Section 4: Track Design
Introduction
Most railroad companies prefer any required track work to
support a TxDOT construction project be
completed
by
a TxDOT contractor. Railroad companies assist by:- Cutting rails.
- Welding or bolting together new track sections.
- Installing switches.
- Relocating signal equipment.
This is not common with all railroad companies. Project designers
should
coordinate responsible party to
provide
materials, remove existing track sections, dispose of materials,
and install new materials prior to developing plans and specifications.
If not properly assigned at the beginning of a project
,
TxDOT may be at risk of a change order during construction.The goal of effective track design is to
ensure
the heavy weight distribution of railroad equipment can travel across
the railroad tracks safely and efficiently without destroying the
railroad equipment or disrupting the ballast or base material beneath
the tracks. This is accomplished using following
components.Rail
Rails classified in weight per linear yard of a single rail
(i.e., 132# rail).
The size
and type
of rail to be used
in a project is the choice of the operating railroad company. Heavier
weights are used on mainline tracks, while smaller sizes may be
used on spur and siding track.Track Panels
Panels are typically 80
foot
in length
and include:- Rails.
- Tie plates.
- Ties.
Track panels are particularly useful when replanking an existing
at-grade crossing. After the existing rails are cut on both ends,
an existing section of track is removed down to the subgrade. After the
subgrade, subballast, and ballast are
placed
,
the track panels are installed. The track panel is bolted on both
ends, and a tamping machine installs ballast. The temporary joint
bars are then removed, and the rails are welded together. Crossing
surface panels are bolted into the ties.Securement
Securing the rails to the ties is done by using:
- Tie spikes and tie plates for timber ties.
- Tie clips and rail seat pads for concrete ties.
Tie plates and clips also assist in distributing the load
of a train over the tie.
Ties
Ties are
supporting members, either
timber
or concrete, to which rail is fastened. They provide distributive
support for the rail and assist in maintaining track alignment and
separation between rails.Timber ties are manufactured from hardwoods such as oak or
Douglas fir and pressure treated with a creosote/tar solution to
prevent decay. Timber tie size is usually 7
inch
by
9 inch by 8 foot 6 inches. Timber tie spacing is usually 18 inches
or 19.5 inches on center.Concrete ties are prestressed with rebar, resist decay, and
generally have a longer useful life than timber ties. Concrete tie
size is usually 11 inch by 9 inch by 8 foot 6 inches. Concrete tie
spacing is usually 20 inches or 24 inches on center.
Switch ties may be timber or concrete ties of varying lengths
(generally 9 feet to 20 feet) that are used to support the track
structure at the location where a
single
track
diverges into two or more tracks by means of the turnout and switch
mechanism.In recent years there has been increasing interest in the
development and use of ties made of composite materials, primarily
polymers mixed with timber or concrete. Composite ties are not in general
use by any of the major railroad companies, though there are some
installed at various locations around the country as test projects.
Ballast
Ballast restrains the movement of crossties to prevent lateral
movement of the track structure, provides distributive support to
the crossties, and provides drainage for the track structure above. Desired
typical
ballast
depth is within 2 inches of top of the ties and 9 to 12 inches below
the bottom of the ties. The width of the ballast section is usually
6 to 12 inches from the ends of the tie with a two-to-one slope
downward from that point to ground level.Sub-ballast
Sub-ballast consists of smaller particles that provide for
additional support of the track structure and a foundation course
to aid further with drainage. As track structure ages and upper
ballast deteriorates, those smaller particles migrate downward,
effectively deepening the lower ballast layer. Maintenance and rehabilitation
projects add newer upper ballast, causing the entire track structure to
gradually rise vertically over time.
Subgrade
On new construction, core samples are usually
collected
to
determine the type and depth of constructed subgrade (compacted
aggregate) that should be used to support the track structure. On existing
older rail lines, the subgrade is typically the native soils present
when the railroad was built.Track Design Standards
AREMA has standard track components and design plans that
are often referenced for track design. The
Class I
railroad
companies (BNSF, CN, CP, CSX, CPKC
, NS, UPRR)
also have their own specific engineering and design standards for
some components and design that may vary from AREMA standards and
supersede AREMA standards. Some of these are also common standards used
by more than one railroad company, such as BNSF/UPRR common standards.TxDOT has permission from UPRR and BNSF to use their standards
and common standard sheets in PS&E packages. The designer should
confirm from the railroad company the standard to use prior to developing
the track design plans. Track design should only be performed by
individuals with prior track design experience familiar with both
AREMA and railroad company standards.
Turnouts
A turnout is
a track panel
that diverts
trains from one track to another. The length of the turnout is determined
by angle of the turnout casting (referred to as a “frog”). The shorter
the turnout, the sharper the angle of divergence will be, which
restricts train operating speeds through the turnout. The initial
point of divergence where the two tracks effectively meet is referred
to as the “switch” and the moveable rails at that location referred
to as a “switch point”.Grades and Horizontal Curves
Railroad optimum design for grades is 0.5% or less, though
up to 1.5% is acceptable in certain circumstances. Steeper grades
result in continual reduction in train speed and can actually cause
a train to stall if the grade is too steep, or require the use of
additional locomotives, which is a major operating cost.
Horizontal curvature is not nearly as critical, though it
can affect train speed and handling. The degree of curvature and
desired train speed will impact the amount of superelevation used.
Consecutive curves also require the design of a tangent length of
track between curves to prevent the train from rocking, which can
result in derailments.