Monthly State Let Construction Report For Abilene District As Of Mar 13, 2024 Page 3 Of 3

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMITCHELL
HighwayCR
FromON CR 616 (412)
ToAT N FORK CHAMPION CREEK
CSJ0908-21-039
Proj IDBR 2B20(209)
Work TypeBRIDGE REPLACEMENT
 
0.066711084.00510398.5271.7
Work Order09-08-23
Work Began10-16-23
Work Completed
Time Computed12-07-23
Contract Working Days84
Addl Days Granted0
Working Days Charged55
Percent Time Used65
Contractor(s)
DELGADO'S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0908-21-039
BARRICADES UNLIMITED (1.01)
TEXAS SHAFTS, INC. (10.42)
HERMANOS STEEL, LLC (0.23)
Contract #06233043
Totals711084.0020597.40510398.5271.7

CountyFISHER
HighwayCR
FromGYP CREEK
To.
CSJ0908-23-053
Proj IDBR 2023(945)
Work TypeBRIDGE REPLACEMENT
 
917198.00247477.9626.9
Work Order07-26-23
Work Began11-13-23
Work Completed
Time Computed10-24-23
Contract Working Days96
Addl Days Granted0
Working Days Charged31
Percent Time Used32
Contractor(s)
DELGADO'S CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0908-23-053
BARRICADES UNLIMITED (0.90)
HARDY HOLE DRILLING (4.97)
Contract #06233448
Totals917198.005000.00247477.9626.9

CountyKENT
HighwayCR
FromAT COOPER CREEK
To.
CSJ0908-27-006
Proj IDBR 2023(941)
Work TypeBRIDGE REPLACEMENT
 
0.069878015.000.000.0
Work Order01-10-24
Work Began00-00-00
Work Completed
Time Computed02-09-24
Contract Working Days89
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0908-27-006
BARRICADES UNLIMITED (0.52)
MORRIS COUNTY CONTRACTORS, L.L.C. (2.45)
Contract #12233216
Totals878015.000.000.000.0

CountyTAYLOR
HighwayCS
FromFORREST AVE
ToKIRKWOOD ST
CSJ0908-33-102
Proj IDSTP 2B23(133)HESG
Work TypeTRAFFIC CONTROL DEVICES
 
0.340200053.00173803.0086.8
Work Order09-06-23
Work Began01-02-24
Work Completed
Time Computed10-06-23
Contract Working Days38
Addl Days Granted0
Working Days Charged10
Percent Time Used26
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0908-33-102
AWP SAFETY (5.42)
Contract #08233063
Totals200053.000.00173803.0086.8

CountyTAYLOR
HighwayCS
FromAT CEDAR CREEK
To.
CSJ0908-33-106
Proj IDBR 2022(944)
Work TypeBRIDGE REPLACEMENT
 
0.0671316532.40841584.0363.9
Work Order06-14-23
Work Began10-13-23
Work Completed
Time Computed09-12-23
Contract Working Days133
Addl Days Granted0
Working Days Charged57
Percent Time Used42
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-33-106
CONTRACTORS SERVICE, LTD. (0.73)
D. I. J. CONSTRUCTION, INC. (0.69)
HJC FARMS, INC. (1.67)
DK CONTRACTING, LLC (0.66)
WYLIE DRILLING & DRAINAGE, INC. (5.46)
TORO BRAVO CONSTRUCTION, LLC (0.32)
Contract #05233036
Totals1316532.40289624.02841584.0363.9

CountyJONES
HighwayFM 1082
FromWEST OF CHEYENNE CIRCLE
ToEAST OF DAM
CSJ0972-03-021
Proj IDF 2B23(134)
Work TypeNEW LOCATION NON-FREEWAY
 
1.3638867738.993172244.1335.7
Work Order09-07-23
Work Began10-27-23
Work Completed
Time Computed12-06-23
Contract Working Days261
Addl Days Granted0
Working Days Charged65
Percent Time Used24
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0972-03-021
ALAMO BROTHERS CONCRETE INC (4.35)
BARRICADES UNLIMITED (0.16)
BLACK JACK ENERGY SERVICES, LLC (38.55)
SCOTT DERR PAINTING CO, LLC (0.16)
HODGES AND SON CONSTRUCTION COMPANY, INC. (1.55)
MURRAY CONSTRUCTION (0.37)
HJC FARMS, INC. (2.66)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.41)
FLAT LINE, INC. (0.75)
PENHALL COMPANY (0.06)
TORO BRAVO CONSTRUCTION, LLC (0.06)
Contract #08233216
Totals8867738.99571715.003172244.1335.7

CountyJONES
HighwayFM 1082
FromEAST OF DAM
ToFM 3522
CSJ0972-03-023
Proj IDF 2024(776)
Work TypeRESTORATION
 
4.1613582697.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days141
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0972-03-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243212
Totals3582697.000.000.000.0

