Monthly State Let Construction Report For Abilene District As Of May 15, 2013 Page 1 Of 2

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyHOWARD
Highway IH 20
From AT US 87 (NEW LOCATION)
To .
CSJ 0005-05-102
Proj ID DMO 2012(263)
Work Type CONSTRUCT NEW INTERCHANGE
 
2.719 18434933.58 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 01-01-14
Contract Working Days 470
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DELHUR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0005-05-102
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133202
Totals 18434933.58 0.00 0.00 0.0

CountyHOWARD
Highway BI 20-G
From US 87
To SH 350
CSJ 0005-10-015
Proj ID STP 2012(144)
Work Type PLAN, ASB, ACP, SIDWLK, AND PAV MRK
 
0.652 3812216.32 592744.38 3248127.57 85.2
Work Order 02-06-12
Work Began 04-11-12
Work Completed  
Time Computed 04-09-12
Contract Working Days 193
Addl Days Granted 40
Working Days Charged 225
Percent Time Used 96
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-10-015
JAVELINA CONSTRUCTION SOUTH, INC.(1.27%)
NITE LITE, INC.(1.44%)
WILLIS ELECTRIC CO., LP( 12.56%)
W.S. CONSTRUCTION COMPANY( 20.82%)
TEX OP CONSTRUCTION, LP(0.79%)
UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(0.56%)
TOTAL HIGHWAY MAINTENANCE, LLC (1.46%)
Contract # 12113221
Totals 3812216.32 592744.38 3248127.57 85.2

CountyHOWARD
Highway BI 20-G
From NEAR JONES STREET IN BIG SPRING
To US 87
CSJ 0005-10-016
Proj ID DMO 2013(423)
Work Type REHABILITATION, ACP, SIDEWALKS
 
1.092 5646935.90 387514.08 387514.08 6.8
Work Order 03-12-13
Work Began 04-04-13
Work Completed  
Time Computed 03-28-13
Contract Working Days 170
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 13
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0005-10-016
CONTRACTORS SERVICE COMPANY(0.30%)
TEX OP CONSTRUCTION, LP(2.51%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.91%)
WILLIS ELECTRIC CO., LP(0.29%)
W.S. CONSTRUCTION COMPANY( 23.45%)
Contract # 01133206
Totals 5646935.90 387514.08 387514.08 6.8

CountyNOLAN
Highway IH 20 ETC
From LAMAR ST ON RAMP (FTG RDS ONLY)
To HOPKINS RD OFF RAMP
CSJ 0006-02-108
Proj ID STP 2013(149)
Work Type SEAL COAT
 
88.478 3445319.70 0.00 714850.44 20.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-03-12
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-02-108
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11123018
Totals 3445319.70 0.00 714850.44 20.7

CountyTAYLOR
Highway IH 20
From PINE STREET
To LP 322__(FRONTAGE ROADS ONLY)
CSJ 0006-06-093
Proj ID IM 0202(234)
Work Type SUBGR, FL BS, C & G, SURF, SGNS, ILLUM, SGL
 
3.961 12481302.25 1474371.39 5000638.65 40.0
Work Order 08-28-12
Work Began 10-25-12
Work Completed  
Time Computed 10-25-12
Contract Working Days 416
Addl Days Granted 0
Working Days Charged 111
Percent Time Used 26
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-06-093
WILLIS ELECTRIC CO., LP(5.88%)
TEXAS ALTERNATIVE GRASSER, INC.(0.10%)
CONTRACTORS SERVICE COMPANY(0.67%)
D. I. J. CONSTRUCTION, INC.(1.08%)
RPV CONSTRUCTION (2.48%)
KARMY CONSTRUCTION INC (8.14%)
FARR FOUNDATION, INC.(0.82%)
Contract # 06123002
Totals 12481302.25 1474371.39 5000638.65 40.0

CountyCALLAHAN
Highway IH 20
From AT FM 603
To .
CSJ 0006-07-072
Proj ID IM 0202(239)G
Work Type SAFETY LIGHTING
 
1.945 443023.24 52821.00 52821.00 11.9
Work Order 02-22-13
Work Began 00-00-00
Work Completed  
Time Computed 05-23-13
Contract Working Days 67
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HIGHWAY INTELLIGENT TRAFFIC SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-07-072
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (4.33%)
Contract # 12123011
Totals 443023.24 52821.00 52821.00 11.9

CountyTAYLOR
Highway BI 20-R
From AT RAINY CREEK (PSN 49)
To .
CSJ 0006-18-051
Proj ID BR 2013(370)
Work Type BRIDGE REPLACEMENT
 
1.187 2400617.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-10-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 217
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
REECE CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0006-18-051
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133029
Totals 2400617.08 0.00 0.00 0.0

CountySCURRY
Highway US 84
From EAST OF HERMLEIGH
To NEAR BU 84-G E OF SNYDER (WB ONLY)
CSJ 0053-09-069
Proj ID NH 2013(487)
Work Type DEEP MILL FILL DR LN, SEAL, OVERLAY
 
7.013 2338232.48 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 38
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CONTRACT PAVING CO.
SUBCONTRACTOR(S) FOR CCSJ: 0053-09-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03133231
Totals 2338232.48 0.00 0.00 0.0

CountySHACKELFORD
Highway FM 601
From AT HUBBARD CREEK
To .
CSJ 0107-03-013
Proj ID BR 2013(520)
Work Type REHABILITATE BRIDGE
 
