Monthly Local Let Maintenance Report For Fort Worth District As Of Feb 09, 2018 Page 3 Of 6

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHOOD
HighwayUS0377
FromVARIOUS ROADWAYS IN HOOD AND
ToSOMERVELL COUNTIES
CSJ6294-99-001
Proj IDRMC - 629499001
Work TypeROADSIDE MOWING
 
0.010242961.36221040.10100.0
Work Order05-16-16
Work Began05-16-16
Work Completed01-10-18
Time Computed05-23-16
Contract Working Days64
Addl Days Granted44
Working Days Charged102
Percent Time Used94
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6294-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150204
Totals242961.3627712.54221040.10100.0

CountyWISE
HighwayUS0081
FromWISE & JACK COUNTY
ToMAINTENANCE OFFICES AND YARDS
CSJ6295-54-001
Proj IDSUP - 629554001
Work TypeGROUNDS MAINTENANCE
 
0.01022860.0033210.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-15-16
Work Began03-20-16
Work Completed
Time Computed03-22-16
Contract Working Days365
Addl Days Granted0
Working Days Charged222
Percent Time Used60
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6295-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150233
Totals22860.000.0033210.0099.9

CountyPARKER
HighwayIH0020
FromVARIOUS LOCATION WITHIN PARKER &
ToPALO PINTO COUNTIES
CSJ6295-61-001
Proj IDSUP - 629561001
Work TypePICNIC_AREA MAINTENANCE
 
0.01071135.6268252.6095.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-01-16
Work Began01-01-16
Work Completed
Time Computed01-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6295-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150232
Totals71135.620.0068252.6095.9

CountyTARRANT
HighwayUS0287
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6296-05-001
Proj IDRMC - 629605001
Work TypeFULL-WIDTH MOWING
 
0.010325410.30312607.4096.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-17-16
Work Began05-17-16
Work Completed
Time Computed05-24-16
Contract Working Days56
Addl Days Granted0
Working Days Charged48
Percent Time Used85
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150205
Totals325410.300.00312607.4096.2

CountyTARRANT
HighwayIH0035W
FromVARIOUS ROADWAYS IN
ToSOUTH TARRANT COUNTY
CSJ6296-37-001
Proj IDRMC - 629637001
Work TypeCALL-OUT THERMO
 
0.010275156.50266048.46100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-16
Work Began10-05-16
Work Completed11-27-17
Time Computed10-03-16
Contract Working Days106
Addl Days Granted0
Working Days Charged67
Percent Time Used63
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160205
Totals275156.500.00266048.46100.0

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS IN PARKER, PALO PINTO,
ToAND ERATH COUNTIES
CSJ6296-63-001
Proj IDRMC - 629663001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010309572.40409982.2099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-25-16
Work Began04-01-16
Work Completed
Time Computed04-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged305
Percent Time Used83
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150206
Totals309572.400.00409982.2099.9

CountyJACK
HighwayUS0380
FromVARIOUS ROADWAYS IN
ToJACK COUNTY
CSJ6297-09-001
Proj IDRMC - 629709001
Work TypeROADSIDE MOWING
 
0.010241384.05215932.52100.0
Work Order06-29-16
Work Began06-15-16
Work Completed01-03-18
Time Computed07-07-16
Contract Working Days64
Addl Days Granted28
Working Days Charged92
Percent Time Used100
Contractor(s)
FOUR R OILFIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150203
Totals241384.0547332.01215932.52100.0

CountyERATH
HighwayBU0377J
FromVARIOUS ROADWAYS IN ERATH, HOOD,
ToSOMERVELL, & PARKER COUNTIES
CSJ6297-14-001
Proj IDRMC - 629714001
Work TypeCALLOUT REFLECTORIZED PVMNT MRKS & MRKR
 
0.010184315.00281602.2099.9
Work Order09-13-16
Work Began09-13-16
Work Completed
Time Computed09-15-16
Contract Working Days53
Addl Days Granted5
Working Days Charged48
Percent Time Used82
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160206
Totals184315.0024879.10281602.2099.9

CountyJOHNSON
HighwaySH0174
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6297-54-001
Proj IDRMC - 629754001
Work TypeCALL OUT REFLEC PAV MRKGS & MRKRS
 
0.010264215.00235440.6589.1
Work Order04-28-17
Work Began09-27-16
Work Completed
Time Computed09-27-16
Contract Working Days86
Addl Days Granted0
Working Days Charged38
Percent Time Used44
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160203
Totals264215.0011420.50235440.6589.1

CountyPARKER
HighwayIH0020
FromWEATHERFORD/MINERAL WELLS OFFICES &
ToGORDON LOCATION
CSJ6298-59-001
Proj IDSUP - 629859001
Work TypeJANITORIAL & GROUNDS WORK MAINTENANCE
 
