Monthly State Let Construction Report For Houston District As Of Apr 10, 2018 Page 8 Of 10

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHARRIS
HighwayCS
FromEASTSIDE ST: WESTHEIMER ST
ToLEVY PARK
CSJ0912-72-313
Proj IDSTP 1702(285)
Work TypeRECONSTRUCT ROADWAY
 
0.7335787450.162561380.7844.2
Work Order07-20-17
Work Began10-23-17
Work Completed
Time Computed08-19-17
Contract Working Days205
Addl Days Granted0
Working Days Charged85
Percent Time Used41
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-313
CPAVE, INC. (0.31)
MVA CONSTRUCTION LLC (1.96)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.30)
SOUTHERN CRUSHED CONCRETE LLC (0.72)
TEXAS WALL & LANDSCAPE (11.86)
PROFESSIONAL TRAFFIC CONTROL, LLC (1.61)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (11.70)
AAA FLEXIBLE PIPE CLEANING COMPANY, INC. (0.21)
CP REBAR AND PT INSTALLATION (0.35)
Contract #06173030
Totals5787450.16300508.602561380.7844.2

CountyHARRIS
HighwayVA
FromFALLS STREET
ToLOCKWOOD DRIVE
CSJ0912-72-315
Proj IDSTP 2014(142)TE
Work TypeCONSTRUCT MULTI-USE PATH
 
0.8671323726.00728799.7455.0
Work Order06-22-16
Work Began08-10-16
Work Completed
Time Computed07-22-16
Contract Working Days136
Addl Days Granted0
Working Days Charged39
Percent Time Used28
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-315
SPECIALTY DRILLING, LTD. (1.17)
Contract #04163021
Totals1323726.00105274.17728799.7455.0

CountyHARRIS
HighwayVA
FromAT HERMANN PARK/BRAYS BAYOU TRAIL
ToFROM ALMEDA RD TO HOLCOMBE BLVD
CSJ0912-72-319
Proj IDSTP 2014(141)TE
Work TypeCONSTRUCT MULTI-USE PATH CONNECTORS
 
0.467792114.50715098.2290.2
Work Order07-27-16
Work Began10-17-16
Work Completed
Time Computed10-25-16
Contract Working Days151
Addl Days Granted0
Working Days Charged136
Percent Time Used90
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-319
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05163231
Totals792114.507010.02715098.2290.2

CountyHARRIS
HighwayCR
FromWEST LAKE HOUSTON PKWY, FROM UPRR
ToWILL CLAYTON PKWY
CSJ0912-72-335
Proj IDCC 912-72-335
Work TypeITS FOR HIGH DEMAND ARTERIAL STREET
 
0.0011789743.301987181.6299.9
Work Order05-16-16
Work Began09-06-16
Work Completed
Time Computed09-01-16
Contract Working Days200
Addl Days Granted0
Working Days Charged190
Percent Time Used95
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-335
STRIPE-A-LINE, INC. (1.88)
SOUTH RANGER CONSTRUCTION, INC. (9.79)
MENADE, INC. (15.51)
Contract #12153013
Totals1789743.300.001987181.6299.9

CountyHARRIS
HighwayCR
FromFEDERAL ROAD AT PTRA RAILROAD
To.
CSJ0912-72-336
Proj IDSTP 1702(286)MM
Work TypeCONST RAILROAD GRADE SEPARTION
 
0.52311194639.230.000.0
Work Order08-28-17
Work Began00-00-00
Work Completed
Time Computed09-27-17
Contract Working Days537
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-336
HIGHWAY 1, LLC (0.61)
GMJ PAVING CO. (0.36)
SCOTT DERR PAINTING CO, LLC (0.05)
SOUTHERN CRUSHED CONCRETE LLC (0.64)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.26)
WILLOW CITY SIGN & RAIL, INC. (0.11)
Contract #06173007
Totals11194639.230.000.000.0

CountyHARRIS
HighwayVA
FromON FM 270 FROM NASA ROAD 1
ToHENDERSON ROAD
CSJ0912-72-413
Proj IDSTP 2014(138)TE
Work TypeSHARED USE PATH
 
1.9021764011.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days150
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0912-72-413
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04183216
Totals1764011.100.000.000.0

CountyGALVESTON
HighwayVA
FromAT GALVESTON FERRY
To.
CSJ0912-73-205
Proj IDFT 912-73-205
Work TypeRECON OF FERRY BULKHEAD & WORK DOCK
 
0.00121325783.009193183.3343.1
Work Order02-03-17
Work Began04-17-17
Work Completed
Time Computed04-17-17
Contract Working Days450
Addl Days Granted0
Working Days Charged222
Percent Time Used49
Contractor(s)
TEXAS GULF CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0912-73-205
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12163006
Totals21325783.00601115.989193183.3343.1

