Monthly State Let Construction Report For Abilene District As Of May 10, 2016 Page 1 Of 2

Last Update: Tuesday, May 10, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOWARD
Highway IH 20
From AT US 87 (NEW LOCATION)
To .
CSJ 0005-05-102
Proj ID DMO 2012(263)
Work Type CONSTRUCT NEW INTERCHANGE
 
2.719 18434933.58 1461578.17 15454759.12 83.8
Work Order 08-19-13
Work Began 05-13-14
Work Completed  
Time Computed 01-01-14
Contract Working Days 470
Addl Days Granted 13
Working Days Charged 439
Percent Time Used 90
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-102
W.S. CONSTRUCTION COMPANY(8.38%)
COPPELL CONSTRUCTION CO., INC. (8.49%)
DRILL TECH DRILLING & SHORING, INC.( 16.58%)
PRICE CONSTRUCTION, LTD. ( 28.11%)
TEXAS SHAFTS, INC. (1.76%)
FELIX CHAVEZ & SON CONSTRUCTION(0.24%)
MARTIN GONZALES INCORPORATED (1.32%)
WILLIS ELECTRIC CO., LP(2.27%)
HJC FARMS, INC.(1.58%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.36%)
TEX OP CONSTRUCTION, LP(0.23%)
TEXAS FAR WEST CONSTRUCTION & ENGINEERING(0.50%)
ARANDA`S TRUCKING(0.74%)
NOBLES ROAD CONSTRUCTION, INC. (0.26%)
AARON CONCRETE CONTRACTORS, L.P. (0.60%)
Contract # 05133202
Totals 18434933.58 1461578.17 15454759.12 83.8

CountyHOWARD
Highway BI 20-G ETC
From IH 20 WEST OF BIG SPRING
To NEAR JONES STREET
CSJ 0005-10-021
Proj ID NH 2016(203)
Work Type SEAL COAT
 
99.259 3396196.05 298884.04 1020763.00 30.0
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 05-09-16
Contract Working Days 47
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0005-10-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153218
Totals 3396196.05 298884.04 1020763.00 30.0

CountyNOLAN
Highway IH 20 ETC
From 0.037 MI W OF CR 104
To 1.1 MI E OF CR 104
CSJ 0006-02-112
Proj ID STP 2016(904)HES
Work Type HFC, TEXT CL & SHLDR, CHEVRONS
 
8.560 3498754.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-112
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163029
Totals 3498754.25 0.00 0.00 0.0

CountyCALLAHAN
Highway IH 20
From AT DRAW (IH 20 ML)
To 1.00 MI E OF TAYLOR C/L
CSJ 0006-07-076
Proj ID BR 2016(567)
Work Type REPAIR CULVERT SAFETY END TREATMENT
 
0.271 249106.80 46190.20 46190.20 18.5
Work Order 03-31-16
Work Began 04-20-16
Work Completed  
Time Computed 04-14-16
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 10
Percent Time Used 31
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-07-076
W.O.E. CONSTRUCTION(9.14%)
PIPE RUNNERS PLUS, LLC (7.47%)
HJC FARMS, INC.( 12.20%)
Contract # 01163014
Totals 249106.80 46190.20 46190.20 18.5

CountyTAYLOR
Highway US 84
From NEAR OLD BANKHEAD HWY
To NEAR US 83
CSJ 0006-18-055
Proj ID NH 2016(915)
Work Type SPOT REPAIR, MILL & OVERLAY
 
2.660 2371863.21 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-18-055
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163231
Totals 2371863.21 0.00 0.00 0.0

CountyTAYLOR
Highway SH 351
From IH 20
To ABILENE EAST CITY LIMIT
CSJ 0011-01-030
Proj ID STP 1302(056)
Work Type FL BS, STRS, PCTB, C & G, SDWLK, DRVWY, SMA
 
1.768 6920469.81 296132.49 3272911.76 47.2
Work Order 04-10-15
Work Began 06-10-15
Work Completed  
Time Computed 06-10-15
Contract Working Days 270
Addl Days Granted 10
Working Days Charged 180
Percent Time Used 64
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0011-01-030
CONTRACTORS SERVICE COMPANY(0.59%)
WILLIS ELECTRIC CO., LP( 12.40%)
STRIPING TECHNOLOGY, L.P.(1.68%)
MARCOM"S MOWING SERVICE, LLC (0.26%)
O. TREVINO CONSTRUCTION, LLC (5.52%)
WOLFE CONSTRUCTION GROUP, INC. (0.91%)
BILL STARKS CONSTRUCTION COMPANY (3.42%)
JORDAN CONCRETE( 13.77%)
Contract # 03153036
Totals 6920469.81 296132.49 3272911.76 47.2