0.01063455.1255225.1287.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-25-16
Work Began02-01-16
Work Completed
Time Computed02-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged360
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6298-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160231
Totals63455.120.0055225.1287.0

CountyTARRANT
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6298-99-001
Proj IDSUP - 629899001
Work TypeLANDSCAPE MAINTENANCE
 
0.010105030.00105030.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-16
Work Began04-05-16
Work Completed
Time Computed04-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged53
Percent Time Used14
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6298-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160231
Totals105030.000.00105030.0099.9

CountyERATH
HighwayBU0377J
FromVARIOUS ROADWAYS IN ERATH, HOOD,
ToAND SOMERVELL COUNTIES
CSJ6299-81-001
Proj IDRMC - 629981001
Work TypeRUMBLE STRIP
 
0.010196000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09160201
Totals196000.000.000.000.0

CountyWISE
HighwayUS0380
FromVARIOUS LOCATIONS IN WISE AND JACK
ToCOUNTIES
CSJ6299-90-001
Proj IDRMC - 629990001
Work TypeGUARDRAIL INSTALLATION AND REPAIR
 
0.100347400.00321553.50100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-31-16
Work Began10-31-16
Work Completed11-15-17
Time Computed11-10-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
MARCOM'S MOWING SERVICE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160201
Totals347400.000.00321553.50100.0

CountyWISE
HighwayUS0081
FromVARIOUS LOCATIONS IN
ToWISE COUNTY
CSJ6299-91-001
Proj IDRMC - 629991001
Work TypeDEBRIS REMOVAL
 
0.010194817.00142224.5073.0
Work Order07-19-16
Work Began07-26-16
Work Completed
Time Computed07-27-16
Contract Working Days180
Addl Days Granted0
Working Days Charged103
Percent Time Used57
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6299-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160202
Totals194817.003019.45142224.5073.0

CountyJOHNSON
HighwayIH0035W
FromVARIOUS ROADWAYS IN
ToJOHNSON COUNTY
CSJ6300-67-001
Proj IDRMC - 630067001
Work TypeCLEANING & SHAPING DITCHES KEENE FY17
 
0.010243000.00392524.2599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-25-16
Work Began09-27-16
Work Completed
Time Computed10-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged64
Percent Time Used17
Contractor(s)
TEXAS DRAINAGE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160201
Totals243000.000.00392524.2599.9

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS WITHIN PARKER
ToAND PALO PINTO COUNTIES
CSJ6301-31-001
Proj IDRMC - 630131001
Work TypeCALL OUT REFLEC PAV MRKGS PARKER
 
0.010255737.50229345.3089.6
Work Order07-11-16
Work Began07-17-16
Work Completed
Time Computed07-14-16
Contract Working Days89
Addl Days Granted0
Working Days Charged62
Percent Time Used69
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160206
Totals255737.50829.62229345.3089.6

CountyPALO PINTO
HighwayIH0020
FromCR 119
ToAT IH 20
CSJ6301-32-001
Proj IDRMC - 630132001
Work TypeBRIDGE REPAIR
 
0.01064725.0068992.9399.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-13-16
Work Began00-00-00
Work Completed
Time Computed10-20-16
Contract Working Days14
Addl Days Granted0
Working Days Charged7
Percent Time Used50
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6301-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160207
Totals64725.000.0068992.9399.9

CountyJOHNSON
HighwayIH0035W
FromJOHNSON COUNTY
To.
CSJ6301-97-001
Proj IDRMC - 630197001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010136860.80123788.90100.0
Work Order11-29-16
Work Began12-06-16
Work Completed01-25-18
Time Computed12-06-16
Contract Working Days365
Addl Days Granted31
Working Days Charged387
Percent Time Used97
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6301-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160205
Totals136860.808800.30123788.90100.0

CountyTARRANT
HighwayIH0035W
FromSPECIAL MAINTENANCE
ToWAGGOMAN STREET
CSJ6302-11-001
Proj IDSUP - 630211001
Work TypeJANITORIAL MAINTENANCE
 
0.0108336.048336.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6302-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160231
Totals8336.040.008336.0499.9

CountyTARRANT
HighwayIH0030
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6302-93-001
Proj IDRMC - 630293001
Work TypeCLEANING & SEALING JOINTS & CRACKS
 
0.010347656.40395102.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-14-16
Work Began00-00-00
Work Completed
Time Computed11-21-16
Contract Working Days45
Addl Days Granted0
Working Days Charged12
Percent Time Used26
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6302-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160204
Totals347656.400.00395102.0099.9

page 1 | page 2 | page 3 | page 4 | page 5 | page 6