Monthly State Let Construction Report For Abilene District As Of Aug 10, 2015 Page 2 Of 3

Last Update: Monday, August 10, 2015
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOWARD
Highway US 87
From MARTIN COUNTY LINE
To 4.929 MI E OF MARTIN C/L (NBL ONLY)
CSJ 0068-07-050
Proj ID NH 1502(194)
Work Type PLAN, UNDSL, SUPER PAVE, MBGF
 
28.052 12331796.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-16-15
Work Began 00-00-00
Work Completed  
Time Computed 12-14-15
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0068-07-050
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153008
Totals 12331796.40 0.00 0.00 0.0

CountySTONEWALL
Highway SH 283 ETC
From US 380
To HASKELL COUNTY LINE
CSJ 0106-06-033
Proj ID STP 2015(546)
Work Type SEAL COAT
 
194.747 6122799.18 947565.87 6114996.52 99.8
Work Order 02-10-15
Work Began 05-18-15
Work Completed  
Time Computed 03-13-15
Contract Working Days 41
Addl Days Granted 0
Working Days Charged 39
Percent Time Used 95
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0106-06-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01153222
Totals 6122799.18 947565.87 6114996.52 99.8

CountyNOLAN
Highway BS 70-G
From AVENUE B IN SWEETWATER
To IH 20
CSJ 0264-01-036
Proj ID STP 2013(372)
Work Type REHABILITATION, ACP, SIDEWALKS
 
1.287 6493251.00 31671.74 6498115.87 100.0
Work Order 06-20-13
Work Began 09-03-13
Work Completed 02-13-15
Time Computed 08-20-13
Contract Working Days 318
Addl Days Granted 0
Working Days Charged 299
Percent Time Used 94
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0264-01-036
DOUBLE A CONTRACTING, L.P. (0.44%)
KARMY CONSTRUCTION INC (4.04%)
WILLIS ELECTRIC CO., LP(4.46%)
HJC FARMS, INC.(0.35%)
DUSTROL, INC.(0.99%)
CONTRACTORS SERVICE COMPANY(0.69%)
Contract # 02133222
Totals 6493251.00 31671.74 6498115.87 100.0

CountyTAYLOR
Highway US 277
From FM 3438
To FM 707
CSJ 0407-06-040
Proj ID STP 1502(291)
Work Type PLAN, FL PAV STR RPR, SUPER PAV,
 
6.543 6510587.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-31-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 109
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0407-06-040
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153254
Totals 6510587.92 0.00 0.00 0.0

CountyCALLAHAN
Highway US 283
From SH 36
To COLEMAN COUNTY LINE
CSJ 0437-04-025
Proj ID STP 2014(266)
Work Type REWORKING BASE, FLEX BASE, & 2CST
 
10.616 4270742.32 295637.60 1368702.17 32.0
Work Order 07-18-14
Work Began 02-16-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 157
Addl Days Granted 0
Working Days Charged 71
Percent Time Used 45
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0437-04-025
DOUBLE A CONTRACTING, L.P. (2.20%)
CONTRACTORS SERVICE COMPANY(0.48%)
RICE ENVIRONMENTAL SERVICES(0.38%)
PRIME ECO GROUP, INC.(1.03%)
WILLIS ELECTRIC CO., LP(0.04%)
Contract # 05143008
Totals 4270742.32 295637.60 1368702.17 32.0

CountyHOWARD
Highway SH 176
From MARTIN COUNTY LINE
To APPROX 1 MILE EAST OF FM 2599
CSJ 0548-04-019
Proj ID STP 1502(193)
Work Type PLANE, CMT TRT BS, BRG RL, SUPER PAVE
 