CountyHARRIS
HighwayFM 865
FromALMEDA-GENOA
ToBW 8
CSJ0976-01-019
Proj IDC 976-1-19
Work TypeGR, BS & SURF
 
1.27213285921.4415270912.8899.9
Work Order02-12-14
Work Began09-28-15
Work Completed
Time Computed11-09-14
Contract Working Days305
Addl Days Granted8
Working Days Charged317
Percent Time Used101
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-019
INTERSTATE BARRICADES & MARKINGS, INC. (0.15)
BREDA COMPANY, INC. (0.56)
CPAV SPECIALTIES, LP (0.20)
FLORIDA TRAFFIC CONTROL DEVICES, INC. (2.48)
JOHN REED AND COMPANY, LLC (7.70)
PEREZ CONSTRUCTION CO. (2.23)
TEXOP CONSTRUCTION (1.40)
DURWOOD GREENE CONSTRUCTION CO. (1.87)
ROSALES TRUCKING (2.32)
NATIONAL DEWATERING SYSTEMS (0.15)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.99)
RAY"S THREADING AND FAB SHOP (0.28)
ABLE PAVING (0.09)
INTERSTATE BARRICADES & MARKINGS, INC. (0.78)
BORTUNCO (0.11)
MICKIE SERVICE, INC. (0.51)
TRAF-TEX, INC. (0.07)
Contract #11133025
Totals13285921.440.0015270912.8899.9

CountyHARRIS
HighwayFM 865
FromIH 610
ToALMDEDA GENOA
CSJ0976-01-039
Proj IDNH 2018(562)
Work TypeBS REP,MILL,O/L,STRIP W/ TS
 
4.4052411705.720.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days115
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 0976-01-039
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183214
Totals2411705.720.000.000.0

CountyGALVESTON
HighwayFM 518
FromFRIENDSWOOD LINK ROAD
ToRIVERSIDE
CSJ0976-03-103
Proj IDNH 2016(627)
Work TypeLANDSCAPE DEV
 
2.310227694.62208489.5291.5
Work Order09-15-16
Work Began11-08-16
Work Completed
Time Computed10-17-16
Contract Working Days45
Addl Days Granted0
Working Days Charged41
Percent Time Used91
Contractor(s)
GREEN SOURCE ENVIRONMENTAL SOLUTIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0976-03-103
TRAF-TEX, INC. (2.70)
Contract #08163230
Totals227694.620.00208489.5291.5

CountyGALVESTON
HighwayFM 2094
FromAT DAVIS ROAD
To.
CSJ0976-04-020
Proj IDSTP 2017(497)HES
Work TypeTS IMPRVMTS
 
0.250213735.35227215.2599.9
Work Order02-09-17
Work Began06-16-17
Work Completed
Time Computed03-11-17
Contract Working Days180
Addl Days Granted0
Working Days Charged71
Percent Time Used39
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0976-04-020
STRIPE LINES, INC. (1.44)
SPRING CREEK CONSTRUCTION, INC. (16.70)
Contract #01173228
Totals213735.350.00227215.2599.9

CountyGALVESTON
HighwayFM 646
FromFM 1764
ToSH 6
CSJ0978-01-034
Proj IDC 978-1-34
Work TypeGR, BASE, SURF, STRS
 
1.22212830994.0012922486.0399.9
Work Order02-17-16
Work Began07-05-16
Work Completed
Time Computed05-17-16
Contract Working Days310
Addl Days Granted37
Working Days Charged325
Percent Time Used93
Contractor(s)
STERLING DELAWARE HOLDING COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0978-01-034
CPAVE, INC. (0.23)
DOUBLE OAK CONSTRUCTION, INC. (0.23)
WILLOW CITY SIGN & RAIL, INC. (0.42)
ROSALES TRUCKING (2.13)
MESA ROD BUSTERS, INC. (3.55)
TOM-MAC, INC. (0.70)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (3.53)
INTERSTATE BARRICADES & MARKINGS, INC. (0.99)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.72)
RAY"S THREADING AND FAB SHOP (0.21)
G. S. I. HIGHWAY PRODUCTS (0.26)
DURWOOD GREENE CONSTRUCTION CO. (5.63)
PEREZ CONSTRUCTION CO. (0.06)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.02)
Contract #12153206
Totals12830994.00324520.8212922486.0399.9

CountyGALVESTON
HighwayFM 3436
FromFM 646
ToFM 517
CSJ0978-02-078
Proj IDC 978-2-78
Work TypeREPLACE MBGF, LEVEL UP, TOM
 
1.588625529.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-09-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0978-02-078
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03183232
Totals625529.300.000.000.0

CountyBRAZORIA
HighwayFM 524
From0.495 MI SOUTHWEST OF FM 1459
ToFM 521
CSJ1004-01-063
Proj IDSTP 2018(418)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
3.425438751.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days104
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1004-01-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01183022
Totals438751.100.000.000.0

