Monthly State Let Construction Report For Dallas District As Of Sep 10, 2024 Page 5 Of 8

Last Update: Tuesday, September 10, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyKAUFMAN
HighwayFM 148
FromFM 2613
ToSH 274
CSJ0751-03-043
Proj IDF 2024(168)
Work TypeRESTORATION
 
4.7469345341.96993416.9310.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-08-24
Work Began06-03-24
Work Completed
Time Computed00-00-00
Contract Working Days294
Addl Days Granted0
Working Days Charged50
Percent Time Used17
Contractor(s)
BAKER & COMPANY CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0751-03-043
FLEX SUPPLY, LLC (0.32)
TEXANA LAND & ASPHALT, INC. (28.15)
STRIPING TECHNOLOGY, L.P. (1.26)
AWP SAFETY (0.69)
JM YANEZ CONSTRUCTION, INC. (6.51)
NEED GRASS NOW LLC (3.09)
PROFESSIONAL TRAFFIC CONTROL LLC (0.13)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.94)
A. L. HELMCAMP, INC. (0.34)
COLD CREEK CONSTRUCTION, LTD (1.16)
CARTHAGE DRILLING, LLC (0.01)
DUSTROL, INC. (0.13)
SOUTHWEST ENVIRONMENT SERVICES LLC (0.73)
Contract #04243030
Totals9345341.96434697.85993416.9310.6

CountyDENTON
HighwayFM 455
FromAT CLEAR CREEK
To.
CSJ0816-02-083
Proj IDBR 2023(437)
Work TypeBRIDGE REPLACEMENT
 
4788222.294555804.1896.4
Work Order03-16-23
Work Began08-07-23
Work Completed
Time Computed08-07-23
Contract Working Days138
Addl Days Granted0
Working Days Charged205
Percent Time Used148
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0816-02-083
BRENDA PRICE TRUCKING (0.62)
DFW REBAR, INC. (0.35)
DUSTROL, INC. (0.82)
HODGES AND SON CONSTRUCTION COMPANY, INC. (3.55)
PEACHTREE CONSTRUCTION, LTD. (5.42)
SOUTHEAST GRINDING AND GROOVING LLC (0.08)
SOUTHERN CROSS CONTRACTORS, LLC (0.64)
STRIPING TECHNOLOGY, L.P. (0.77)
TEXAS SWPPP SERVICES (0.06)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.78)
MASSEY CONTRACTORS, LLC (4.42)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (4.29)
AWP SAFETY (0.57)
Contract #02233221
Totals4788222.29127640.064555804.1896.4

CountyDENTON
HighwayFM 455
FromAT PECAN CREEK
To.
CSJ0816-03-020
Proj IDBR 2022(430)
Work TypeBRIDGE REPLACEMENT
 
0.1141968730.151892751.6299.9
CountyDENTON
HighwayFM 455
FromAT MUSTANG CREEK
To.
CSJ0816-03-021
Proj IDBR 2021(140)
Work TypeBRIDGE REPLACEMENT
 
0.2112275217.652171511.9795.4
Work Order05-12-22
Work Began06-23-22
Work Completed
Time Computed06-13-22
Contract Working Days323
Addl Days Granted0
Working Days Charged497
Percent Time Used153
Contractor(s)
NEW WORLD CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0816-03-020
TEXAS SWPPP SERVICES (0.80)
LINDAMOOD, INC. (0.86)
FC TRAFFIC CONTROL, INC. (0.51)
TOTAL HIGHWAY MAINTENANCE, LLC (1.29)
SOUTHERN CROSS CONTRACTORS, LLC (2.40)
TEXOP CONSTRUCTION (0.70)
WYLIE DRILLING & DRAINAGE, INC. (3.40)
PEACHTREE CONSTRUCTION, LTD. (6.47)
MARCOM"S MOWING SERVICE, LLC (0.19)
SITE-SAFE, LLC (1.02)
DALLAS TEXAS LOGISTICS LLC (0.58)
HERMANOS STEEL, LLC (0.21)
HERMANOS STEEL, LLC (0.11)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.00)
A-CORE CONCRETE CUTTING OF TEXAS, INC. (0.28)
IBCTX, LLC (2.37)
DENALI SERVICES & TRANSPORT LLC (0.23)
Contract #04223210
Totals4243947.8030424.894064263.5999.7

