|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | NOLAN |
| Highway |
IH 20 |
| From |
AT SH 70 IN SWEETWATER |
| To |
(NORTH AND SOUTH FRONTAGE ROADS) |
| CSJ |
0006-03-130 |
| Proj ID |
IM 0202(224) |
| Work Type |
SIGNAL UPGRADE |
| |
|
0.057 |
197891.00 |
116224.87 |
159751.00 |
80.7 |
| Work Order |
02-20-08 |
| Work Began |
10-06-08 |
| Work Completed |
|
| Time Computed |
06-15-08 |
| Contract Working Days |
41 |
| Addl Days Granted |
0 |
| Working Days Charged |
25 |
| Percent Time Used |
60 |
| Contractor(s) |
| WILLIS ELECTRIC CO., LP |
SUBCONTRACTOR(S) FOR CCSJ: 0006-03-130 CONTRACTORS SERVICE COMPANY(2.27%) D. I. J. CONSTRUCTION, INC.(4.97%)
|
| Contract # |
01083214 |
|
Totals |
197891.00 |
116224.87 |
159751.00 |
80.7 |
|
| County | TAYLOR |
| Highway |
IH 20 ETC |
| From |
W OF MERKEL (N FRTG RDS ONLY) |
| To |
E OF MERKEL |
| CSJ |
0006-04-066 |
| Proj ID |
IM 0202(227) |
| Work Type |
SEAL COAT |
| |
|
118.643 |
3617493.72 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
32 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| BRANNAN PAVING CO., LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0006-04-066 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11083205 |
|
Totals |
3617493.72 |
0.00 |
0.00 |
0.0 |
|
| County | TAYLOR |
| Highway |
IH 20 |
| From |
NEAR SPINKS ROAD IN TYE |
| To |
THE INTRCHNG AT US 83/US 277 IN ABL |
| CSJ |
0006-05-098 |
| Proj ID |
C 6-5-98 |
| Work Type |
RELOCATE RAMPS & UPGRADE FRNTG RDS |
| |
|
13.627 |
22582509.93 |
393034.45 |
16050985.96 |
71.0 |
| Work Order |
09-14-06 |
| Work Began |
10-23-06 |
| Work Completed |
|
| Time Computed |
09-30-06 |
| Contract Working Days |
462 |
| Addl Days Granted |
1 |
| Working Days Charged |
435 |
| Percent Time Used |
93 |
| Contractor(s) |
| J. H. STRAIN & SONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0006-05-098 KOTHMANN, LTD. (4.19%) STREET FOUNDATION DRILLING (1.11%) CEN-TEX SEEDING, INC.(1.34%) JAVELINA CONSTRUCTION SOUTH, INC.(0.43%) WILLIS ELECTRIC CO., LP(5.31%) GARY A. CRAIN, INC.(0.07%) CONTRACTORS SERVICE COMPANY(1.00%) TEXAS HIGHWAY MARKINGS, LLC(1.11%) ARK CONTRACTING SERVICES, LLC(1.11%) RUNNING HORSE CONSTRUCTION, INC. (0.29%)
|
| Contract # |
08063008 |
|
Totals |
22582509.93 |
393034.45 |
16050985.96 |
71.0 |
|
| County | NOLAN |
| Highway |
BI 20-M |
| From |
AT THE AT&SF RAILWAY |
| To |
IN SWEETWATER |
| CSJ |
0006-15-030 |
| Proj ID |
BR 2007(750) |
| Work Type |
REHABILITATE BRIDGE AND APPROACHES |
| |
|
0.205 |
1854782.35 |
146383.20 |
1773555.33 |
97.1 |
| Work Order |
10-05-07 |
| Work Began |
12-05-07 |
| Work Completed |
|
| Time Computed |
10-21-07 |
| Contract Working Days |
171 |
| Addl Days Granted |
39 |
| Working Days Charged |
246 |
| Percent Time Used |
117 |
| Contractor(s) |
| GIBSON & ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0006-15-030 DUSTROL, INC.(0.55%) PRICE CONSTRUCTION, LTD. ( 15.86%) SCOTT DERR PAINTING CO (0.38%) TEXAS HIGHWAY MARKINGS, LLC(0.92%) WILLIS ELECTRIC CO., LP(3.51%) HIGHWAY TECHNOLOGIES (1.55%)
|
| Contract # |
09073028 |
|
Totals |
1854782.35 |
146383.20 |
1773555.33 |
97.1 |
|
| County | NOLAN |
| Highway |
