Monthly State Let Construction Report For Abilene District As Of Dec 12, 2017 Page 2 Of 2

Last Update: Tuesday, December 12, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOWARD
HighwayVA
FromIH 20
ToFM 700
CSJ0908-12-022
Proj IDDMO 1102(493)
Work TypeCONSTRUCT NEW RELIEF ROUTE
 
8.1530.0030202272.260.0
Work Order01-13-17
Work Began02-21-17
Work Completed
Time Computed02-13-17
Contract Working Days680
Addl Days Granted4
Working Days Charged200
Percent Time Used29
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-022
STRIPE-A-ZONE, INC. (0.54)
W.S. CONSTRUCTION COMPANY (4.94)
DELHUR INDUSTRIES, INC. (33.90)
ALTUS TRAFFIC MANAGEMENT LLC (0.10)
DIIBS SPECIALISTS (0.46)
TEXAS SHAFTS, INC. (1.91)
AARON CONCRETE CONTRACTORS, L.P. (1.54)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.90)
SOUTHEAST GRINDING & GROOVING, LLC (0.06)
ROBERT KENT CONSTRUCTION (0.23)
EMERGY (2.44)
DTM TRUCKING, INC. (0.15)
HERITAGE ASPHALT COMPANY (9.45)
PLATINUM PIPELINE SERVICES, LLC (0.03)
CHOCTAW ERECTORS, INC. (0.18)
Contract #09163001
Totals0.004491624.2830202272.260.0

CountyCALLAHAN
HighwayCR
FromON CR 152 (SIGNED CR 484)
ToAT DEEP CREEK (PSN 2)
CSJ0908-34-022
Proj IDBR 2016(763)
Work TypeBRIDGE REPLACEMENT
 
0.3171472447.50504482.9734.2
Work Order09-18-17
Work Began10-09-17
Work Completed
Time Computed10-09-17
Contract Working Days241
Addl Days Granted0
Working Days Charged34
Percent Time Used14
Contractor(s)
ELLIS-MCGINNIS CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0908-34-022
CONTRACTORS SERVICE COMPANY (0.95)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.86)
DIIBS SPECIALISTS (3.01)
Contract #08173013
Totals1472447.50131954.95504482.9734.2

CountySCURRY
HighwayFM 1606
FromSH 208
ToUS 84
CSJ1526-03-015
Proj IDSTP 2016(678)
Work TypeSUBGR WIDEN, FL BS, STRS, 2CST,MBGF
 
9.3306876410.355986241.9987.9
Work Order04-19-16
Work Began05-09-16
Work Completed
Time Computed05-09-16
Contract Working Days228
Addl Days Granted41
Working Days Charged324
Percent Time Used120
Contractor(s)
SALINAS CONSTRUCTION TECHNOLOGIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1526-03-015
CONTRACTORS SERVICE COMPANY (0.33)
DOUBLE A CONTRACTING (0.33)
HJC FARMS, INC. (3.44)
Contract #02163233
Totals6876410.3586292.705986241.9987.9

CountySCURRY
HighwayFM 1610
FromBORDEN COUNTY LINE
ToFM 1606
CSJ1531-02-012
Proj IDSTP 2016(679)
Work TypeRESTORE AND WIDEN EXISTING ROADWAY
 
7.0445397845.795330694.8099.5
Work Order04-14-16
Work Began08-02-16
Work Completed
Time Computed05-14-16
Contract Working Days220
Addl Days Granted5
Working Days Charged261
Percent Time Used116
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1531-02-012
CONTRACTORS SERVICE COMPANY (0.49)
BRENDA CONSTRUCTION (8.07)
BARRICADES UNLIMITED (1.08)
HJC FARMS, INC. (2.28)
Contract #02163022
Totals5397845.7912194.005330694.8099.5

CountyHOWARD
HighwayFM 2230
FromUS 87
ToFM 846
CSJ2149-01-009
Proj IDSTP 2013(765)
Work TypeEXC,EMB,FL BS,STRS,2 CRSE SURF TRT
 
10.9656178220.666261168.6399.9
Work Order04-02-15
Work Began05-20-15
Work Completed
Time Computed06-01-15
Contract Working Days331
Addl Days Granted71
Working Days Charged352
Percent Time Used87
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2149-01-009
REECE CONSTRUCTION CO., INC. (26.62)
GARY A. CRAIN, INC. (0.05)
TEXAS SHAFTS, INC. (1.31)
ALTUS TRAFFIC MANAGEMENT LLC (0.50)
BARRICADES UNLIMITED (1.44)
HJC FARMS, INC. (1.06)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (2.05)
SAENZ TRANSPORT, LLC (6.16)
ARANDA"S TRUCKING (2.26)
GONZALES DUMP TRUCK SERVICES (0.80)
Contract #02153010
Totals6178220.660.006261168.6399.9