Monthly Local Let Maintenance Report For Beaumont District As Of Mar 13, 2024 Page 3 Of 4

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyJEFFERSON
HighwayUS0069
FromUS69
ToUS69
CSJ6451-19-001
Proj IDSUP - 645119001
Work TypeJANITORIAL MAINTENANCE
 
0.01092945.7347921.1451.5
Work Order07-19-23
Work Began08-01-23
Work Completed
Time Computed08-01-23
Contract Working Days365
Addl Days Granted0
Working Days Charged213
Percent Time Used58
Contractor(s)
WORKQUEST
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6451-19-001
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC. (100.00)
Contract #07232037
Totals92945.736803.0247921.1451.5

CountyJEFFERSON
HighwaySH0347
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6451-81-001
Proj IDMMC - 645181001
Work TypeFLEXIBLE BASE
 
0.01089100.00176969.6999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began09-11-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged169
Percent Time Used46
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6451-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08232065
Totals89100.005164.03176969.6999.9

CountyTYLER
HighwayFM0256
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6454-13-001
Proj IDMMC - 645413001
Work TypeASPHALTIC PATCHING MATERIAL
 
0.010283691.00109117.6438.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6454-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232055
Totals283691.0062262.68109117.6438.4

CountyJEFFERSON
HighwayUS0069
FromUS69
ToUS69
CSJ6454-35-001
Proj IDSUP - 645435001
Work TypeLITTER REMOVAL
 
0.01080388.5830901.6738.4
Work Order08-22-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6454-35-001
RUCON, INC. (100.00)
Contract #08232031
Totals80388.580.0030901.6738.4

CountyTYLER
HighwayUS0190
FromUS190
ToUS190
CSJ6454-37-001
Proj IDSUP - 645437001
Work TypeLITTER REMOVAL
 
0.010101982.9064015.9662.7
Work Order08-22-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6454-37-001
RUCON, INC. (100.00)
Contract #08232032
Totals101982.9013500.1264015.9662.7

CountyHARDIN
HighwayUS0069
FromUS69
ToUS69
CSJ6454-39-001
Proj IDSUP - 645439001
Work TypeLITTER REMOVAL
 
0.010106566.5654848.0651.4
Work Order08-22-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged151
Percent Time Used41
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6454-39-001
RUCON, INC. (100.00)
Contract #08232033
Totals106566.566036.9054848.0651.4

CountyLIBERTY
HighwayUS0090
FromUS90
ToUS90
CSJ6454-41-001
Proj IDSUP - 645441001
Work TypeLITTER REMOVAL
 
0.010232845.09146605.6162.9
Work Order08-22-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6454-41-001
RUCON, INC. (100.00)
Contract #08232034
Totals232845.0922003.64146605.6162.9

CountyJASPER
HighwayUS0190
FromUS190
ToUS190
CSJ6454-43-001
Proj IDSUP - 645443001
Work TypeLITTER REMOVAL
 
0.010154832.4391015.4258.7
Work Order08-22-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6454-43-001
RUCON, INC. (100.00)
Contract #08232035
Totals154832.4325395.8091015.4258.7

CountyJEFFERSON
HighwaySH0073
FromSH73
ToSH73
CSJ6454-45-001
Proj IDSUP - 645445001
Work TypeGROUNDS MAINTENANCE
 
0.01029565.125141.7617.3
Work Order08-22-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged182
Percent Time Used49
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6454-45-001
RUCON, INC. (100.00)
Contract #08232036
Totals29565.120.005141.7617.3

CountyCHAMBERS
HighwaySH0061
FromSH61
ToSH61
CSJ6454-47-001
Proj IDSUP - 645447001
Work TypeLITTER REMOVAL
 
0.010206009.1970719.7534.3
Work Order08-22-23
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6454-47-001
RUCON, INC. (98.75)
Contract #08232037
Totals206009.190.0070719.7534.3

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6455-58-001
Proj IDMMC - 645558001
Work TypeHOT-MIX COLD-LAID
 