BI 20-M ETC |
| From |
LP 170 |
| To |
FM 1544 |
| CSJ |
0006-15-032 |
| Proj ID |
STP 2009(124) |
| Work Type |
SEAL COAT |
| |
|
79.290 |
3888170.54 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
32 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| RONALD R. WAGNER & CO., LP |
SUBCONTRACTOR(S) FOR CCSJ: 0006-15-032 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11083218 |
|
Totals |
3888170.54 |
0.00 |
0.00 |
0.0 |
|
| County | TAYLOR |
| Highway |
US 84 |
| From |
AT FM 3438 |
| To |
. |
| CSJ |
0006-18-044 |
| Proj ID |
HP 2007(669) |
| Work Type |
CONSTRUCT INTERCHANGE |
| |
|
0.804 |
22735157.50 |
1102420.27 |
8488855.51 |
37.3 |
| Work Order |
01-03-08 |
| Work Began |
02-18-08 |
| Work Completed |
|
| Time Computed |
12-03-07 |
| Contract Working Days |
563 |
| Addl Days Granted |
0 |
| Working Days Charged |
157 |
| Percent Time Used |
27 |
| Contractor(s) |
| W.W. WEBBER, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0006-18-044 HIGHWAY TECHNOLOGIES (0.51%) STEPHENS MARTIN PAVING, L.P. ( 10.89%) ATS DRILLING, L.P. (2.87%) ALTEX LANDSCAPE CONSTRUCTION, INC. (0.84%) CAPROCK SPECIALITY CONTRACTORS (0.11%) HJC FARMS, INC.(0.16%) MICA CORPORATION (0.73%) NORTH TEXAS BOMANITE, INC. (0.25%) S & S BRIDGE PAINTING, INC.(0.30%) WILLIS ELECTRIC CO., LP(1.29%) TEXAS HIGHWAY MARKINGS, LLC(0.29%) INDUS CONSTRUCTION, L.P. (5.04%) AAA FENCE CO.(0.01%) ABIDE WELDING, INC.(0.15%)
|
| Contract # |
07073203 |
|
Totals |
22735157.50 |
1102420.27 |
8488855.51 |
37.3 |
|
| County | SHACKELFORD |
| Highway |
US 180 |
| From |
ON US 180 |
| To |
AT N PRONG OF HUBBARD CK |
| CSJ |
0011-05-043 |
| Proj ID |
BR 2008(161) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.322 |
1610871.01 |
213123.81 |
1429288.37 |
88.7 |
| Work Order |
01-03-08 |
| Work Began |
01-10-08 |
| Work Completed |
|
| Time Computed |
01-19-08 |
| Contract Working Days |
180 |
| Addl Days Granted |
0 |
| Working Days Charged |
164 |
| Percent Time Used |
91 |
| Contractor(s) |
| L.A. SEARS CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0011-05-043 WILLIS ELECTRIC CO., LP(3.26%) TEXAS SHAFTS, INC. (3.81%) TEXAS HIGHWAY MARKINGS, LLC(1.02%) TEXAS ALTERNATIVE GRASSER, INC.(0.22%) J. H. STRAIN & SONS, INC.(6.92%) RUNNING HORSE CONSTRUCTION, INC. (3.10%) HIGHWAY TECHNOLOGIES (0.61%) GUAJARDO STEEL (0.55%) CAPROCK SPECIALITY CONTRACTORS (0.16%) BACK TO NATURE (0.11%) RAYMOND PAINTING, INC. (0.57%)
|
| Contract # |
11073017 |
|
Totals |
1610871.01 |
213123.81 |
1429288.37 |
88.7 |
|
| County | STONEWALL |
| Highway |
US 83 |
| From |
AT SALT FORK OF BRAZOS (PSN 29) |
| To |
. |
| CSJ |
0032-07-023 |
| Proj ID |
BR 2007(751) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
1.157 |
2348402.76 |
-17921.83 |
1373378.76 |
58.4 |
| County | STONEWALL |
| Highway |
US 83 |
| From |
AT STINKING CREEK |
| To |
ON US 83 |
| CSJ |
0032-07-024 |
| Proj ID |
BR 2007(751) |
| Work Type |
REPL BR & APPR'S |
| |
|
1.078 |
1111753.97 |
172661.20 |
820446.25 |
73.7 |
| Work Order |
09-11-07 |
| Work Began |
10-02-07 |
| Work Completed |
|
| Time Computed |
09-27-07 |
| Contract Working Days |
280 |
| Addl Days Granted |
