AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - AMARILLO DISTRICT
Last Update: Friday, May 3, 2013
| ITEMS 1122 2002 TO 1124 2001 |
| Item No |
Description |
Units |
April 30, 2013 |
Twelve Month Moving |
Usage |
| Quantity |
Avg Bid |
Quantity |
Avg Bid |
| 1122 2002 |
ROCK FILTER DAMS (INSTALL) (TY 2) |
LF |
|
|
46.000 |
48.00000 |
1 |
| 1122 2009 |
ROCK FILTER DAMS (REMOVE) |
LF |
|
|
46.000 |
11.25000 |
1 |
| 1122 2019 |
CONSTRUCTION EXITS (REMOVE) |
SY |
|
|
156.000 |
3.00000 |
1 |
| 1122 2031 |
SANDBAGS FOR EROSION CONTROL |
EA |
|
|
1,360.000 |
2.58824 |
2 |
| 1122 2032 |
SANDBAGS FOR EROSION CONTROL (6") |
LF |
|
|
2,995.000 |
14.41018 |
4 |
| 1122 2037 |
TEMPORARY SEDIMENT CONTROL FENCE INSTL |
LF |
|
|
14,922.000 |
3.77335 |
10 |
| 1122 2057 |
TEMPORARY SEDIMENT CONTROL FENCE REMOV |
LF |
|
|
5,176.000 |
1.16922 |
8 |
| 1124 2001 |
GATE VALVE (COMPLETE) (2") |
EA |
|
|
1.000 |
1,900.00000 |
1 |