Monthly State Let Construction Report For Abilene District As Of Feb 10, 2017 Page 2 Of 2

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMITCHELL
HighwayFM 2836
FromAT CHERRY CREEK
To.
CSJ2331-01-014
Proj IDBR 2016(615)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.1651445914.791232541.1388.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-10-16
Work Began03-14-16
Work Completed
Time Computed03-14-16
Contract Working Days82
Addl Days Granted0
Working Days Charged148
Percent Time Used180
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2331-01-014
M & D FOUNDATION DRILLING INDUSTRIES, INC. (2.75)
WOLFE CONSTRUCTION GROUP, INC. (0.30)
ALTUS TRAFFIC MANAGEMENT LLC (0.31)
KLP COMMERCIAL, LLC (2.55)
RIO"S STEEL (0.62)
HOUSTON SAWING & DRILLING (0.30)
BARRICADES UNLIMITED (0.20)
BICK"S CONSTRUCTION, INC. (1.11)
NOBLES ROAD CONSTRUCTION, INC. (0.17)
Contract #12153044
Totals1445914.790.001232541.1388.3

CountyJONES
HighwayFM 3116
FromAT CLEAR FORK OF BRAZOS
ToPSN #2
CSJ2721-02-013
Proj IDC 2721-2-13
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.2031045832.50294500.0028.1
Work Order09-26-16
Work Began11-28-16
Work Completed
Time Computed10-26-16
Contract Working Days93
Addl Days Granted0
Working Days Charged39
Percent Time Used41
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 2721-02-013
CONTRACTORS SERVICE COMPANY (0.78)
LANCO TURF & SEEDING, INC. (1.25)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.39)
SCOTT DERR PAINTING CO, LLC (0.46)
PENHALL COMPANY (0.33)
STRIPE-A-ZONE, INC. (1.40)
MCL CONTRACTING, LLC (0.60)
Contract #08163033
Totals1045832.5034700.00294500.0028.1

page 1 | page 2