8 |
| Working Days Charged |
243 |
| Percent Time Used |
84 |
| Contractor(s) |
| BAKER BRIDGE, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0032-07-023 CONTRACTORS SERVICE COMPANY(0.49%) 76 MILLING, INC. (0.17%) PENHALL COMPANY(0.89%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.72%) STEPHENS MARTIN PAVING, L.P. (2.65%) S & S BRIDGE PAINTING(0.49%) REGULATORY MANAGEMENT SYSTEMS(0.21%) TEXAS HIGHWAY MARKINGS, LLC(0.64%) HJC FARMS, INC.(1.05%)
|
| Contract # |
08073223 |
|
Totals |
3460156.73 |
154739.37 |
2193825.01 |
63.4 |
|
| County | TAYLOR |
| Highway |
US 83 |
| From |
US 277 (S 14TH ST) (FTG RDS ONLY) |
| To |
LP 322 / US 83 INTERCHANGE |
| CSJ |
0034-01-118 |
| Proj ID |
STP 2007(752) |
| Work Type |
PLAN, U / S, ACP, & ADD AUX LNS ON FR RD |
| |
|
3.668 |
3285714.09 |
606468.07 |
3271127.87 |
99.5 |
| Work Order |
09-11-07 |
| Work Began |
04-06-08 |
| Work Completed |
|
| Time Computed |
01-07-08 |
| Contract Working Days |
160 |
| Addl Days Granted |
4 |
| Working Days Charged |
113 |
| Percent Time Used |
68 |
| Contractor(s) |
| J. H. STRAIN & SONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0034-01-118 CONTRACTORS SERVICE COMPANY(1.64%) JAVELINA CONSTRUCTION SOUTH, INC.(2.44%) KARMY CONSTRUCTION INC (2.74%) TEXAS HIGHWAY MARKINGS, LLC(2.05%) HJC FARMS, INC.(4.40%)
|
| Contract # |
08073220 |
|
Totals |
3285714.09 |
606468.07 |
3271127.87 |
99.5 |
|
| County | SCURRY |
| Highway |
US 84 |
| From |
AT THE BN & SF RAILROAD |
| To |
SOUTH OF SNYDER |
| CSJ |
0053-09-062 |
| Proj ID |
BR 2007(011) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.871 |
6964041.64 |
326617.96 |
4628679.23 |
66.4 |
| Work Order |
05-24-07 |
| Work Began |
05-24-07 |
| Work Completed |
|
| Time Computed |
06-09-07 |
| Contract Working Days |
320 |
| Addl Days Granted |
7 |
| Working Days Charged |
324 |
| Percent Time Used |
99 |
| Contractor(s) |
| STEPHENS MARTIN PAVING, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0053-09-062 BAKER BRIDGE, L.P. ( 45.64%) BOOTHE BROTHERS PAVING COMPANY, INC. (2.71%) JONA CONTRACTING, INC. (1.98%) LANCO TURF & SEEDING, INC. (0.15%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.73%) SOIL EXPRESS, LTD. (0.17%) SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.21%) TEXAS HIGHWAY MARKINGS, LLC(0.60%) UNITED RENTALS HIGHWAY TECHNOLOGIES, L.P. (HOUSTON)(0.45%) WEST TEXAS RUMBLE STRIP(0.04%) WILLIS ELECTRIC CO., LP(0.64%) GARY A. CRAIN, INC.(0.15%) 76 MILLING, INC. (0.96%) HJC FARMS, INC.(0.22%) ADVANCED ENVIRONMENTAL SERVICES(1.75%) J.L. STEEL, L.P. (0.44%)
|
| Contract # |
04073209 |
|
Totals |
6964041.64 |
326617.96 |
4628679.23 |
66.4 |
|
| County | SCURRY |
| Highway |
BU 84-G |
| From |
SH 350 (COLLEGE AVE) |
| To |
US 180 (TRAFFIC CIRCLE IN SNYDER) |
| CSJ |
0053-17-024 |
| Proj ID |
STP 2008(199) |
| Work Type |
FL BS, ACP, STM SWR, C & G, SDWLKS, SGNLS |
| |
|
3.738 |
9665767.54 |
268578.36 |
3329463.63 |
34.4 |
| Work Order |
01-10-08 |
| Work Began |
01-22-08 |
| Work Completed |
|
| Time Computed |
01-22-08 |
| Contract Working Days |
412 |
| Addl Days Granted |
0 |
| Working Days Charged |
172 |
| Percent Time Used |
41 |
