Introduction
Most railroad companies prefer any required track work to
support a TxDOT construction project be
completed
by
a TxDOT contractor. Railroad companies assist by:- Cutting rails.
- Welding or bolting together new track sections.
- Installing switches.
- Relocating signal equipment.
This is not common with all railroad companies. Project designers
should
coordinate responsible party to
provide
materials, remove existing track sections, dispose of materials,
and install new materials prior to developing plans and specifications.
If not properly assigned at the beginning of a project
,
TxDOT may be at risk of a change order during construction.The goal of effective track design is to
ensure
the heavy weight distribution of railroad equipment can travel across
the railroad tracks safely and efficiently without destroying the
railroad equipment or disrupting the ballast or base material beneath
the tracks. This is accomplished using following
components.