0.107 545125.27 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 88
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0107-03-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133025
Totals 545125.27 0.00 0.00 0.0

CountyHASKELL
Highway US 277
From FM 618
To NEAR BU 277-F (SBL ONLY)
CSJ 0157-04-045
Proj ID STP 2013(371)
Work Type MILLING, SPOT BASE REP & SURFACING
 
8.357 3020841.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-03-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0157-04-045
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133017
Totals 3020841.60 0.00 0.00 0.0

CountyNOLAN
Highway BS 70-G
From AVENUE B IN SWEETWATER
To IH 20
CSJ 0264-01-036
Proj ID STP 2013(372)
Work Type REHABILITATION, ACP, SIDEWALKS
 
1.287 6493251.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 318
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0264-01-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133222
Totals 6493251.00 0.00 0.00 0.0

CountyNOLAN
Highway SH 70
From SH 153
To APPROX 1.85 MI SOUTH OF FM 1809
CSJ 0264-02-026
Proj ID STP 2012(441)
Work Type ACP OVERLAY
 
10.532 2989281.52 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-23-13
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NOBLES ROAD CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0264-02-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133022
Totals 2989281.52 0.00 0.00 0.0

CountyTAYLOR
Highway VA
From VARIOUS LOCATIONS IN
To THE ABILENE DISTRICT
CSJ 0908-00-078
Proj ID STP 2013(310)
Work Type CURB RAMPS
 
1.000 345815.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-15-13
Work Began 00-00-00
Work Completed  
Time Computed 05-01-13
Contract Working Days 126
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-00-078
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01133023
Totals 345815.00 0.00 0.00 0.0

CountyFISHER
Highway CR
From CR 135
To AT COTTONWOOD CK
CSJ 0908-23-031
Proj ID BR 2011(765)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.060 211697.50 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 59
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-23-031
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05133014
Totals 211697.50 0.00 0.00 0.0

CountyFISHER
Highway CR
From CR 246
To AT CLEAR FORK BRAZOS
CSJ 0908-23-032
Proj ID BR 2011(766)
Work Type REPLACE BRIDGE
 
0.084 276103.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-23-032
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133016
Totals 276103.90 0.00 0.00 0.0

CountyFISHER
Highway CR
From ON CR 322 (160)
To AT CLEAR FORK OF BRAZOS (PSN 1)
CSJ 0908-23-033
Proj ID BR 2011(767)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.001 254268.88 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-23-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133214
Totals 254268.88 0.00 0.00 0.0

CountyJONES
Highway VA
From FORT PHANTOM HILL_VISITOR CENTER
To .
CSJ 0908-24-036
Proj ID STP 2000(517)TE
Work Type SCENIC OR HISTORIC HIGHWAY PROGRAM
 
0.001 649700.00 0.00 569827.00 87.7
Work Order 03-05-12
Work Began 03-13-12
Work Completed  
Time Computed 03-21-12
Contract Working Days 180
Addl Days Granted 0
Working Days Charged 125
Percent Time Used 69
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0908-24-036
JUSTICE CONSTRUCTION COMPANY ( 61.56%)
BONTKE BROTHERS CONSTRUCTION COMPANY (2.53%)
KELLEY MASONRY, INC. ( 11.46%)
WYATT ELECTRICAL SERVICES, INC.(3.30%)
LONGMIRE PLUMBING, INC.(3.82%)
SOUTHWEST AIR CONDITIONING & HEATING (2.01%)
DEAN HAGLER, INC.(0.19%)
Contract # 01123228
Totals 649700.00 0.00 569827.00 87.7

CountyHOWARD
Highway FM 1785
From ON FM 1785
To AT PLUM CREEK
CSJ 1155-03-009
Proj ID BR 2013(521)
Work Type REPLACE BRIDGE AND APPROACHES
 
0.001 633633.67 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 128
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1155-03-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04133220
Totals 633633.67 0.00 0.00 0.0

CountyTAYLOR
Highway LP 322
From IH 20 SOUTH FTG RD
To CEDAR CREEK
CSJ 2398-01-046
Proj ID NH 2013(373)
Work Type SPOT BASE RPR, UND SL, OV, MBGF
 
5.959 3787564.95 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 92
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. H. STRAIN & SONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2398-01-046
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02133213
Totals 3787564.95 0.00 0.00 0.0

CountyMITCHELL
Highway FM 670
From AT GLAZE CREEK
To .
CSJ 2471-01-009
Proj ID BR 2012(679)
Work Type REPLACE BRIDGE
 
0.001 782134.95 170343.70 602629.24 77.0
Work Order 09-24-12
Work Began 12-04-12
Work Completed  
Time Computed 10-10-12
Contract Working Days 127
Addl Days Granted 0
Working Days Charged 107
Percent Time Used 84
Contractor(s)
A GREATER AUSTIN DEVELOPMENT CONCRETE CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 2471-01-009
WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(2.78%)
HJC FARMS, INC.(2.05%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.17%)
SOUTHEAST GRINDING & GROOVING, LLC (0.56%)
HIGHWAY TECHNOLOGIES, INC. (1.04%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(2.04%)
NOBLES ROAD CONSTRUCTION, INC. ( 18.12%)
NORTH TEXAS REBAR, LLC (0.19%)
Contract # 08123030
Totals 782134.95 170343.70 602629.24 77.0

page 1 | page 2