5.450 8697657.95 1372341.40 1372341.40 15.7
Work Order 07-07-15
Work Began 07-13-15
Work Completed  
Time Computed 07-13-15
Contract Working Days 252
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 5
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0548-04-019
CONTRACTORS SERVICE COMPANY(0.35%)
DOUBLE A CONTRACTING, L.P. (3.81%)
HJC FARMS, INC.(1.41%)
SCR CONSTRUCTION CO., INC. (2.22%)
TEX OP CONSTRUCTION, LP(1.34%)
HUDSON, INC. (0.12%)
Contract # 05153227
Totals 8697657.95 1372341.40 1372341.40 15.7

CountyTAYLOR
Highway FM 1235
From MERKEL CITY LIMIT
To CR 392
CSJ 0663-03-027
Proj ID STP 2015(789)HES
Work Type FL BS, REWK BS MATL, 2CST, CMP & SET
 
11.020 4552099.47 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-08-15
Work Began 00-00-00
Work Completed  
Time Computed 09-07-15
Contract Working Days 280
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0663-03-027
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153037
Totals 4552099.47 0.00 0.00 0.0

CountyTAYLOR
Highway FM 613
From FM 89 IN BUFFALO GAP
To 0.39 MILES WEST OF US 83 IN TUSCOLA
CSJ 0699-03-017
Proj ID STP 2013(951)
Work Type REHAB & WIDEN
 
7.051 2058772.50 213492.80 1961976.91 98.5
Work Order 10-10-13
Work Began 04-08-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 154
Addl Days Granted 0
Working Days Charged 240
Percent Time Used 155
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0699-03-017
O. TREVINO CONSTRUCTION, LLC ( 18.63%)
MURRAY CONSTRUCTION(3.38%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.00%)
CONTRACTORS SERVICE COMPANY(0.70%)
Contract # 08133258
Totals 2058772.50 213492.80 1961976.91 98.5

CountyTAYLOR
Highway VA
From BI 20-M IN NOLAN COUNTY
To FM 700, AND SH 350 IN HOWARD COUNTY
CSJ 0908-00-079
Proj ID NH 2015(793)
Work Type INS RD IL AM, DRILL SHAFT, ELEC CON
 
1.000 402151.50 14083.52 18867.12 4.6
Work Order 05-21-15
Work Began 00-00-00
Work Completed  
Time Computed 08-20-15
Contract Working Days 89
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-079
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04153224
Totals 402151.50 14083.52 18867.12 4.6

CountyHOWARD
Highway VA
From RM 33
To IH 20
CSJ 0908-12-019
Proj ID BOR 2004(670)
Work Type CONSTRUCT NEW RELIEF ROUTE
 
8.456 44837998.95 2431482.54 25998793.33 57.9
Work Order 03-12-14
Work Began 07-21-14
Work Completed  
Time Computed 05-05-14
Contract Working Days 679
Addl Days Granted 0
Working Days Charged 268
Percent Time Used 39
Contractor(s)
SUNDT CONSTRUCTION, INC.
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0908-12-019
MJE, LLC (2.01%)
HARDY HOLE DRILLING(1.14%)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.15%)
CMT ENGINEERING, INC.(0.24%)
MCL CONTRACTING, LLC (1.29%)
DUSTROL, INC.(0.95%)
OTTO TRUCKING, INC.(4.17%)
PENHALL COMPANY(0.03%)
DUSTIN ALLEN, INC. (0.27%)
WILLIS ELECTRIC CO., LP(0.20%)
SCOTT DERR PAINTING CO, LLC(0.00%)
CRANE SERVICES, INC. (0.18%)
Contract # 12133201
Totals 44837998.95 2431482.54 25998793.33 57.9

CountyMITCHELL
Highway CR
From ON CR 142
To AT THE COLORADO RIVER
CSJ 0908-21-016
Proj ID BR 2008(757)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.173 1272147.12 175127.90 808086.82 63.5
CountyMITCHELL
Highway CR
From 0.02 MILES NORTH CR 123
To AT NO NAME DRAW
CSJ 0908-21-019
Proj ID BR 2008(760)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.060 310822.15 25511.81 294720.13 94.8
Work Order 06-23-14
Work Began 10-24-14
Work Completed  
Time Computed 10-20-14
Contract Working Days 209
Addl Days Granted 0
Working Days Charged 142
Percent Time Used 67
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-21-016
TWIN MOUNTAIN FENCE CO.(0.12%)
BARRICADES UNLIMITED (5.23%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.10%)
ALTEX LANDSCAPE CONSTRUCTION, INC. (0.21%)
MCL CONTRACTING, LLC (0.22%)
Contract # 04143228
Totals 1582969.27 200639.71 1102806.95 69.6