| Contractor(s) |
| CONTRACT PAVING CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0053-17-024 CRAWFORD YANT(0.17%) TEXAS HIGHWAY MARKINGS, LLC(1.04%) W.S. CONSTRUCTION COMPANY( 11.95%) WILLIS ELECTRIC CO., LP(3.65%)
|
| Contract # |
12073003 |
|
Totals |
9665767.54 |
268578.36 |
3329463.63 |
34.4 |
|
| County | TAYLOR |
| Highway |
US 84 |
| From |
AT EAST JIM NED CREEK |
| To |
(STR 1) |
| CSJ |
0054-01-022 |
| Proj ID |
BR 2008(467) |
| Work Type |
REHABILITATE BRIDGE |
| |
|
1.045 |
7528118.31 |
85980.00 |
1991217.54 |
26.4 |
| Work Order |
04-08-08 |
| Work Began |
06-25-08 |
| Work Completed |
|
| Time Computed |
06-07-08 |
| Contract Working Days |
487 |
| Addl Days Granted |
0 |
| Working Days Charged |
86 |
| Percent Time Used |
17 |
| Contractor(s) |
| J. H. STRAIN & SONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0054-01-022 TEXAS SHAFTS, INC. (3.46%) CONTRACTORS SERVICE COMPANY(0.68%) HJC FARMS, INC.(4.40%) TEXAS HIGHWAY MARKINGS, LLC(2.35%) GARY A. CRAIN, INC.(0.20%) JAVELINA CONSTRUCTION SOUTH, INC.(0.50%) ROADWAY TECHNOLOGIES, LLC. (0.32%)
|
| Contract # |
02083204 |
|
Totals |
7528118.31 |
85980.00 |
1991217.54 |
26.4 |
|
| County | SCURRY |
| Highway |
US 180 |
| From |
AT MOOAR CREEK |
| To |
. |
| CSJ |
0295-04-043 |
| Proj ID |
BR 2009(057) |
| Work Type |
REHABILITATE BRIDGE AND APPROACHES |
| |
|
1.174 |
906554.30 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
110 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| AJAX EQUIPMENT COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0295-04-043 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10083010 |
|
Totals |
906554.30 |
0.00 |
0.00 |
0.0 |
|
| County | NOLAN |
| Highway |
US 277 |
| From |
AT FISH CREEK |
| To |
(PSN 12) |
| CSJ |
0407-03-010 |
| Proj ID |
BR 2008(722) |
| Work Type |
REPLACE BRIDGE |
| |
|
0.100 |
941747.68 |
0.00 |
0.00 |
0.0 |
| County | TAYLOR |
| Highway |
FM 89 |
| From |
ON FM 89 |
| To |
AT ELM CREEK |
| CSJ |
2935-01-009 |
| Proj ID |
BR 2008(722) |
| Work Type |
REPLACE BRIDGE |
| |
|
0.100 |
1036437.89 |
49499.79 |
85710.43 |
8.2 |
| County | TAYLOR |
| Highway |
FM 89 |
| From |
AT ELM CREEK |
| To |
(PSN 3) |
| CSJ |
2935-01-010 |
| Proj ID |
BR 2008(722) |
| Work Type |
REPLACE BRIDGE |
| |
|
0.001 |
1194489.68 |
74004.77 |
74004.77 |
6.1 |
| Work Order |
09-09-08 |
| Work Began |
10-29-08 |
| Work Completed |
|
| Time Computed |
10-29-08 |
| Contract Working Days |
366 |
| Addl Days Granted |
0 |
| Working Days Charged |
3 |
| Percent Time Used |
0 |
| Contractor(s) |
| BAKER BRIDGE, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 2935-01-009 CONTRACTORS SERVICE COMPANY(0.70%) JUST GROOVING, LTD.(0.18%) M & D CONSTRUCTION COMPANY, INC. (3.06%) STEPHENS MARTIN PAVING, L.P. (4.32%) TOTAL HIGHWAY MAINTENANCE, LLC (0.74%) DUSTROL, INC. (ROANOKE)(0.43%) LANCO TURF & SEEDING, INC. (0.30%) ROADWAY TECHNOLOGIES, LLC. (0.33%) LEO VENTURES (5.88%)
|
| Contract # |
07083009 |
|
Totals |
3172675.25 |
123504.56 |
159715.20 |
5.0 |
|
| County | TAYLOR |
| Highway |
FM 1235 |
| From |
US 277 |
| To |
FM 89 |
| CSJ |
0663-04-011 |
| Proj ID |
STP 2007(425) |
| Work Type |
