Monthly Local Let Maintenance Report For Beaumont District As Of Jan 10, 2018 Page 4 Of 5

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJEFFERSON
HighwaySH0087
FromIH-10 AT FM364 AND
ToSH87 AT THE INTRACOASTAL CANAL BRIDGE
CSJ6321-09-001
Proj IDRMC - 632109001
Work TypeHAULING ROADWAY MATERIAL
 
0.001189150.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6321-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172001
Totals189150.000.000.000.0

CountyCHAMBERS
HighwayIH0010
FromIH 10
ToIH 10
CSJ6321-33-001
Proj IDSUP - 632133001
Work TypeORANGE LITTER
 
1.000200212.7010877.255.4
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172001
Totals200212.700.0010877.255.4

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6321-34-001
Proj IDSUP - 632134001
Work TypeBEAUMONT LITTER
 
1.000184284.1145579.0424.7
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6321-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172006
Totals184284.119014.0945579.0424.7

CountyJASPER
HighwayUS0190
FromUS 190
ToUS 190
CSJ6321-35-001
Proj IDSUP - 632135001
Work TypeJASPER LITTER
 
1.00086919.8929591.6134.0
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172008
Totals86919.890.0029591.6134.0

CountyLIBERTY
HighwayUS0090
FromUS 90
ToUS 90
CSJ6321-36-001
Proj IDSUP - 632136001
Work TypeLIBERTY LITTER
 
1.000225188.5051510.5722.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-15-17
Work Began09-01-16
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged91
Percent Time Used24
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172002
Totals225188.500.0051510.5722.8

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6321-37-001
Proj IDSUP - 632137001
Work TypeNEWTON LITTER
 
1.00064151.8316485.7225.6
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172009
Totals64151.830.0016485.7225.6

CountyORANGE
HighwaySH0062
FromSH0062
ToSH0062
CSJ6321-38-001
Proj IDSUP - 632138001
Work TypeORANGE LITTER
 
1.000107759.250.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged91
Percent Time Used24
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172004
Totals107759.250.000.000.0

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6321-39-001
Proj IDSUP - 632139001
Work TypePORT ARTHUR LITTER
 
1.000144654.7140758.5128.1
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
SPINDLETOP MHMR SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6321-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172005
Totals144654.718908.4740758.5128.1

CountyHARDIN
HighwayUS0069
FromUS 69
ToUS 69
CSJ6321-40-001
Proj IDSUP - 632140001
Work TypeKOUNTZE LITTER
 
1.00092774.8125339.0427.3
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172003
Totals92774.810.0025339.0427.3

CountyTYLER
HighwayUS0069
FromUS 69
ToUS 69
CSJ6321-41-001
Proj IDSUP - 632141001
Work TypeWOODVILLE LITTER
 
1.00062304.6412214.9419.6
Work Order09-01-17
Work Began09-01-17
Work Completed
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6321-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172007
Totals62304.640.0012214.9419.6

CountyJASPER
HighwayUS0096
FromVARIOUS ROADWAYS IN JASPER, NEWTON
ToAND TYLER COUNTIES
CSJ6322-19-001
Proj IDRMC - 632219001
Work TypeCRACK SEAL
 
53.37498999.270.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AW&E CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6322-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12172001
Totals98999.270.000.000.0

CountyJEFFERSON
HighwaySH0347
FromSH 347
ToSH 347
CSJ6323-21-001
Proj IDSUP - 632321001
Work TypePORT ARTHUR GROUNDS
 
1.00024000.004800.00100.0
Work Order09-01-17
Work Began00-00-00
Work Completed09-01-17
Time Computed09-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged122
Percent Time Used33
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08172010
Totals24000.000.004800.00100.0

CountyJEFFERSON
HighwayIH0010
FromJEFFERSON,
ToORANGE, HARDIN COUNTIES
CSJ6323-40-001
Proj IDEMC - 632340001
Work TypeEMERGENCY ROADWAY REPAIRS
 
0.0101924807.204386968.4899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-11-17
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted60
Working Days Charged68
Percent Time Used75
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-40-001
AMERICAN REMEDIATION OPTIONS, INC. (7.81)
CPAVE, INC. (0.77)
URETEK USA, INC. (1.50)
Contract #10172003
Totals1924807.201638513.284386968.4899.9

CountyJASPER
HighwayUS0096
FromJASPER, NEWTON AND
ToTYLER COUNTIES
CSJ6323-43-001
Proj IDEMC - 632343001
Work TypeEMERGENCY ROADWAY REPAIRS
 
0.010654883.00397048.5660.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-22-17
Work Began09-23-17
Work Completed
Time Computed09-22-17
Contract Working Days30
Addl Days Granted0
Working Days Charged29
Percent Time Used96
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-43-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172004
Totals654883.000.00397048.5660.6

CountyCHAMBERS
HighwayIH0010
FromCHAMBERS AND
ToLIBERTY COUNTIES
CSJ6323-49-001
Proj IDEMC - 632349001
Work TypeEMERGENCY ROADWAY REPAIRS
 
0.010639123.001136487.1999.9
Work Order09-22-17
Work Began09-21-17
Work Completed
Time Computed09-22-17
Contract Working Days30
Addl Days Granted4
Working Days Charged32
Percent Time Used94
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172005
Totals639123.0010962.281136487.1999.9

CountyJEFFERSON
HighwaySH0087
FromVARIOUS LOCATIONS
ToALONG SH 87
CSJ6323-94-001
Proj IDEMC - 632394001
Work TypeEROSION REPAIR TO ROADWAY AND CANAL
 
3.10619225096.8025092.000.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days205
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-94-001
MASON CONSTRUCTION, LTD. (0.14)
Contract #10172004
Totals19225096.8025092.0025092.000.1

CountyTYLER
HighwayUS0069
FromUS 69
ToUS 69
CSJ6324-07-001
Proj IDSUP - 632407001
Work TypeWOODVILLE GROUNDS
 
1.0007650.00750.009.8
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172006
Totals7650.000.00750.009.8

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6324-08-001
Proj IDSUP - 632408001
Work TypeNEWTON GROUNDS
 
1.00010422.14482.064.6
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172007
Totals10422.140.00482.064.6

CountyJASPER
HighwayUS0190
FromUS 190
ToUS 190
CSJ6324-09-001
Proj IDSUP - 632409001
Work TypeJASPER GROUNDS
 
1.00011487.451937.1016.8
Work Order10-01-17
Work Began10-01-17
Work Completed
Time Computed10-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged92
Percent Time Used25
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172008
Totals11487.450.001937.1016.8

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6324-10-001
Proj IDSUP - 632410001
Work TypeDMV GROUNDS
 
1.0005217.00253.004.8
Work Order11-01-17
Work Began11-01-17
Work Completed
Time Computed11-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6324-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09172009
Totals5217.000.00253.004.8

page 1 | page 2 | page 3 | page 4 | page 5