CountyFISHER
Highway CR
From ON CR 153
To AT PLUM CREEK (PSN 1)
CSJ 0908-23-034
Proj ID BR 2013(642)
Work Type REPLACE BR AND APPRS
 
0.066 290974.50 0.00 293763.30 99.9
CountyFISHER
Highway CR
From ON CR 146
To AT BUFFALO CREEK (PSN 1)
CSJ 0908-23-035
Proj ID BR 2013(643)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.067 340532.50 0.00 330831.18 97.1
CountyFISHER
Highway CR
From ON CR 119
To AT ALKALI CREEK (PSN 1)
CSJ 0908-23-036
Proj ID BR 2013(644)
Work Type REPLACE BR AND APPRS
 
0.063 237814.00 0.00 226700.92 95.3
Work Order 06-20-14
Work Began 09-03-14
Work Completed  
Time Computed 09-03-14
Contract Working Days 215
Addl Days Granted 0
Working Days Charged 178
Percent Time Used 82
Contractor(s)
ASHLAR CONTRACTING COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0908-23-034
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.91%)
REDROD STEEL AND CABLE, LLC(0.39%)
CONTRACTORS SERVICE COMPANY(1.09%)
RICE ENVIRONMENTAL SERVICES(3.42%)
Contract # 05143039
Totals 869321.00 0.00 851295.40 97.9

CountyFISHER
Highway CR
From ON CR 183
To AT ROUGH CREEK (PSN 1)
CSJ 0908-23-037
Proj ID BR 2013(724)
Work Type REHABILITATE BRIDGE AND APPROACHES
 
0.086 1781426.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-23-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08153022
Totals 1781426.00 0.00 0.00 0.0

CountyJONES
Highway CR
From CR 201
To AT POST OAK CREEK (PSN 1)
CSJ 0908-24-048
Proj ID BR 2014(043)
Work Type REPLACE BRIDGE
 
0.095 376415.00 0.00 380351.45 100.0
CountyJONES
Highway CR
From ON CR 111
To AT CARTER CREEK
CSJ 0908-24-049
Proj ID BR 2014(044)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.063 242558.00 720.00 230379.00 100.0
Work Order 07-02-14
Work Began 09-09-14
Work Completed 08-07-15
Time Computed 09-02-14
Contract Working Days 143
Addl Days Granted 0
Working Days Charged 143
Percent Time Used 100
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-24-048
CONTRACTORS SERVICE COMPANY(0.99%)
TEXAS ALTERNATIVE GRASSER, INC.(2.18%)
DUSTIN ALLEN, INC. (5.15%)
LONE STAR HIGHWAY PRODUCTS, INC. (3.57%)
STEEL EFFECTS(0.53%)
Contract # 05143020
Totals 618973.00 720.00 610730.45 100.0

CountyHOWARD
Highway FM 821
From FM 2183
To IH 20
CSJ 1156-02-021
Proj ID STP 2015(794)
Work Type SUBGR WIDN, FL BS, 2CST, STRS, SET, MBGF
 
11.542 9379399.55 487897.32 685479.30 7.3
Work Order 05-19-15
Work Began 06-29-15
Work Completed  
Time Computed 06-19-15
Contract Working Days 256
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 8
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1156-02-021
J.V. CONCRETE CONSTRUCTION (2.36%)
CONTRACTORS SERVICE COMPANY(0.28%)
HJC FARMS, INC.(2.54%)
BARRICADES UNLIMITED (2.68%)
Contract # 04153002
Totals 9379399.55 487897.32 685479.30 7.3