EXC, EMB, STRS, FL BS, WIDN, SURF, & SAFE |
| |
|
8.617 |
3196930.50 |
8869.80 |
3040789.73 |
95.1 |
| Work Order |
10-29-07 |
| Work Began |
11-27-07 |
| Work Completed |
|
| Time Computed |
11-14-07 |
| Contract Working Days |
208 |
| Addl Days Granted |
0 |
| Working Days Charged |
179 |
| Percent Time Used |
86 |
| Contractor(s) |
| STEPHENS MARTIN PAVING, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0663-04-011 CONTRACTORS SERVICE COMPANY(0.59%) HJC FARMS, INC.(0.98%) HIGHWAY TECHNOLOGIES (0.00%) J.V. CONCRETE CONSTRUCTION ( 14.20%) MURRAY CONSTRUCTION(1.14%) TEXAS MULCHERS ENVIRONMENTAL SERVICES(0.06%) NITE LITE, INC.(3.87%)
|
| Contract # |
09073210 |
|
Totals |
3196930.50 |
8869.80 |
3040789.73 |
95.1 |
|
| County | SCURRY |
| Highway |
CR |
| From |
ON CR 195 |
| To |
AT DEEP CREEK (PSN 2) |
| CSJ |
0908-19-018 |
| Proj ID |
BR 2006(873) |
| Work Type |
REPLACE BR AND APPRS |
| |
|
0.067 |
271326.30 |
-10440.00 |
150903.75 |
72.4 |
| County | SCURRY |
| Highway |
CR |
| From |
ON CR 136 |
| To |
AT BIG SULPHUR CREEK (PSN 1) |
| CSJ |
0908-19-019 |
| Proj ID |
BR 2006(874) |
| Work Type |
REPLACE BR AND APPRS |
| |
|
0.069 |
310396.45 |
-30430.40 |
214633.00 |
69.1 |
| County | SCURRY |
| Highway |
CR |
| From |
CR 245 |
| To |
AT CANYON CK (PSN 1) |
| CSJ |
0908-19-020 |
| Proj ID |
BR 2006(875) |
| Work Type |
REPLACE BRIDGE |
| |
|
0.069 |
293569.35 |
0.00 |
209800.57 |
71.4 |
| County | KENT |
| Highway |
CR |
| From |
CR 142 |
| To |
AT STINKING CREEK (PSN 2) |
| CSJ |
0908-27-003 |
| Proj ID |
BR 2006(848) |
| Work Type |
REPLACE BRIDGE |
| |
|
0.064 |
235096.10 |
63732.00 |
161687.50 |
68.7 |
| Work Order |
09-14-07 |
| Work Began |
01-15-08 |
| Work Completed |
|
| Time Computed |
11-13-07 |
| Contract Working Days |
141 |
| Addl Days Granted |
14 |
| Working Days Charged |
212 |
| Percent Time Used |
136 |
| Contractor(s) |
| BAKER BRIDGE, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0908-19-018 CONTRACTORS SERVICE COMPANY(1.30%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.60%) STEPHENS MARTIN PAVING, L.P. (0.95%) HJC FARMS, INC.(8.67%)
|
| Contract # |
08073241 |
|
Totals |
1110388.20 |
22861.60 |
737024.82 |
70.4 |
|
| County | NOLAN |
| Highway |
CR |
| From |
ON CR 143 |
| To |
AT SEALE CREEK (PSN 2) |
| CSJ |
0908-20-019 |
| Proj ID |
BR 2006(868) |
| Work Type |
REPLACE BR AND APPRS |
| |
|
0.100 |
306813.55 |
4851.00 |
230874.00 |
75.2 |
| County | FISHER |
| Highway |
CR |
| From |
ON CR 157 |
| To |
AT PLUM CREEK |
| CSJ |
0908-23-018 |
| Proj ID |
BR 2006(793) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.087 |
533059.70 |
8928.00 |
411538.00 |
83.9 |
| County | FISHER |
| Highway |
CR |
| From |
CR 245 |
| To |
AT CLEAR FORK OF BRAZOS (PSN 1) |
| CSJ |
0908-23-019 |
| Proj ID |
BR 2006(794) |
| Work Type |
REHABILITATE BRIDGE AND APPROACHES |
| |
|
0.067 |
289612.65 |
450.00 |
205722.00 |
71.0 |
| County | FISHER |
| Highway |
CR |
| From |
ON CR 278 |
| To |
AT DRAW (PSN 1) |
| CSJ |
0908-23-020 |
| Proj ID |
BR 2006(795) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.063 |
201970.55 |
0.00 |
185408.70 |
91.7 |
| Work Order |
