract #10153022
Totals1946236.0714000.001715416.3788.1

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-162
Proj IDSTP 2017(002)
Work TypeCRACK SEAL
 
172.430369998.68376428.2899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-03-16
Work Began00-00-00
Work Completed
Time Computed12-05-16
Contract Working Days74
Addl Days Granted0
Working Days Charged13
Percent Time Used17
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-162
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09163009
Totals369998.680.00376428.2899.9

CountyPOTTER
HighwayVA
FromVARIOUS LOCATIONS DISTRICTWIDE
To.
CSJ0904-00-164
Proj IDSTP 2017(593)
Work TypeTHERMOPLASTIC STRIPING
 
1.0001085462.590.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-15-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days72
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 0904-00-164
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02173034
Totals1085462.590.000.000.0

CountyPOTTER
HighwayCR
FromON DEWEY AVE AT WEST AMARILLO CREEK
To.
CSJ0904-02-037
Proj IDBR 2014(554)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.0411220116.751363225.5399.9
Work Order06-22-16
Work Began06-28-16
Work Completed
Time Computed06-28-16
Contract Working Days56
Addl Days Granted27
Working Days Charged95
Percent Time Used114
Contractor(s)
DCI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-02-037
BARRICADES UNLIMITED (0.31)
L. A. FULLER & SONS CONSTRUCTION, LTD. (1.87)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (13.83)
SOUTH TEXAS PAINTING COMPANY (0.62)
WOLFE CONSTRUCTION GROUP, INC. (0.27)
MCL CONTRACTING, LLC (0.77)
Contract #04163235
Totals1220116.75369.001363225.5399.9

CountyHEMPHILL
HighwayPW
FromGENE HOWE WILDLIFE MANAGEMENT AREA
To.
CSJ0904-03-017
Proj IDC 904-3-17
Work TypeREHAB EXISTING RDWY
 
4.477938346.79849716.3790.5
Work Order09-22-15
Work Began06-06-16
Work Completed
Time Computed10-21-15
Contract Working Days57
Addl Days Granted0
Working Days Charged49
Percent Time Used85
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0904-03-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08153063
Totals938346.796510.00849716.3790.5

CountyPOTTER
HighwayRM 1061
FromFM 2381
To7.5 MILES NORTH OF FM 2381
CSJ1245-02-043
Proj IDSTP 1502(299)HES
Work TypeWIDEN ROADWAY FOR SAFETY
 
10.5397907537.757525501.1795.1
CountyPOTTER
HighwayRM 1061
From10.50 MILES NORTH OF FM 2381
ToOLDHAM COUNTY LINE
CSJ1245-02-044
Proj IDSTP 1502(355)
Work TypeADD PASSING LANES FOR SAFETY
 
12.8372230786.342224654.7999.7
Work Order08-20-15
Work Began02-03-16
Work Completed
Time Computed08-03-15
Contract Working Days234
Addl Days Granted19
Working Days Charged183
Percent Time Used72
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1245-02-043
BARRICADES UNLIMITED (1.85)
HJC FARMS, INC. (1.25)
W.S. CONSTRUCTION COMPANY (9.93)
WILLIS ELECTRIC CO., LP (0.46)
Contract #06153245
Totals10138324.09151032.409750155.9696.1

CountyHEMPHILL
HighwayRM 2654
FromSH 33
ToFM 277
CSJ2612-01-011
Proj IDSSW 2612-1-11
Work TypeSAFETY WIDENING OF ROADWAY
 
8.2155653751.98849348.7615.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-16-16
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days272
Addl Days Granted0
Working Days Charged26
Percent Time Used9
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2612-01-011
AOC ENVIRONMENTAL, INC. (0.70)
BARRICADES UNLIMITED (0.65)
DOUBLE A CONTRACTING, L.P. (0.96)
DUSTROL, INC. (1.26)
HJC FARMS, INC. (2.76)
HODGES AND SON CONSTRUCTION COMPANY, INC. (8.74)
MISSOURI PETROLEUM PRODUCTS COMPANY LLC (13.65)
O. TREVINO CONSTRUCTION, LLC (1.34)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.87)
W.O.E. CONSTRUCTION (0.18)
WILLIS ELECTRIC CO., LP (0.39)
Contract #07163219
Totals5653751.980.00849348.7615.0

CountyRANDALL
HighwayLP 335
FromIH 27, E
ToBNSF RR
CSJ2635-02-022
Proj IDDMO 2012(189)
Work TypeADDITIONAL 2 LANES AND BRIDGES
 
3.00032232646.8618012430.3555.8
Work Order03-04-14
Work Began11-03-14
Work Completed
Time Computed03-20-14
Contract Working Days645
Addl Days Granted0
Working Days Charged81
Percent Time Used12
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2635-02-022
ALAMO BROTHERS CONCRETE (4.52)
BARRICADES UNLIMITED (1.36)
LONE STAR PRODUCTS (FLOWER MOUND) (0.00)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (0.73)
MCL CONTRACTING, LLC (0.04)
PENHALL COMPANY (AUSTIN) (0.02)
WILLIS ELECTRIC CO., LP (2.97)
Contract #12133202
Totals32232646.86846473.0418012430.3555.8

page 1 | page 2