CountyHASKELL
HighwayFM 600
FromFM 2976
ToJONES COUNTY
CSJ0972-06-015
Proj IDF 2023(915)
Work TypeWIDEN NON-FREEWAY
 
4.5322844984.65349866.0012.2
Work Order07-19-23
Work Began10-09-23
Work Completed
Time Computed08-18-23
Contract Working Days120
Addl Days Granted0
Working Days Charged64
Percent Time Used53
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0972-06-015
FLAT LINE, INC. (1.51)
W. S. CONSTRUCTION COMPANY (8.48)
WEST TEXAS BARRICADE AND LIGHT CO. (0.69)
MURRAY CONSTRUCTION (1.76)
BARRICADES UNLIMITED (0.69)
Contract #06233014
Totals2844984.6598151.00349866.0012.2

CountyNOLAN
HighwayFM 419
FromFISHER COUNTY
ToBI-20
CSJ0983-03-030
Proj IDF 2024(170)
Work TypeOVERLAY
 
3360261.390.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-21-24
Work Began00-00-00
Work Completed
Time Computed03-22-24
Contract Working Days94
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0983-03-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10233214
Totals3360261.390.000.000.0

CountySHACKELFORD
HighwayFM 576
FromFM 576
ToAT DEEP CREEK
CSJ1031-05-018
Proj IDBR 2024(663)
Work TypeBRIDGE REPLACEMENT
 
0.1172414951.880.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-02-24
Work Began00-00-00
Work Completed
Time Computed05-02-24
Contract Working Days111
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
A GREATER AUSTIN DEVELOPMENT COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1031-05-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243227
Totals2414951.880.000.000.0

CountyJONES
HighwayFM 1226
FromAT CALIFORNIA CREEK
To.
CSJ1360-01-030
Proj IDBR 2024(522)
Work TypeBRIDGE REPLACEMENT
 
1671853.750.000.0
Work Order12-13-23
Work Began03-04-24
Work Completed
Time Computed01-12-24
Contract Working Days104
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1360-01-030
M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.50)
FC TRAFFIC CONTROL, INC. (0.48)
TORO BRAVO CONSTRUCTION, LLC (0.25)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.46)
MORRIS COUNTY CONTRACTORS, L.L.C. (1.66)
PENHALL COMPANY (0.27)
TEXOP CONSTRUCTION (0.53)
Contract #11233223
Totals1671853.750.000.000.0

CountyFISHER
HighwayFM 419
FromFM 419
ToDRAW CREEK
CSJ1652-01-015
Proj IDBR 2024(303)
Work TypeBRIDGE REPLACEMENT
 
684071.0028001.004.0
Work Order12-05-23
Work Began03-04-24
Work Completed
Time Computed01-04-24
Contract Working Days74
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ICOS MANAGEMENT, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1652-01-015
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11233219
Totals684071.0028001.0028001.004.0

CountyNOLAN
HighwayFM 1170
From5 MILES SOUTH OF FM 608
ToSH 70
CSJ2033-02-012
Proj IDC 2033-2-12
Work TypeRESTORATION
 
11.74911229184.121596028.4014.2
CountyNOLAN
HighwayFM 1170
FromOAK CREEK
To.
CSJ2033-02-013
Proj IDC 2033-2-13
Work TypeBRIDGE REPLACEMENT
 
0.0361230937.500.000.0
Work Order06-14-23
Work Began10-09-23
Work Completed
Time Computed07-14-23
Contract Working Days269
Addl Days Granted0
Working Days Charged50
Percent Time Used18
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2033-02-012
CONTRACTORS SERVICE, LTD. (0.71)
FLAT LINE, INC. (1.18)
HJC FARMS, INC. (1.41)
DK CONTRACTING, LLC (1.41)
HODGES AND SON CONSTRUCTION COMPANY, INC. (1.27)
TORO BRAVO CONSTRUCTION, LLC (0.05)
Contract #05233011
Totals12460121.621105892.001596028.4012.8

CountySCURRY
HighwayFM 1673
FromFM 1673
ToUS 84
CSJ2189-01-020
Proj IDBR 2024(664)
Work TypeBRIDGE REPLACEMENT
 
7348904.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-05-24
Work Began00-00-00
Work Completed
Time Computed03-06-24
Contract Working Days126
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2189-01-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01243019
Totals7348904.500.000.000.0

CountyNOLAN
HighwayFM 608
FromFISHER COUNTY
ToBU 84-J
CSJ2379-02-010
Proj IDC 2379-2-10
Work TypeREHABILITATION OF EXISTING ROAD
 
5.2894084995.250.000.0
Work Order10-25-23
Work Began00-00-00
Work Completed
Time Computed11-24-23
Contract Working Days134
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BONTKE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 2379-02-010
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09233014
Totals4084995.250.000.000.0

page 1 | page 2 | page 3