09-14-07 |
| Work Began |
01-03-08 |
| Work Completed |
|
| Time Computed |
11-13-07 |
| Contract Working Days |
161 |
| Addl Days Granted |
8 |
| Working Days Charged |
214 |
| Percent Time Used |
126 |
| Contractor(s) |
| BAKER BRIDGE, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0908-23-018 CONTRACTORS SERVICE COMPANY(1.04%) STEPHENS MARTIN PAVING, L.P. (1.03%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.11%) HJC FARMS, INC.(8.32%)
|
| Contract # |
08073237 |
|
Totals |
1331456.45 |
14229.00 |
1033542.70 |
80.3 |
|
| County | HASKELL |
| Highway |
CR ETC |
| From |
ON CR 181 (PSN 1) |
| To |
AT PAINT CREEK |
| CSJ |
0908-22-011 |
| Proj ID |
BR 2007(470) |
| Work Type |
REPLACE BRIDGE & APPROACHES |
| |
|
0.380 |
1574189.65 |
0.00 |
14700.00 |
0.9 |
| Work Order |
09-09-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
09-25-08 |
| Contract Working Days |
246 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| BAKER BRIDGE, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0908-22-011 CONTRACTORS SERVICE COMPANY(1.25%) LEO VENTURES (8.17%) S & S BRIDGE PAINTING(0.19%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.30%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (5.56%) PENHALL COMPANY (AUSTIN) (0.18%)
|
| Contract # |
07083017 |
|
Totals |
1574189.65 |
0.00 |
14700.00 |
0.9 |
|
| County | TAYLOR |
| Highway |
CS |
| From |
NORTH ENTRANCE OF DYESS AFB |
| To |
FM 3438 |
| CSJ |
0908-33-066 |
| Proj ID |
STP 2001(870) |
| Work Type |
RECONSTRUCT CITY STREET |
| |
|
2.359 |
4667902.96 |
275568.83 |
275568.83 |
5.9 |
| Work Order |
09-25-08 |
| Work Began |
10-11-08 |
| Work Completed |
|
| Time Computed |
10-11-08 |
| Contract Working Days |
234 |
| Addl Days Granted |
0 |
| Working Days Charged |
10 |
| Percent Time Used |
4 |
| Contractor(s) |
| CONTRACT PAVING CO. |
SUBCONTRACTOR(S) FOR CCSJ: 0908-33-066 WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.11%) SHANNON YOUNG CO., INC.(6.15%) HIGHWAY TECHNOLOGIES, L.P. (1.00%) WILLIS ELECTRIC CO., LP(0.41%) KIOWA PEAK INDUSTRIES INC(0.74%) SD TRUCKING(2.46%) REYNALDO GARCIA(0.04%) ROLANDO GARZA TRUCKING (0.27%) CARMONA TRUCKING (0.04%) P. ARREOLA TRUCKING(0.09%) GONZALES TRUCKING(0.18%) ARNULFO M. ARIZMENDI TRUCKING(0.32%) RRR TRUCKING, LLC. (0.23%) ROBERTO D. MORALES TRUCKING(0.04%) S & G TRUCKING (0.09%) GARCIA'S TRUCKING(0.04%) M.A. GARZA TRUCKING(0.13%) GARZA'S TRUCKING (0.13%) J E DEHOYOS TRUCKING (0.04%)
|
| Contract # |
08083209 |
|
Totals |
4667902.96 |
275568.83 |
275568.83 |
5.9 |
|
| County | JONES |
| Highway |
FM 1082 |
| From |
US 277 EAST FRONTAGE ROAD |
| To |
FM 1226 IN HAWLEY |
| CSJ |
0975-02-019 |
| Proj ID |
STP 2009(006) |
| Work Type |
EXC, EMB, STR, RIPRAP, EROSION CONTROL |
| |
|
0.738 |
719047.75 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-27-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
11-12-08 |
| Contract Working Days |
117 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| BEAR CREEK CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0975-02-019 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09083019 |
|
Totals |
719047.75 |
0.00 |
0.00 |
0.0 |
|