Monthly Local Let Maintenance Report For Fort Worth District As Of Feb 09, 2018 Page 5 Of 6

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyTARRANT
HighwayIH0035W
FromSPECIAL MAINTENANCE
ToWAGGOMAN STREET
CSJ6315-33-001
Proj IDSUP - 631533001
Work TypeJANITORIAL MAINTENCANCE
 
0.0108526.606394.9575.0
Work Order00-00-00
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged300
Percent Time Used82
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6315-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04170231
Totals8526.60710.556394.9575.0

CountyJOHNSON
HighwayUS0067
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6315-64-001
Proj IDSUP - 631564001
Work TypeLITTER REMOVAL
 
0.010193333.86106687.7655.1
Work Order09-15-17
Work Began09-25-17
Work Completed
Time Computed09-22-17
Contract Working Days365
Addl Days Granted0
Working Days Charged147
Percent Time Used40
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170231
Totals193333.8622817.53106687.7655.1

CountyWISE
HighwayUS0081
FromLITTER REMOVAL WITHIN
ToWISE & JACK COUNTIES
CSJ6315-65-001
Proj IDSUP - 631565001
Work TypeLITTER REMOVAL
 
0.010221679.5478106.7135.2
Work Order09-12-17
Work Began09-13-17
Work Completed
Time Computed09-13-17
Contract Working Days365
Addl Days Granted0
Working Days Charged136
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170232
Totals221679.5416040.6678106.7135.2

CountyTARRANT
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6315-66-001
Proj IDSUP - 631566001
Work TypeLITTER REMOVAL
 
0.010482216.16195229.0040.4
Work Order00-00-00
Work Began09-05-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged147
Percent Time Used40
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170233
Totals482216.1645886.38195229.0040.4

CountySOMERVELL
HighwayUS0067
FromVARIOUS ROADWAYS IN HOOD, SOMERVELL &
ToERATH COUNTIES
CSJ6315-67-001
Proj IDSUP - 631567001
Work TypeLITTER REMOVAL
 
0.010143861.0055275.9538.4
Work Order09-19-17
Work Began09-26-17
Work Completed
Time Computed09-26-17
Contract Working Days365
Addl Days Granted0
Working Days Charged178
Percent Time Used48
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170234
Totals143861.0012571.1855275.9538.4

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS IN PARKER AND
ToPALO PINTO COUNTIES
CSJ6315-68-001
Proj IDSUP - 631568001
Work TypeLITTER REMOVAL
 
0.010293917.44121077.4141.1
Work Order09-15-17
Work Began09-22-17
Work Completed
Time Computed09-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged137
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-68-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170235
Totals293917.4421529.44121077.4141.1

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6315-69-001
Proj IDSUP - 631569001
Work TypeLITTER REMOVAL
 
0.010391997.62137429.1235.0
Work Order09-14-17
Work Began09-15-17
Work Completed
Time Computed09-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged128
Percent Time Used35
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-69-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170236
Totals391997.6227756.74137429.1235.0

CountyJOHNSON
HighwayUS0067
FromJOHNSON COUNTY
ToWITHIN CITY LIMITS
CSJ6315-82-001
Proj IDSUP - 631582001
Work TypeLANDSCAPING MAINTENANCE
 
0.01017700.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-17
Work Began06-01-17
Work Completed
Time Computed12-07-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05170231
Totals17700.000.000.000.0

CountyJOHNSON
HighwayFM2280
FromKEENE MAINTENANCE
ToOFFICE
CSJ6315-86-001
Proj IDSUP - 631586001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.01025095.002020.008.0
Work Order00-00-00
Work Began12-04-17
Work Completed
Time Computed12-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged57
Percent Time Used15
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11170231
Totals25095.001010.002020.008.0

CountyWISE
HighwayUS0081
FromUS DECATUR,OFFICE JACKSBORO OFFICE, OLD
ToAREA OFFICE, JACKSBORO MAINTENANCE YARD
CSJ6315-87-001
Proj IDSUP - 631587001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.01062450.009000.0014.4
Work Order11-03-17
Work Began11-03-17
Work Completed
Time Computed11-09-17
Contract Working Days365
Addl Days Granted0
Working Days Charged85
Percent Time Used23
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6315-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10170231
Totals62450.003000.009000.0014.4

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN JOHNSON
ToCOUNTY
CSJ6316-02-001
Proj IDRMC - 631602001
Work TypeCLEANING AND SEALING JOINTS & CRACKS
 
