Monthly State Let Construction Report For Houston District As Of Apr 12, 2024 Page 3 Of 13

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyBRAZORIA
HighwayBS 288B
FromFM 523
ToFM 521
CSJ0111-09-042
Proj IDC 111-9-42
Work TypeOVERLAY
 
5.79510948342.4310044443.0291.7
Work Order01-04-23
Work Began06-19-23
Work Completed
Time Computed05-04-23
Contract Working Days163
Addl Days Granted0
Working Days Charged165
Percent Time Used101
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0111-09-042
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (1.42)
MAIN LANE INDUSTRIES LTD. (1.69)
STRIPE LINES, INC. (2.65)
THIRD COAST SERVICES LLC (2.96)
TRAFFIC SIGNS & LINES, LLC (0.87)
INTERSTATE BARRICADES & MARKINGS, INC. (0.12)
HOLES INCORPORATED (0.06)
CREACOM, INC. (0.07)
PROFESSIONAL TRAFFIC CONTROL LLC (0.09)
Contract #12223210
Totals10948342.4322730.8610044443.0291.7

CountyBRAZORIA
HighwayBS 288B
FromSH 35
ToFM 523
CSJ0111-09-044
Proj IDC 111-9-44
Work TypeOVERLAY
 
4.8933933801.944542861.9599.9
Work Order05-10-22
Work Began08-17-22
Work Completed
Time Computed06-09-22
Contract Working Days144
Addl Days Granted3
Working Days Charged143
Percent Time Used97
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0111-09-044
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (2.54)
CREACOM, INC. (4.11)
INTERSTATE BARRICADES & MARKINGS, INC. (0.39)
PINNACLE GRINDING AND GROOVING LLC (8.74)
TRAFFIC SIGNS & LINES, LLC (3.60)
MAIN LANE INDUSTRIES LTD. (0.58)
Contract #04223011
Totals3933801.940.004542861.9599.9

CountyWALLER
HighwayUS 290
FromEAST OF FM 362
ToWEST OF FM 362.
CSJ0114-11-082
Proj IDNH 2B20(183)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.2014591144.057942095.1099.9
Work Order10-21-20
Work Began01-21-21
Work Completed
Time Computed11-20-20
Contract Working Days271
Addl Days Granted162
Working Days Charged531
Percent Time Used122
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-11-082
A&J REBAR LLC (0.21)
GMJ PAVING CO. (1.04)
ROMAR UNLIMITED, INC. (0.93)
REPUBLIC TRAFFIC SAFETY, INC. (1.26)
SCOTT DERR PAINTING CO, LLC (0.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.89)
PROFESSIONAL TRAFFIC CONTROL LLC (1.33)
CITYLYNX, INC. (5.22)
OSCAR ORDUNO, INC. (45.63)
GOULD INDUSTRIES LLC (14.23)
CURB PLANET INC. (0.16)
Contract #09203215
Totals4591144.05193921.977942095.1099.9

CountyWALLER
HighwayUS 290
FromJAMES MUSE PARKWAY
ToNORTH OF FM 362
CSJ0114-11-086
Proj IDC 114-11-86
Work TypeNEW LOCATION NON-FREEWAY
 
10942905.023300725.5330.1
Work Order04-12-23
Work Began10-12-23
Work Completed
Time Computed07-11-23
Contract Working Days304
Addl Days Granted0
Working Days Charged115
Percent Time Used37
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-11-086
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (5.03)
HOUSTON CRUSHED CONCRETE, L.L.C. (0.12)
TRAFFIC SIGNS & LINES, LLC (0.92)
FARR FOUNDATION, INC. (0.98)
MESA ROD BUSTERS, INC. (0.94)
SPECIALTY DRILLING, LLC (0.80)
THIRD COAST SERVICES LLC (6.83)
AARON CONCRETE CONTRACTORS, LLC (0.82)
MD LAWN & LANDSCAPE LLC (0.14)
Contract #11223010
Totals10942905.02431812.503300725.5330.1

CountyWALLER ETC
HighwayUS 290 ETC
FromBLASINGAME/OLD HOWTH RD (W OF SH 6)
ToWALLER/HARRIS COUNTY LINE
CSJ0114-11-088
Proj IDF 2022(096)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
47.7443145018.501876801.0459.6
Work Order12-16-21
Work Began04-03-23
Work Completed
Time Computed01-15-22
Contract Working Days120
Addl Days Granted0
Working Days Charged108
Percent Time Used90
Contractor(s)
YELLOWSTONE LANDSCAPE - CENTRAL, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-11-088
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11213222
Totals3145018.5054291.321876801.0459.6

