Monthly Local Let Maintenance Report For Beaumont District As Of Feb 09, 2018 Page 2 Of 5

Last Update: Friday, February 09, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLIBERTY
HighwayUS0059
FromUS 59
ToUS 59
CSJ6303-91-001
Proj IDSUP - 630391001
Work TypeLARGE DEBRIS - LIBERTY
 
1.00075483.2049354.4065.3
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted365
Working Days Charged610
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
SDR & ASSOC. INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-91-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162005
Totals75483.202903.2049354.4065.3

CountyORANGE
HighwaySH0062
FromSH 62
ToSH 62
CSJ6303-95-001
Proj IDSUP - 630395001
Work TypeORANGE JANITORIAL
 
1.0006889.896078.0088.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
UNITED SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6303-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162007
Totals6889.890.006078.0088.2

CountyHARDIN
HighwayUS0096
FromHARDIN COUNTY
ToHARDIN COUNTY
CSJ6306-44-001
Proj IDBPM - 630644001
Work TypeRIPRAP AND SCOUR REPAIRS
 
0.001244250.00225565.3392.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-03-17
Work Completed
Time Computed00-00-00
Contract Working Days53
Addl Days Granted0
Working Days Charged42
Percent Time Used79
Contractor(s)
NORMAN HIGHWAY CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172001
Totals244250.000.00225565.3392.3

CountyCHAMBERS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6306-50-001
Proj IDSUP - 630650001
Work TypeANAHUAC LITTER
 
1.000186599.18138002.19100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-16
Work Began09-01-16
Work Completed09-01-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162007
Totals186599.180.00138002.19100.0

CountyORANGE
HighwaySH0062
FromVARIOUS
ToVARIOUS
CSJ6306-55-001
Proj IDSUP - 630655001
Work TypeORANGE LITTER
 
1.00087470.3464960.55100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-16
Work Began09-01-16
Work Completed09-01-17
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6306-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162004
Totals87470.340.0064960.55100.0

CountyLIBERTY
HighwayUS0059
FromUS 59 IN LIBERTY COUNTY
ToUS 59 IN LIBERTY COUNTY
CSJ6307-58-001
Proj IDRMC - 630758001
Work TypeOVERLAY OF EXISTING ROADWAYS
 
1.000192805.00386584.88100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-30-17
Work Completed07-10-17
Time Computed00-00-00
Contract Working Days23
Addl Days Granted0
Working Days Charged23
Percent Time Used100
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6307-58-001
REPUBLIC TRAFFIC SAFETY, INC. (3678.34)
Contract #12162001
Totals192805.000.00386584.88100.0

CountyORANGE
HighwayIH0010
FromVARIOUS
To.
CSJ6308-22-001
Proj IDSUP - 630822001
Work TypeJANITORIAL AND GROUNDS
 
0.001403580.50268987.9666.7
Work Order08-26-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged512
Percent Time Used70
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162031
Totals403580.5017138.35268987.9666.7

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6310-29-001
Proj IDRMC - 631029001
Work TypeINSTALLATION OF DELINEATORS
 
0.001155900.00144396.8092.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-10-17
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged47
Percent Time Used31
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6310-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04172001
Totals155900.000.00144396.8092.6

CountyORANGE
HighwaySH0062
FromSH 62
ToSH 62
CSJ6311-17-001
Proj IDSUP - 631117001
Work TypeORANGE GROUNDS MAINTENANCE
 
1.0008910.006930.0077.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162003
Totals8910.000.006930.0077.7

CountyJASPER
HighwayUS0190
FromUS 190
ToUS 190
CSJ6311-21-001
Proj IDSUP - 631121001
Work TypeJASPER PICNIC MAINTENANCE
 
1.00015654.6013260.80100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-01-16
Work Began11-01-16
Work Completed11-01-17
Time Computed11-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6311-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162007
Totals15654.600.0013260.80100.0