0.010205978.00183928.4089.2
Work Order10-30-17
Work Began11-14-17
Work Completed
Time Computed11-06-17
Contract Working Days43
Addl Days Granted0
Working Days Charged17
Percent Time Used39
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170201
Totals205978.00106176.40183928.4089.2

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATIONS IN
ToPARKER AND PALO PINTO
CSJ6316-03-001
Proj IDRMC - 631603001
Work TypeSWEEPING AND DEBRIS
 
0.010286745.3381499.6528.4
Work Order10-04-17
Work Began10-04-17
Work Completed
Time Computed10-04-17
Contract Working Days365
Addl Days Granted120
Working Days Charged120
Percent Time Used24
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6316-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170203
Totals286745.3312820.2081499.6528.4

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6316-15-001
Proj IDRMC - 631615001
Work TypeCALL OUT REFLEC PVMT MRKGS & MRKRS
 
0.010256350.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days88
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10170201
Totals256350.000.000.000.0

CountyJOHNSON
HighwayIH0035W
FromJOHNSON COUNTY
To.
CSJ6316-30-001
Proj IDRMC - 631630001
Work TypeSWEEPING AND DEBRIS REMOVAL JOHNSON CO
 
0.010138385.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DEMENT ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-30-001
TEXAS TMA RENTAL (100.00)
Contract #12170201
Totals138385.400.000.000.0

CountyTARRANT
HighwayIH0020
FromRUSH CREEK
ToBOWEN ROAD
CSJ6316-31-001
Proj IDRMC - 631631001
Work TypeASBESTOS ABATEMENT OF BRIDGE RAILING
 
0.010313167.50276133.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-09-17
Work Completed11-27-17
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged25
Percent Time Used55
Contractor(s)
SCR CIVIL CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-31-001
1 PRIORITY ENVIRONMENTAL SERVICES, INC. (56.20)
ALTUS TRAFFIC MANAGEMENT LLC (2.35)
Contract #07170205
Totals313167.500.00276133.00100.0

CountyWISE
HighwayUS0380
FromVARIOUS LOCATIONS IN WISE & JACK COUNTY
ToMAINTENANCE AREAS
CSJ6316-56-001
Proj IDRMC - 631656001
Work TypeTREE & BRUSH TRIMMING AND REMOVAL
 
0.100350500.0072790.0020.7
Work Order10-25-17
Work Began11-02-17
Work Completed
Time Computed11-02-17
Contract Working Days110
Addl Days Granted0
Working Days Charged40
Percent Time Used36
Contractor(s)
BOEN LANDSCAPING & IRRIGATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6316-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170201
Totals350500.0018145.0072790.0020.7

CountyWISE
HighwayUS0081
FromVARIOUS LOCATIONS WITHIN WISE
ToAND JACK CONTIES
CSJ6318-04-001
Proj IDSUP - 631804001
Work TypePICNIC AREA MAINTENANCE
 
0.01056810.002325.00100.0
Work Order01-04-18
Work Began01-05-18
Work Completed11-30-17
Time Computed01-05-18
Contract Working Days365
Addl Days Granted0
Working Days Charged22
Percent Time Used6
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6318-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170231
Totals56810.002325.002325.00100.0

CountySOMERVELL
HighwayUS0067
FromVARIOUS LOCATIONS IN HOO, SOMERVELL
ToAND ERATH COUNTIES
CSJ6318-05-001
Proj IDSUP - 631805001
Work TypePICNIC AREA MAINTENANCE
 
0.010114036.346131.735.3
Work Order01-02-18
Work Began01-03-18
Work Completed
Time Computed01-03-18
Contract Working Days365
Addl Days Granted0
Working Days Charged25
Percent Time Used6
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12170232
Totals114036.346131.736131.735.3

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATION WITHIN PARKER
To& PALO PINTO COUNTIES
CSJ6318-06-001
Proj IDSUP - 631806001
Work TypePICNIC AREA MAINTENANCE
 
0.01077143.20883.071.1
Work Order01-15-18
Work Began01-15-18
Work Completed
Time Computed01-15-18
Contract Working Days358
Addl Days Granted0
Working Days Charged11
Percent Time Used3
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6318-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01180231
Totals77143.20883.07883.071.1

CountyPARKER
HighwayIH0020
FromVARIOUS ROADS IN
ToPARKER / PALO PINTO
CSJ6318-28-001
Proj IDRMC - 631828001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
116.000239500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days137
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
WESTGATE GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6318-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08170202
Totals239500.000.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6