CountyWALLER
HighwayUS 290
FromWASHINGTON C/L
ToHARRIS C/L
CSJ0114-11-094
Proj IDSTP 2024(635)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
12.7721936235.790.000.0
CountyHARRIS
HighwayUS 290
FromWALLER C/L
ToFIELDS STORE RD.
CSJ0114-12-016
Proj IDSTP 2024(635)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
34359.210.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days189
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-11-094
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04243016
Totals1970595.000.000.000.0

CountyHARRIS
HighwayUS 290
FromWALLER COUNTY LINE
ToEAST OF HEGAR ROAD
CSJ0114-12-012
Proj IDF 2023(685)
Work TypeOVERLAY
 
6.5343991011.244115037.9499.9
Work Order05-05-23
Work Began06-19-23
Work Completed
Time Computed06-04-23
Contract Working Days53
Addl Days Granted0
Working Days Charged128
Percent Time Used241
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0114-12-012
WILLIAMS ROAD, LLC (4.64)
HIGHWAY 1 LLC (7.32)
Contract #04233017
Totals3991011.240.004115037.9499.9

CountyHARRIS
HighwayUS 290
FromAT HEGAR ROAD AND FIELD STORE ROAD
To.
CSJ0114-12-015
Proj IDC 114-12-15
Work TypeCULVERT & STORM DRAINAGE WORK
 
0.379425417.80477213.97100.0
Work Order04-12-23
Work Began05-22-23
Work Completed04-08-24
Time Computed05-12-23
Contract Working Days60
Addl Days Granted0
Working Days Charged51
Percent Time Used85
Contractor(s)
FORDE CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0114-12-015
K4 ENVIRONMENTAL LLC (11.11)
ROMAR UNLIMITED, INC. (3.87)
Contract #03233238
Totals425417.800.00477213.97100.0

CountyMONTGOMERY
HighwayIH 69
FromHARRIS COUNTY LINE
ToLIBERTY COUNTY LINE
CSJ0177-05-112
Proj IDC 177-5-112
Work TypeCORRIDOR TRAFFIC MANAGEMENT
 
17.7303716482.69541164.7914.5
Work Order11-16-22
Work Began00-00-00
Work Completed
Time Computed12-16-22
Contract Working Days270
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-05-112
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10223204
Totals3716482.690.00541164.7914.5

CountyHARRIS
HighwayIH 69
FromSL 8 EAST
ToFM 1960
CSJ0177-07-118
Proj IDC 177-7-118
Work TypeTRAFFIC CONTROL DEVICES
 
3.407975659.051328303.6999.9
Work Order01-18-23
Work Began05-05-23
Work Completed
Time Computed02-17-23
Contract Working Days109
Addl Days Granted0
Working Days Charged92
Percent Time Used84
Contractor(s)
STRIPE LINES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-07-118
HIGHWAY 1 LLC (49.45)
Contract #12223018
Totals975659.05198106.861328303.6999.9

CountyHARRIS
HighwayIH 69
FromIH 69 NB
ToIH 610 WB
CSJ0177-11-159
Proj IDSTP 2023(018)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
1.640184301.3096507.0052.3
Work Order10-19-22
Work Began00-00-00
Work Completed
Time Computed11-18-22
Contract Working Days20
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REPUBLIC TRAFFIC SAFETY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-11-159
SAFETEX,INC. (0.00)
Contract #09223229
Totals184301.300.0096507.0052.3

CountyHARRIS
HighwayIH 69
FromIH 69 SB
ToIH 10 EB
CSJ0177-11-160
Proj IDSTP 2024(483)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.300150592.500.000.0
CountyHARRIS
HighwayIH 10
FromIH 10 WB
ToIH 69 NB
CSJ0508-01-387
Proj IDSTP 2024(483)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
401765.000.000.0
CountyHARRIS
HighwayVA
FromVARIOUS LOCATIONS ON IH 610
To.
CSJ0912-72-744
Proj IDF 2024(482)
Work TypeTRAFFIC CONTROL DEVICES
 
31.4791350083.500.000.0
Work Order02-21-24
Work Began00-00-00
Work Completed
Time Computed03-22-24
Contract Working Days113
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 0177-11-160
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12233209
Totals1902441.000.000.000.0

CountyMONTGOMERY
HighwaySL 494
FromN OF KINGWOOD DR
ToHARRIS C/L
CSJ0177-14-010
Proj IDSTP 1802(602)
Work TypeWDN GR, STRS, BS & PAV
 
