Monthly Local Let Maintenance Report For Fort Worth District As Of Oct 16, 2017 Page 4 Of 6

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWISE
HighwayUS0380
FromVARIOUS LOCATIONS IN
ToWISE AND JACK COUNTIES
CSJ6301-45-001
Proj IDRMC - 630145001
Work TypeROUTINE SWEEPING
 
0.010394056.00373250.0094.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-29-16
Work Began08-01-16
Work Completed
Time Computed07-27-16
Contract Working Days365
Addl Days Granted0
Working Days Charged27
Percent Time Used7
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05160201
Totals394056.000.00373250.0094.7

CountyJOHNSON
HighwayIH0035W
FromJOHNSON COUNTY
To.
CSJ6301-97-001
Proj IDRMC - 630197001
Work TypeSWEEPING AND DEBRIS REMOVAL
 
0.010136860.8081102.7059.2
Work Order11-29-16
Work Began12-06-16
Work Completed
Time Computed12-06-16
Contract Working Days365
Addl Days Granted0
Working Days Charged268
Percent Time Used73
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6301-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160205
Totals136860.808600.3081102.7059.2

CountyTARRANT
HighwayIH0035W
FromSPECIAL MAINTENANCE
ToWAGGOMAN STREET
CSJ6302-11-001
Proj IDSUP - 630211001
Work TypeJANITORIAL MAINTENANCE
 
0.0108336.048336.0499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6302-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160231
Totals8336.040.008336.0499.9

CountyTARRANT
HighwayIH0030
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6302-93-001
Proj IDRMC - 630293001
Work TypeCLEANING & SEALING JOINTS & CRACKS
 
0.010347656.40395102.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-14-16
Work Began00-00-00
Work Completed
Time Computed11-21-16
Contract Working Days45
Addl Days Granted0
Working Days Charged12
Percent Time Used26
Contractor(s)
CHAMPION INFRASTRUCTURE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6302-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160204
Totals347656.400.00395102.0099.9

CountyJOHNSON
HighwayUS0067
FromVARIOUS ROADWAYS WITHIN
ToJOHNSON COUNTY
CSJ6303-10-001
Proj IDSUP - 630310001
Work TypeLITTER REMOVAL
 
0.010210810.78207217.3598.2
Work Order09-01-16
Work Began09-08-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged359
Percent Time Used98
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6303-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160231
Totals210810.780.00207217.3598.2

CountyWISE
HighwayUS0081
FromLITTER REMOVAL WITHIN
ToWISE & JACK COUNTIES
CSJ6303-11-001
Proj IDSUP - 630311001
Work TypeLITTER REMOVAL
 
0.010230985.30200985.3087.0
Work Order09-15-16
Work Began09-15-16
Work Completed
Time Computed09-27-16
Contract Working Days365
Addl Days Granted0
Working Days Charged338
Percent Time Used92
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6303-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160232
Totals230985.300.00200985.3087.0

CountyTARRANT
HighwayIH0020
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6303-12-001
Proj IDSUP - 630312001
Work TypeLITTER REMOVAL
 
0.010482216.16483929.3999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6303-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160233
Totals482216.161897.90483929.3999.9

CountySOMERVELL
HighwayUS0067
FromVARIOUS ROADWAYS IN HOOD, SOMERVELL, &
ToERATH COUNTIES
CSJ6303-13-001
Proj IDSUP - 630313001
Work TypeLITTER REMOVAL
 
0.010137244.12141571.2499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-16
Work Began09-20-16
Work Completed
Time Computed09-27-16
Contract Working Days365
Addl Days Granted0
Working Days Charged364
Percent Time Used99
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6303-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160236
Totals137244.120.00141571.2499.9

CountyPARKER
HighwayIH0020
FromVARIOUS ROADWAYS IN PARKER AND
ToPALO PINTO COUNTIES
CSJ6303-14-001
Proj IDSUP - 630314001
Work TypeLITTER REMOVAL
 
0.010299276.40297634.7699.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-19-16
Work Began09-20-16
Work Completed
Time Computed09-20-16
Contract Working Days365
Addl Days Granted0
Working Days Charged276
Percent Time Used75
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6303-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160234
Totals299276.400.00297634.7699.4

CountyTARRANT
HighwayIH0820
FromVARIOUS ROADWAYS IN
ToNORTH TARRANT COUNTY
CSJ6303-15-001
Proj IDSUP - 630315001
Work TypeLITTER REMOVAL
 
0.010385962.26339869.0588.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-22-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged327
Percent Time Used89
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160235
Totals385962.260.00339869.0588.0

CountyTARRANT
HighwayIH0820
FromJANITORIAL FOR SAGINAW
ToMAINTENANCE OFFICE
CSJ6303-19-001
Proj IDSUP - 630319001
Work TypeJANITORIAL MAINTENANCE
 