CountyTAYLOR
Highway SH 351
From AT FM 2833
To .
CSJ 0011-01-033
Proj ID STP 2015(585)HES
Work Type INSTALL TRAFFIC SIGNAL
 
0.189 173645.88 14502.05 130863.30 100.0
Work Order 03-20-15
Work Began 08-25-15
Work Completed 04-29-16
Time Computed 04-20-15
Contract Working Days 36
Addl Days Granted 2
Working Days Charged 60
Percent Time Used 157
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0011-01-033
TX DOWN UNDER CONSTRUCTION LLC (1.58%)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC(1.90%)
STREET FOUNDATION DRILLING (2.01%)
Contract # 02153232
Totals 173645.88 14502.05 130863.30 100.0

CountyJONES
Highway US 83
From JUST SOUTH OF 13TH STREET IN ANSON
To NEAR US 277
CSJ 0033-04-065
Proj ID NH 2016(149)
Work Type PLANE, PVMNT REPR, UNDERSL, OVERLAY
 
2.432 4425888.54 189162.25 800894.38 18.0
Work Order 11-24-15
Work Began 02-29-16
Work Completed  
Time Computed 02-29-16
Contract Working Days 152
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 21
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-04-065
CONTRACTORS SERVICE COMPANY(0.36%)
DUSTROL, INC.(3.77%)
BONTKE BROTHERS CONSTRUCTION COMPANY (7.76%)
HJC FARMS, INC.(1.80%)
BARRICADES UNLIMITED (2.84%)
Contract # 10153018
Totals 4425888.54 189162.25 800894.38 18.0

CountyTAYLOR
Highway BU 83-D
From HILL STREET
To NEAR IH 20
CSJ 0033-08-038
Proj ID NH 2016(916)
Work Type PLAN, STR RPR, UNDSL, ACP, MBGF, BR RL
 
7.394 9806711.43 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0033-08-038
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163008
Totals 9806711.43 0.00 0.00 0.0

CountyTAYLOR
Highway US 84
From US 83
To COLEMAN COUNTY LINE
CSJ 0054-01-031
Proj ID NH 2016(917)
Work Type SPOT REPAIR, SEAL & OVERLAY
 
11.210 7380051.17 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0054-01-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163216
Totals 7380051.17 0.00 0.00 0.0

CountyHOWARD
Highway US 87
From MARTIN COUNTY LINE
To 4.929 MI E OF MARTIN C/L (NBL ONLY)
CSJ 0068-07-050
Proj ID NH 1502(194)
Work Type PLAN, UNDSL, SUPER PAVE, MBGF
 
28.052 12331796.40 1646046.01 11391334.68 92.3
Work Order 06-16-15
Work Began 10-08-15
Work Completed  
Time Computed 10-05-15
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 111
Percent Time Used 88
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0068-07-050
BARRICADES UNLIMITED (1.52%)
CONTRACTORS SERVICE COMPANY(0.47%)
HJC FARMS, INC.(0.68%)
TEX OP CONSTRUCTION, LP(1.07%)
WEST TEXAS RUMBLE STRIP(0.30%)
Contract # 05153008
Totals 12331796.40 1646046.01 11391334.68 92.3

CountySTONEWALL
Highway US 380 ETC
From 0.036 MI W OF FM 2211
To 0.346 MI E OF FM 2211
CSJ 0106-04-034
Proj ID STP 2016(672)HES
Work Type HIGH FRICT SURF TRT & PROF PAV MARK
 
2.117 695241.50 508885.00 508885.00 73.1
Work Order 03-14-16
Work Began 04-15-16
Work Completed  
Time Computed 04-13-16
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 40
Contractor(s)
AMERICAN CIVIL CONSTRUCTORS WEST COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 0106-04-034
BARRICADES UNLIMITED ( 10.43%)
Contract # 02163016
Totals 695241.50 508885.00 508885.00 73.1

CountyJONES
Highway SH 6 ETC
From BU 277-G
To SHACKELFORD COUNTY LINE
CSJ 0107-01-036
Proj ID STP 2016(305)
Work Type SEAL COAT
 
225.805 5991840.62 183482.30 1574874.64 26.2
Work Order 12-04-15
Work Began 00-00-00
Work Completed  
Time Computed 06-09-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0107-01-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11153008
Totals 5991840.62 183482.30 1574874.64 26.2

CountyCALLAHAN
Highway SH 36
From TAYLOR CO. LINE
To FM 603
CSJ 0181-02-029
Proj ID STP 2016(676)
Work Type PLAN, FLEX PAV STR RPR, SUPER PAV ACP
 