CountyCHAMBERS
HighwaySH0073
FromVARIOUS LOCATIONS IN CHAMBERS
ToAND LIBERTY COUNTIES
CSJ6311-75-001
Proj IDBPM - 631175001
Work TypeJOINT/CONCRETE REP/CLEAN&SEAL/RAIL UPGRA
 
1.000262770.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6311-75-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172004
Totals262770.000.000.000.0

CountyNEWTON
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6312-26-001
Proj IDRMC - 631226001
Work TypeNEWTON ~ ROW MOWING
 
272.000295109.20145924.6049.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-28-17
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged19
Percent Time Used19
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172001
Totals295109.200.00145924.6049.9

CountyTYLER
HighwayUS0069
FromVARIOUS
ToVARIOUS
CSJ6312-30-001
Proj IDRMC - 631230001
Work TypeWOODVILLE ~ ROW MOWING
 
253.400317392.00158646.0049.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-19-17
Work Completed
Time Computed00-00-00
Contract Working Days96
Addl Days Granted0
Working Days Charged20
Percent Time Used20
Contractor(s)
P-VILLE, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172002
Totals317392.000.00158646.0049.9

CountyJEFFERSON
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6312-31-001
Proj IDRMC - 631231001
Work TypeBEAUMONT MAINTENANCE ROW MOWING
 
208.000338025.00168150.0049.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-30-17
Work Completed
Time Computed00-00-00
Contract Working Days154
Addl Days Granted0
Working Days Charged28
Percent Time Used18
Contractor(s)
WAYNE YANCEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6312-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172003
Totals338025.000.00168150.0049.7

CountyLIBERTY
HighwaySH0105
FromVARIOUS ROADWAYS IN LIBERTY AND
ToCHAMBERS COUNTIES
CSJ6313-40-001
Proj IDRMC - 631340001
Work TypeSH 105 ETC., CRACK SEAL
 
25.68034854.4834854.3899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days15
Addl Days Granted0
Working Days Charged2
Percent Time Used13
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6313-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07172001
Totals34854.480.0034854.3899.9

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6313-87-001
Proj IDSUP - 631387001
Work TypeBEAUMONT AO MO JANITORIAL
 
1.0008603.063983.14100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-17
Work Began02-01-17
Work Completed11-01-17
Time Computed02-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged255
Percent Time Used69
Contractor(s)
TIBH INDUSTRIES, INC.
UNITED SERVICE INDUSTRIES
SUBCONTRACTOR(S) FOR CCSJ: 6313-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01172001
Totals8603.060.003983.14100.0

CountyJEFFERSON
HighwayIH0010
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6314-11-001
Proj IDRMC - 631411001
Work TypeCABLE BARRIER REPAIR
 
0.001217150.00132969.0061.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-18-17
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged136
Percent Time Used37
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-11-001
ELITE CASTLE RESOURCES LLC (89.36)
Contract #05172001
Totals217150.0038340.00132969.0061.2

CountyTYLER
HighwayUS0069
FromUS 69
ToUS 69
CSJ6314-17-001
Proj IDSUP - 631417001
Work TypeWOODVILLE JANITORIAL
 
1.0004476.004476.00100.0
Work Order02-01-17
Work Began02-01-17
Work Completed02-01-18
Time Computed02-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6314-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01172002
Totals4476.00373.004476.00100.0

CountyJASPER
HighwayUS0190
FromUS 190
ToUS 190
CSJ6314-19-001
Proj IDSUP - 631419001
Work TypeJASPER JANITORIAL
 
1.0007536.007536.0099.9
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
BURKE CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6314-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01172004
Totals7536.00628.007536.0099.9

CountyJEFFERSON
HighwayUS0069
FromUS 69
ToUS 69
CSJ6314-73-001
Proj IDSUP - 631473001
Work TypeBEAUMONT AO MO GROUNDS
 
1.0003850.003150.0081.8
Work Order03-01-17
Work Began03-01-17
Work Completed
Time Computed03-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged337
Percent Time Used92
Contractor(s)
TIBH INDUSTRIES, INC.
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172002
Totals3850.000.003150.0081.8