1.83514347428.7321657427.2899.9
Work Order02-20-19
Work Began07-08-19
Work Completed
Time Computed03-22-19
Contract Working Days384
Addl Days Granted331
Working Days Charged1,012
Percent Time Used141
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0177-14-010
ADCOCK 4 INVESTMENTS, LLC (5.32)
BLACKTOP INDUSTRIES LLC (0.16)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.38)
TRAF-TEX, INC. (1.89)
LONESTAR TRAFFIC SAFETY, LLC (0.22)
ROMAR UNLIMITED, INC. (0.79)
JAMES CONSTRUCTION GROUP, L.L.C. (3.31)
BATTERSON, LLP (0.87)
TEXOP CONSTRUCTION (0.97)
DORAN STEEL, INC. (1.50)
P&Z LOGISTICS INC. (0.12)
CURB PLANET INC. (0.11)
HIGHWAY PAVEMENT SPECIALTIES, INC. (0.27)
WM TRUCKING & EXCAVATING INC. (0.64)
LINDSEY CONSTRUCTION, INC. (0.00)
ARANDA BROTHERS CONSTRUCTION CO., INC. (0.00)
HOUSTON SAWING & DRILLING (0.04)
AIMS COMPANIES (0.01)
JASSO"S SAWING & SEALING (0.18)
TEXAS MATERIALS GROUP, INC. (0.33)
Contract #08183010
Totals14347428.730.0021657427.2899.9

CountyMONTGOMERY
HighwaySL 494
FromFM 1485 WEST
ToFM 1485 EAST
CSJ0177-14-037
Proj IDC 177-14-37
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.3111321754.751803869.7099.9
Work Order01-12-22
Work Began05-02-22
Work Completed
Time Computed05-12-22
Contract Working Days92
Addl Days Granted0
Working Days Charged86
Percent Time Used93
Contractor(s)
MAIN LANE INDUSTRIES LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0177-14-037
LONESTAR TRAFFIC SAFETY, LLC (0.33)
TRAF-TEX, INC. (10.04)
T&T TRUCKING (1.03)
BATTERSON, LLP (1.79)
WILLOW CITY SIGN & RAIL, INC. (3.79)
SLS CONSTRUCTION, INC. (6.80)
JB PINNACLE GROUP, LLC (3.62)
J KRU LAND SERVICES, LLC (0.62)
SCOTT DERR PAINTING CO, LLC (0.11)
Contract #10213016
Totals1321754.750.001803869.7099.9

CountyMONTGOMERY
HighwaySL 494
FromAT CANEY CREEK
To.
CSJ0177-14-039
Proj IDBR 2022(511)
Work TypeBRIDGE REPLACEMENT
 
8553522.778552876.8999.9
Work Order06-09-22
Work Began09-07-22
Work Completed
Time Computed09-07-22
Contract Working Days211
Addl Days Granted0
Working Days Charged210
Percent Time Used99
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0177-14-039
J. T. B. SERVICES, INC. (1.84)
MESA ROD BUSTERS, INC. (0.64)
LONESTAR TRAFFIC SAFETY, LLC (0.08)
SCOTT DERR PAINTING CO, LLC (0.14)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.04)
WILLOW CITY SIGN & RAIL, INC. (1.27)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.81)
MESA ROD BUSTERS, INC. (0.38)
MARTIN MARIETTA MATERIALS, INC. (0.41)
PRIMATE CONSTRUCTION, LP (0.12)
AARON CONCRETE CONTRACTORS, LLC (2.06)
MTAM CORPORATION (0.09)
HIGHWAY 1 LLC (0.19)
TEXAS CUTTING & CORING GP, INC. (0.22)
Contract #05223209
Totals8553522.778507.908552876.8999.9

CountyHARRIS
HighwaySH 35
FromAT BELFORT AVE
To.
CSJ0178-01-037
Proj IDSTP 2021(188)HES
Work TypeTRAFFIC CONTROL DEVICES
 
0.200313438.45414203.5799.9
Work Order01-14-21
Work Began09-15-23
Work Completed
Time Computed05-14-21
Contract Working Days38
Addl Days Granted0
Working Days Charged33
Percent Time Used86
Contractor(s)
STATEWIDE TRAFFIC SIGNAL COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0178-01-037
HIGHWAY 1 LLC (2.78)
REDLINE CONSTRUCTION SERVICES LLC (10.22)
Contract #12203221
Totals313438.4511088.70414203.5799.9