CountyHARRIS
HighwayFM 2100
From0.104 MI S OF HUFFMAN-CLEVELAND RD
To0.413 MI S OF HUFFMAN-CLEVELAND RD
CSJ1062-02-026
Proj IDSTP 2018(563)
Work TypeINST TN LNS,SHLDR WDEN ,MILL OL&PV
 
0.309234040.680.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-14-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days36
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1062-02-026
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183016
Totals234040.680.000.000.0

CountyHARRIS
HighwayFM 1942
FromUS 90
ToCROSBY LYNCHBURG RD
CSJ1062-05-009
Proj IDSTP 2015(614)MM
Work TypeWIDEN ROADWAY
 
0.3153477178.183983895.3999.9
Work Order03-30-15
Work Began10-26-15
Work Completed
Time Computed05-29-15
Contract Working Days157
Addl Days Granted0
Working Days Charged139
Percent Time Used88
Contractor(s)
ARANDA BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1062-05-009
ALLSTATE SIGNAL & CONSTRUCTION, LLC (6.16)
BATTERSON,LLP (1.29)
Contract #02153223
Totals3477178.180.003983895.3999.9

CountyFORT BEND
HighwayFM 1093
FromFM 1489
To0.47 MI W OF FM 359
CSJ1258-02-037
Proj IDSTP 2018(564)
Work TypeBASE REPAIR AND OVERLAY
 
4.213781727.270.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-12-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1258-02-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183205
Totals781727.270.000.000.0

CountyMONTGOMERY
HighwayFM 1097
FromIH 45
ToSH 75
CSJ1259-01-036
Proj IDSTP 1502(201)
Work TypeWIDEN FOR CLTL & 2" OVERLAY
 
0.8205567522.755795795.7899.9
Work Order11-12-15
Work Began07-11-16
Work Completed
Time Computed03-11-16
Contract Working Days155
Addl Days Granted11
Working Days Charged231
Percent Time Used139
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1259-01-036
J & M CONTRACTING, COMPANY (50.28)
WILLOW CITY SIGN & RAIL, INC. (0.26)
STRIPE LINES, INC. (1.02)
THIRD COAST SERVICES LLC (11.67)
CEN TEX HYDROSEED, INC. (0.39)
717 CONSTRUCTION SERVICES (0.70)
Contract #08153057
Totals5567522.756478.705795795.7899.9

CountyMONTGOMERY
HighwayFM 1774
From0.045 MI S OF W. LOST CREEK BLVD
ToFM 149
CSJ1400-04-011
Proj IDSTP 1402(182)
Work TypeGR, STRS, BS & CONC PAV
 
2.83118070204.0511261571.0862.3
Work Order11-03-14
Work Began07-14-16
Work Completed
Time Computed11-19-14
Contract Working Days360
Addl Days Granted46
Working Days Charged266
Percent Time Used65
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-011
WILLOW CITY SIGN & RAIL, INC. (0.62)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.92)
SCMU (2.06)
INDUS CONSTRUCTION, L.P. (0.92)
TEX OP CONSTRUCTION, LP (0.89)
ANGEL BROTHERS ENTERPRISES, LTD. (6.34)
CURB PLANET INC. (0.01)
THIRD COAST SERVICES LLC (1.71)
EUBANK EXCAVATION, L.L.C. (0.54)
CPAVE, INC. (0.31)
PROFESSIONAL TRAFFIC CONTROL, LLC (1.21)
ADF EXCAVATION, LLC (0.53)
ROMAR UNLIMITED, INC. (2.90)
Contract #08143203
Totals18070204.05216546.5911261571.0862.3

CountyMONTGOMERY
HighwayFM 1774
FromFM 1486
To0.109 MILE NORTH OF FM 1488
CSJ1400-04-021
Proj IDSTP 1602(483)MM
Work TypeGR, STRS, BS & CONC PAV
 
1.17323247170.4314111507.6560.7
Work Order11-01-16
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days687
Addl Days Granted1
Working Days Charged322
Percent Time Used46
Contractor(s)
JAMES CONSTRUCTION GROUP, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 1400-04-021
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.43)
WILLOW CITY SIGN & RAIL, INC. (0.68)
THIRD COAST SERVICES LLC (1.48)
LONESTAR TRAFFIC SAFETY, LLC (0.08)
EGGEMEYER LAND CLEARING, LLC (0.55)
TEX OP CONSTRUCTION, LP (0.26)
MESA ROD BUSTERS, INC. (1.26)
CPAVE, INC. (0.11)
SCOTT DERR PAINTING CO, LLC (0.45)
W. W. FOUNDATION DRILLING, LTD. (5.98)
CHOCTAW ERECTORS, INC. (16.77)
PROFFESSIONAL TRAFFIC CONTROL, LLC. (0.20)
Contract #08163003
Totals23247170.43419200.7714111507.6560.7