0.010307200.0023322.607.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-24-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged129
Percent Time Used35
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6455-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232056
Totals307200.000.0023322.607.5

CountyORANGE
HighwaySH0062
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6455-71-001
Proj IDMMC - 645571001
Work TypeHOT-MIX COLD-LAID
 
0.010116250.00185772.1599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6455-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232058
Totals116250.0062271.25185772.1599.9

CountyLIBERTY
HighwayUS0090
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6455-73-001
Proj IDMMC - 645573001
Work TypeHOT-MIX COLD-LAID
 
0.010215000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged123
Percent Time Used33
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6455-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09232057
Totals215000.000.000.000.0

CountyJEFFERSON
HighwayUS0069
FromDISTRICTWIDE
ToDISTRICTWIDE
CSJ6456-57-001
Proj IDMMC - 645657001
Work TypeWINTER WEATHER MATERIAL
 
0.010280560.00204112.2072.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-16-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged106
Percent Time Used29
Contractor(s)
SOUTHWEST ENVIROTX PARTNERS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6456-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10232050
Totals280560.00137204.40204112.2072.7

CountyTYLER
HighwayUS0287
FromUS 287
ToUS 287
CSJ6456-65-001
Proj IDSUP - 645665001
Work TypeGROUNDS MAINTENANCE
 
0.0105304.50257.504.8
Work Order09-21-23
Work Began10-01-23
Work Completed
Time Computed10-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6456-65-001
RUCON, INC. (100.00)
Contract #09232031
Totals5304.500.00257.504.8

CountyNEWTON
HighwayUS0190
FromUS 190
ToUS 190
CSJ6456-67-001
Proj IDSUP - 645667001
Work TypeGROUNDS MAINTENANCE
 
0.01010734.772293.9321.3
Work Order09-26-23
Work Began10-01-23
Work Completed
Time Computed10-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6456-67-001
RUCON, INC. (95.47)
Contract #09232032
Totals10734.770.002293.9321.3

CountyJASPER
HighwayUS0190
FromUS190
ToUS190
CSJ6456-69-001
Proj IDSUP - 645669001
Work TypeGROUNDS MAINTENANCE
 
0.010147060.20101145.5268.7
Work Order09-21-23
Work Began10-01-23
Work Completed
Time Computed10-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged152
Percent Time Used41
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6456-69-001
RUCON, INC. (100.00)
Contract #09232033
Totals147060.200.00101145.5268.7

CountyJEFFERSON
HighwayUS0069
FromUS69
ToUS69
CSJ6458-43-001
Proj IDSUP - 645843001
Work TypeSTATE USE CONTRACT
 
0.01088183.008047.009.1
Work Order10-24-23
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6458-43-001
RUCON, INC. (100.00)
Contract #10232031
Totals88183.004148.008047.009.1

CountyJEFFERSON
HighwayUS0069
FromUS69
ToUS69
CSJ6458-45-001
Proj IDSUP - 645845001
Work TypeSTATE USE CONTRACT
 
0.0107826.00944.0012.0
Work Order10-24-23
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
WORKQUEST
RUCON, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6458-45-001
RUCON, INC. (100.00)
Contract #10232032
Totals7826.00506.00944.0012.0

CountyORANGE
HighwaySH0062
FromSH62
ToSH62
CSJ6458-47-001
Proj IDSUP - 645847001
Work TypeJANITORIAL MAINTENANCE
 
0.01012108.124036.0433.3
Work Order10-25-23
Work Began11-01-23
Work Completed
Time Computed11-01-23
Contract Working Days366
Addl Days Granted0
Working Days Charged121
Percent Time Used33
Contractor(s)
WORKQUEST
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6458-47-001
OPPORTUNITIES FOR DESERVING INDIVIDUALS, INC. (100.00)
Contract #10232038
Totals12108.121009.014036.0433.3

page 1 | page 2 | page 3 | page 4