0.01011861.5211861.5299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-01-16
Work Began07-05-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged357
Percent Time Used97
Contractor(s)
TIBH INDUSTRIES, INC.
I AM WORKS ASSOCIATION
SUBCONTRACTOR(S) FOR CCSJ: 6303-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160231
Totals11861.520.0011861.5299.9

CountyTARRANT
HighwayIH0820
FromVARIOUS LOCATION WITHIN
ToNORTH TARRANT COUNTY
CSJ6303-66-001
Proj IDRMC - 630366001
Work TypeCALL-OUT STRIPING & PREFAB HANDWORK
 
0.010252480.00208091.4082.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-05-16
Work Began12-05-16
Work Completed
Time Computed12-05-16
Contract Working Days120
Addl Days Granted0
Working Days Charged41
Percent Time Used34
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160210
Totals252480.000.00208091.4082.4

CountyPARKER
HighwayUS0180
FromVARIOUS ROADWAYS WITHIN
ToPARKER & PALO PINTO COUNTIES
CSJ6303-67-001
Proj IDRMC - 630367001
Work TypeCLEANING & SEALING JOINTS & CRACKS
 
0.010187211.70174457.5293.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-18-17
Work Began00-00-00
Work Completed
Time Computed01-25-17
Contract Working Days29
Addl Days Granted0
Working Days Charged10
Percent Time Used34
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6303-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160209
Totals187211.700.00174457.5293.1

CountyJOHNSON
HighwayIH0035W
FromVARIOUS LOCATIONS WITHIN
ToJOHNSON COUNTY
CSJ6304-39-001
Proj IDRMC - 630439001
Work TypeTREE & BRUSH TRIMMING / REMOVAL
 
0.010326665.00148536.0045.4
Work Order05-01-17
Work Began04-05-17
Work Completed
Time Computed05-08-17
Contract Working Days150
Addl Days Granted0
Working Days Charged49
Percent Time Used32
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160202
Totals326665.000.00148536.0045.4

CountyWISE
HighwaySH0199
FromVARIOUS LOCATIONS IN WISE AND
ToJACK COUNTY
CSJ6304-64-001
Proj IDRMC - 630464001
Work TypeTREE & BRUSH TRIMMING AND REMOVAL
 
0.100272520.00319967.5099.9
Work Order01-09-17
Work Began01-09-17
Work Completed
Time Computed01-16-17
Contract Working Days50
Addl Days Granted60
Working Days Charged138
Percent Time Used125
Contractor(s)
RAE'S LIVESTOCK, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6304-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09160203
Totals272520.0013835.00319967.5099.9

CountyPARKER
HighwaySH0199
FromVARIOUS LOCATIONS IN
ToPARKER/PALO PINTO
CSJ6304-93-001
Proj IDRMC - 630493001
Work TypeTREE TRIMMING
 
0.010177000.00422100.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-17-16
Work Began10-17-16
Work Completed
Time Computed10-24-16
Contract Working Days86
Addl Days Granted42
Working Days Charged111
Percent Time Used86
Contractor(s)
KASPARIAN UNDERGROUND, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6304-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160204
Totals177000.000.00422100.0099.9

CountyWISE
HighwaySH0114
FromVARIOUS LOCATIONS IN WISE & JACK COUNTY
ToMAINTENANCE AREAS
CSJ6305-38-001
Proj IDRMC - 630538001
Work TypeRAISED PAVEMENT MARKERS
 
0.100196340.7826809.7613.6
Work Order09-18-17
Work Began09-25-17
Work Completed
Time Computed09-25-17
Contract Working Days19
Addl Days Granted0
Working Days Charged5
Percent Time Used26
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06170201
Totals196340.7826809.7626809.7613.6

CountyTARRANT
HighwayIH0020
FromFORT WORTH
ToDISTRICT COMPLEX
CSJ6307-94-001
Proj IDSUP - 630794001
Work TypeGROUNDS MAINTENANCE
 
0.01083829.3165105.8177.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged306
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6307-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08160237
Totals83829.313729.7265105.8177.6

CountyTARRANT
HighwayUS0287
FromVARIOUS LOCATIONS WITHIN
ToSOUTH TARRANT COUNTY
CSJ6311-71-001
Proj IDRMC - 631171001
Work TypeFULL DEPTH REPAIR OF EXISTING CONCRETE
 
0.010243481.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days26
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
IIPL USA LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07170202
Totals243481.000.000.000.0

CountyWISE
HighwayUS0081
FromWISE & JACK AREA
ToAND MAINTENANCE OFFICES
CSJ6311-85-001
Proj IDSUP - 631185001
Work TypeJANITORIAL MAINTENANCE
 
0.01061550.0056340.0091.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-16
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged329
Percent Time Used90
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6311-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10160231
Totals61550.006815.0056340.0091.5

page 1 | page 2 | page 3 | page 4 | page 5 | page 6