6.216 5388974.29 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0181-02-029
CONTRACTORS SERVICE COMPANY(0.31%)
WOLFE CONSTRUCTION GROUP, INC. (0.11%)
JORDAN CONCRETE(2.23%)
HJC FARMS, INC.(1.13%)
WILLIS ELECTRIC CO., LP(3.82%)
DOUBLE A CONTRACTING, L.P. (3.81%)
MICA CORPORATION (1.63%)
Contract # 02163010
Totals 5388974.29 0.00 0.00 0.0

CountyTAYLOR
Highway US 277
From 5 MILES NORTH OF FM 89
To 2.6 MILES NORTH OF FM 1086
CSJ 0407-05-025
Proj ID STP 2016(008)HES
Work Type TEXTURIZE SHOULDERS / TEXTURING
 
27.351 192277.66 0.00 187487.96 97.5
Work Order 10-21-15
Work Began 02-22-16
Work Completed  
Time Computed 02-22-16
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 39
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0407-05-025
RED 16 CONSTRUCTION(6.43%)
Contract # 09153219
Totals 192277.66 0.00 187487.96 97.5

CountyTAYLOR
Highway US 277
From FM 3438
To FM 707
CSJ 0407-06-040
Proj ID STP 1502(291)
Work Type PLAN, FL PAV STR RPR, SUPER PAV,
 
6.543 6510587.92 410310.34 5909057.93 90.7
Work Order 07-31-15
Work Began 10-05-15
Work Completed  
Time Computed 08-31-15
Contract Working Days 109
Addl Days Granted 3
Working Days Charged 98
Percent Time Used 87
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0407-06-040
DOUBLE A CONTRACTING, L.P. (1.24%)
ACU CONSTRUCTION LLC (1.32%)
SCR CONSTRUCTION CO., INC. (0.23%)
SIGNAL SERVICES GROUP, INC.(0.42%)
HJC FARMS, INC.(1.67%)
CONTRACTORS SERVICE COMPANY(0.19%)
PRIME ECO GROUP, INC.(0.61%)
Contract # 06153254
Totals 6510587.92 410310.34 5909057.93 90.7

CountyCALLAHAN
Highway US 283
From SH 36
To COLEMAN COUNTY LINE
CSJ 0437-04-025
Proj ID STP 2014(266)
Work Type REWORKING BASE, FLEX BASE, & 2CST
 
10.616 4270742.32 204507.04 3530726.07 83.1
Work Order 07-18-14
Work Began 02-16-15
Work Completed  
Time Computed 02-01-15
Contract Working Days 157
Addl Days Granted 11
Working Days Charged 189
Percent Time Used 112
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0437-04-025
DOUBLE A CONTRACTING, L.P. (2.20%)
CONTRACTORS SERVICE COMPANY(0.48%)
RICE ENVIRONMENTAL SERVICES(0.38%)
PRIME ECO GROUP, INC.(1.03%)
WILLIS ELECTRIC CO., LP(0.04%)
Contract # 05143008
Totals 4270742.32 204507.04 3530726.07 83.1

CountyMITCHELL
Highway SH 208
From CR 633
To COKE COUNTY LINE
CSJ 0454-03-041
Proj ID STP 2016(372)
Work Type SPOT REPAIR, UNDERSEAL, 2" OV SP - D
 
5.319 2654056.80 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-21-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 56
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0454-03-041
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10153230
Totals 2654056.80 0.00 0.00 0.0

CountyHOWARD
Highway FM 669
From BORDEN COUNTY LINE
To 0.055 MILES NORTH OF CR 30
CSJ 0558-04-021
Proj ID STP 2016(010)HES
Work Type TEXTURIZE SHOULDERS (PROFILE PAVEME
 
17.458 130266.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-22-15
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 20
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FLAT LINE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0558-04-021
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09153023
Totals 130266.35 0.00 0.00 0.0

CountyTAYLOR
Highway FM 1235
From MERKEL CITY LIMIT
To CR 392
CSJ 0663-03-027
Proj ID STP 2015(789)HES
Work Type FL BS, REWK BS MATL, 2CST, CMP & SET
 
11.020 4552099.47 49928.17 1313117.40 28.8
Work Order 06-08-15
Work Began 09-08-15
Work Completed  
Time Computed 09-07-15
Contract Working Days 280
Addl Days Granted 50
Working Days Charged 19
Percent Time Used 8
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0663-03-027
CONTRACTORS SERVICE COMPANY(1.01%)
DOUBLE A CONTRACTING, L.P. (2.37%)
HJC FARMS, INC.(2.91%)
BRENDA CONSTRUCTION( 11.84%)
Contract # 04153037
Totals 4552099.47 49928.17 1313117.40 28.8

page 1 | page 2