Detail Letting Schedule for Hardin County (FY 2008)
Detail Letting Schedule for Hardin County (FY 2008) | ||||
Last Update: Monday, February 2, 2009 |
Hardin County (FY 2008) |
CCSJ: 0065-05-131 | |||
District: | Beaumont | Let Date: | MAR 2008 |
Highway: | US 96 | Let Status: | Actual |
Project ID: | CM 2008(408) | CSJ: | 0065-05-131 |
Description: | IMPROVE INTERSECTION | Handling Code: |
|
Limits From: | AT CHANCE RD IN LUMBERTON | Fund Cat: | 5 |
Limits To: | . | Estimate: | $180,776 |
Length: | 0.1 Miles | Actual: | $137,041 |
Back... |
Totals for 0065-05-131 | ||
---|---|---|---|
Length: | 0.1 Miles | ||
Estimate: | $180,776 | ||
Actual: | $137,041 | ||
CCSJ: 0339-03-034 | |||
District: | Beaumont | Let Date: | APR 2008 |
Highway: | SH 105 | Let Status: | Actual |
Project ID: | NH 2008(477) | CSJ: | 0339-03-034 |
Description: | OVERLAY EXISTING ROADWAY | Handling Code: |
|
Limits From: | FM 770 (EAST JUNCTION), EAST | Fund Cat: | 1 |
Limits To: | 0.762 MI WEST OF SH 326 | Estimate: | $2,549,236 |
Length: | 12.6 Miles | Actual: | $1,927,398 |
District: | Beaumont | Let Date: | APR 2008 |
Highway: | SH 105 | Let Status: | Actual |
Project ID: | NH 2008(477) | CSJ: | 1096-01-053 |
Description: | OVERLAY EXISTING ROADWAY | Handling Code: |
|
Limits From: | FM 770 (WEST JUNCTION), EAST | Fund Cat: | 11 |
Limits To: | FM 770 (EAST JUNCTION) | Estimate: | $461,804 |
Length: | 2.3 Miles | Actual: | $352,828 |
Back... |
Totals for 0339-03-034 | ||
Length: | 14.9 Miles | ||
Estimate: | $3,011,040 | ||
Actual: | $2,280,226 | ||
CCSJ: 0602-01-043 | |||
District: | Beaumont | Let Date: | MAY 2008 |
Highway: | SH 327 | Let Status: | Actual |
Project ID: | STP 2008(571) | CSJ: | 0602-01-043 |
Description: | REHABILITATE EXISTING ROADWAY | Handling Code: |
|
Limits From: | MILL CREEK, EAST | Fund Cat: | 1 |
Limits To: | BU 96F IN SILSBEE | Estimate: | $1,175,000 |
Length: | 2.5 Miles | Actual: | $1,058,619 |
District: | Beaumont | Let Date: | MAY 2008 |
Highway: | FM 787 | Let Status: | Actual |
Project ID: | STP 2008(571) | CSJ: | 0813-02-035 |
Description: | OVERLAY EXISTING ROADWAY & ADD SHOULDERS | Handling Code: |
|
Limits From: | LIBERTY CO/L, EAST | Fund Cat: | 1 |
Limits To: | FM 1293 | Estimate: | $1,644,610 |
Length: | 5.7 Miles | Actual: | $1,371,986 |
Back... |
Totals for 0602-01-043 | ||
Length: | 8.2 Miles | ||
Estimate: | $2,819,610 | ||
Actual: | $2,430,605 | ||
CCSJ: 0813-03-039 | |||
District: | Beaumont | Let Date: | JAN 2008 |
Highway: | FM 421 | Let Status: | Actual |
Project ID: | STP 2007(916) | CSJ: | 0813-03-039 |
Description: | RESTORE EXISTING ROADWAY AND ADD SHOULDERS | Handling Code: |
|
Limits From: | SH 326, EAST | Fund Cat: | 11 |
Limits To: | 4.5 MILES | Estimate: | $1,973,077 |
Length: | 4.7 Miles | Actual: | $1,411,658 |
District: | Beaumont | Let Date: | JAN 2008 |
Highway: | FM 1293 | Let Status: | Actual |
Project ID: | STP 2007(916) | CSJ: | 1947-01-018 |
Description: | RESTORE EXISTING ROADWAY AND ADD SHOULDERS | Handling Code: |
|
Limits From: | 6 MI EAST OF FM 787, EAST | Fund Cat: | 11 |
Limits To: | FM 1003 | Estimate: | $1,433,700 |
Length: | 6.3 Miles | Actual: | $1,126,385 |
Back... |
Totals for 0813-03-039 | ||
Length: | 11.0 Miles | ||
Estimate: | $3,406,777 | ||
Actual: | $2,538,043 | ||
CCSJ: 0920-03-063 | |||
District: | Beaumont | Let Date: | JAN 2008 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2007(266) | CSJ: | 0920-03-063 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | CR 161 AT CYPRESS CREEK | Fund Cat: | 6 |
Limits To: | (STR AA0161001) | Estimate: | $822,153 |
Length: | 0.1 Miles | Actual: | $625,277 |
Back... |
Totals for 0920-03-063 | ||
Length: | 0.1 Miles | ||
Estimate: | $822,153 | ||
Actual: | $625,277 | ||
CCSJ: 0920-03-067 | |||
District: | Beaumont | Let Date: | JUN 2008 |
Highway: | CR | Let Status: | Actual |
Project ID: | BR 2007(760) | CSJ: | 0920-03-067 |
Description: | REPLACE BRIDGE AND APPROACHES | Handling Code: |
|
Limits From: | COOKS RD AT BRANCH | Fund Cat: | 6 |
Limits To: | (STR AA0536001) | Estimate: | $274,752 |
Length: | 0.1 Miles | Actual: | $341,315 |
Back... |
Totals for 0920-03-067 | ||
Length: | 0.1 Miles | ||
Estimate: | $274,752 | ||
Actual: | $341,315 |
|
|