CountySCURRY
Highway FM 1606
From SH 350
To SH 208
CSJ 1526-02-009
Proj ID STP 1502(293)
Work Type SUBGR WIDEN, FL BS, STRS, 2CST, MBGF
 
7.101 6584662.31 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 194
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1526-02-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153058
Totals 6584662.31 0.00 0.00 0.0

CountyTAYLOR
Highway FM 1750
From NEAR LP 322 IN ABILENE
To NEAR MARIAH STREET IN POTOSI
CSJ 1655-01-026
Proj ID STP 2015(795)
Work Type SPOT REPAIR, SPOT LEVEL - UP, SEAL & OV
 
5.026 2294679.90 17391.93 17391.93 0.7
CountyTAYLOR
Highway FM 1750
From AT FM 707
To .
CSJ 1655-01-027
Proj ID STP 2015(796)HES
Work Type INSTALL TRAFFIC SIGNAL
 
0.190 377510.44 0.00 0.00 0.0
Work Order 05-19-15
Work Began 07-20-15
Work Completed  
Time Computed 07-19-15
Contract Working Days 108
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 9
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 1655-01-026
WILLIS ELECTRIC CO., LP(6.91%)
DUSTIN ALLEN, INC. (0.37%)
CONTRACTORS SERVICE COMPANY(0.78%)
TEXAS ALTERNATIVE GRASSER, INC.(0.08%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.66%)
Contract # 04153239
Totals 2672190.34 17391.93 17391.93 0.6

CountyHOWARD
Highway FM 846
From FM 669
To FM 1205
CSJ 1872-02-017
Proj ID STP 1502(216)
Work Type EMB, EXC, STRS, SET, SURF, MBGF
 
16.092 9519743.52 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-30-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 311
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SBBI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1872-02-017
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05153055
Totals 9519743.52 0.00 0.00 0.0

CountySCURRY
Highway FM 1269
From APPROX 1 MILE S. OF GARZA CNTY LINE
To US 180
CSJ 1873-02-022
Proj ID STP 1302(042)
Work Type REHAB & WIDEN
 
16.020 4597730.26 602507.50 3123569.40 67.9
Work Order 02-13-15
Work Began 03-11-15
Work Completed  
Time Computed 03-01-15
Contract Working Days 240
Addl Days Granted 0
Working Days Charged 80
Percent Time Used 33
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1873-02-022
BARRICADES UNLIMITED (1.86%)
TEXAS ALTERNATIVE GRASSER, INC.(0.21%)
HJC FARMS, INC.(1.23%)
W.S. CONSTRUCTION COMPANY(7.93%)
BLACK JACK ENERGY SERVICES ( 39.53%)
Contract # 01153025
Totals 4597730.26 602507.50 3123569.40 67.9

CountyHOWARD
Highway FM 2230
From US 87
To FM 846
CSJ 2149-01-009
Proj ID STP 2013(765)
Work Type EXC, EMB, FL BS, STRS, 2 CRSE SURF TRT
 
10.965 6178220.66 412050.57 1340113.18 21.6
Work Order 04-02-15
Work Began 05-20-15
Work Completed  
Time Computed 06-01-15
Contract Working Days 331
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 9
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2149-01-009
REECE CONSTRUCTION CO., INC. ( 26.62%)
GARY A. CRAIN, INC.(0.05%)
TEXAS SHAFTS, INC. (1.31%)
ALTUS TRAFFIC MANAGEMENT LLC (0.50%)
BARRICADES UNLIMITED (1.44%)
HJC FARMS, INC.(1.06%)
LIPHAM ASPHALT AND PAVING COMPANY, LLC (2.05%)
SAENZ TRANSPORT, LLC (6.16%)
ARANDA"S TRUCKING(2.26%)
GONZALES DUMP TRUCK SERVICES (0.80%)
Contract # 02153010
Totals 6178220.66 412050.57 1340113.18 21.6

page 1 | page 2 | page 3