CountyHARRIS
HighwaySH 35
From0.1 MILE NORTH OF SL 8
To0.1 MILE SOUTH OF SL 8
CSJ0178-01-042
Proj IDSTP 2023(893)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200685716.92200928.0029.3
CountyGALVESTON
HighwayFM 2004
FromAT FM 646
To.
CSJ2523-01-029
Proj IDSTP 2023(893)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200154561.510.000.0
CountyGALVESTON
HighwayFM 646
From0.1 MI N OF 28TH ST
To0.1 MI S OF 28TH ST
CSJ2523-03-013
Proj IDSTP 2023(893)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.200145241.270.000.0
Work Order08-03-23
Work Began00-00-00
Work Completed
Time Computed12-01-23
Contract Working Days153
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0178-01-042
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06233633
Totals985519.700.00200928.0020.3

CountyBRAZORIA
HighwaySH 35
FromFM 523
ToFM 2403
CSJ0178-03-156
Proj IDC 178-3-156
Work TypeOVERLAY
 
15.40020773975.765575270.2926.8
Work Order07-06-22
Work Began10-11-22
Work Completed
Time Computed09-05-22
Contract Working Days416
Addl Days Granted30
Working Days Charged281
Percent Time Used63
Contractor(s)
DURWOOD GREENE CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0178-03-156
NBG CONSTRUCTORS, INC. (0.50)
WEST TEXAS ROCK RESOURCES, LLC (0.10)
PROFESSIONAL TRAFFIC CONTROL LLC (2.76)
INTERSTATE BARRICADES & MARKINGS, INC. (0.11)
TRAFFIC SIGNS & LINES, LLC (2.10)
TRAFFIC SYSTEMS CONSTRUCTION, INC. (0.83)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C. (1.18)
Contract #06223207
Totals20773975.76193121.675575270.2926.8

CountyBRAZORIA
HighwaySH 35
FromFM 523
ToBS 288B
CSJ0178-03-158
Proj IDC 178-3-158
Work TypeOVERLAY
 
4.8944500659.534084327.1491.0
Work Order05-10-22
Work Began06-09-22
Work Completed
Time Computed06-09-22
Contract Working Days101
Addl Days Granted0
Working Days Charged114
Percent Time Used112
Contractor(s)
JAMES CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0178-03-158
BATTERSON, LLP (0.26)
DUSTROL, INC. (2.25)
WILLOW CITY SIGN & RAIL, INC. (5.25)
WEST TEXAS ROCK RESOURCES, LLC (0.14)
PROFESSIONAL TRAFFIC CONTROL LLC (6.58)
MAIN LANE INDUSTRIES LTD. (6.91)
PFEIFFER & SON LTD. (4.37)
SWEEPING CORPORATION OF AMERICA, LLC (0.35)
CPAVE, INC. (0.11)
HOLES INCORPORATED (0.03)
WALLACE CONCRETE SAWING, LLC (0.80)
Contract #04223211
Totals4500659.530.004084327.1491.0

CountyHARRIS
HighwaySH 35
FromGRIGGS ROAD
ToIH 45/SPUR 5
CSJ0178-09-018
Proj IDC 178-9-18
Work TypeNEW LOCATION FREEWAY
 
1.81092261473.1235962200.8238.9
CountyHARRIS
HighwaySH 35
FromGRIGGS ROAD
ToIH 45/SPUR 5
CSJ0178-09-032
Proj IDROW 178-9-18
Work TypeRIGHT OF WAY
 
1.8101684303.901246800.5874.0
Work Order04-05-23
Work Began04-13-23
Work Completed
Time Computed04-13-23
Contract Working Days597
Addl Days Granted427
Working Days Charged278
Percent Time Used27
Contractor(s)
WILLIAMS BROTHERS CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0178-09-018
LONG LEGACY ENTERPRISES, LLC (0.03)
HIGHWAY 1 LLC (0.44)
ALLSTATE SIGNAL & CONSTRUCTION, LLC (5.12)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LTD. (0.73)
SCOTT DERR PAINTING CO, LLC (0.00)
BASE CONSTRUCTION L.L.P. (8.17)
QUALITY TURF FARMS, L.C. (0.56)
SK CONCRETE SERVICES LLC (0.19)
MESA ROD BUSTERS, INC. (1.18)
BELL BOTTOM FOUNDATION CO. (3.20)
AMERICAN INFRASTRUCTURE MAINTENANCE MANAGEMENT LLC (0.08)
DORAN STEEL, INC. (0.25)
Contract #03233001
Totals93945777.022201328.3637209001.4039.6

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8 | page 9 | page 10 | page 11 | page 12 | page 13