CountyCOLLIN
HighwayFM 455
FromAT EAST FORK TRINITY RIVER RELIEF WEST
ToAT EAST FORK TRINITY RIVER RELIEF EAST
CSJ0816-04-104
Proj IDBR 2B24(272)
Work TypeBRIDGE REPLACEMENT
 
0.0325864308.930.000.0
CountyCOLLIN
HighwayFM 455
FromAT HURRICANE CREEK
To.
CSJ0816-04-105
Proj IDBR 2B24(272)
Work TypeBRIDGE REPLACEMENT
 
3716691.070.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-06-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days305
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 0816-04-104
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07243207
Totals9581000.000.000.000.0

CountyCOLLIN
HighwayFM 2862
FromSH 5
ToWESTOVER LANE
CSJ0816-05-025
Proj IDSTP 2023(916)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.6447607273.376386444.6683.9
Work Order11-01-23
Work Began11-08-23
Work Completed
Time Computed11-08-23
Contract Working Days230
Addl Days Granted0
Working Days Charged143
Percent Time Used62
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0816-05-025
FORTSON CONTRACTING, INC. (0.43)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.21)
LINEAR TRAFFIC MARKINGS LLC (0.91)
LOLLAR CONSTRUCTION GROUP LLC (17.11)
MARCOMS CONSTRUCTION LLC (1.32)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.01)
WEST TEXAS ROCK RESOURCES, LLC (0.10)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.55)
KITCHING & CO., LLC (4.42)
Contract #06233220
Totals7607273.37342778.276386444.6683.9

CountyDENTON
HighwayFM 428
FromAT PECAN CREEK
To.
CSJ0817-01-025
Proj IDBR 2022(619)
Work TypeBRIDGE REPLACEMENT
 
0.2443733494.151919479.7051.4
CountyDENTON
HighwayFM 2153
FromAT CULP BRANCH
To.
CSJ2248-01-008
Proj IDBR 2022(620)
Work TypeBRIDGE REPLACEMENT
 
0.1712115046.701451974.4668.6
Work Order07-06-22
Work Began08-08-22
Work Completed
Time Computed08-08-22
Contract Working Days522
Addl Days Granted0
Working Days Charged506
Percent Time Used96
Contractor(s)
ATLANTIC SPECIALTY INSURANCE COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0817-01-025
MORRIS COUNTY CONTRACTORS, L.L.C. (3.26)
TOTAL HIGHWAY MAINTENANCE, LLC (0.90)
TEXAS TRAFFIC AND BARRICADE, LLC (0.51)
BARRICADES UNLIMITED (0.77)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.00)
TRP CONSTRUCTION GROUP, LLC (0.49)
PENHALL COMPANY (0.14)
BRENDA PRICE TRUCKING, INC. (2.07)
CIVIL TREE SOLUTIONS, LLC (0.27)
DFW REBAR, INC. (0.17)
PEACHTREE CONSTRUCTION, LTD. (6.21)
SOUTHEAST GRINDING AND GROOVING LLC (0.17)
STOIC CIVIL CONSTRUCTION, INC. (3.89)
SUPERIOR TRAFFIC CONTROL, LLC (0.51)
SYNERGY SIGNS & SERVICES LLC (1.29)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.47)
TEX OP CONSTRUCTION, LP (1.26)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.77)
TEXAS SWPPP SERVICES (1.01)
WYLIE DRILLING & DRAINAGE, INC. (2.47)
ED BELL CONSTRUCTION COMPANY (0.00)
WEST TEXAS ROCK RESOURCES, LLC (0.09)
Contract #06223011
Totals5848540.85196249.103371454.1657.6

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-330
Proj IDC 918-00-330
Work TypeTRAFFIC CONTROL DEVICES
 
2444000.002107307.2886.2
Work Order10-14-21
Work Began07-19-22
Work Completed
Time Computed02-11-22
Contract Working Days913
Addl Days Granted0
Working Days Charged775
Percent Time Used84
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-330
ROAD MASTER STRIPING, LLC (3.31)
JR WEST TEXAS CONCRETE LLC (1.82)
Contract #09213010
Totals2444000.000.002107307.2886.2

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-351
Proj IDC 918-00-351
Work TypeTRAFFIC CONTROL DEVICES
 
4521287.501417220.6731.3
Work Order10-06-22
Work Began08-11-23
Work Completed
Time Computed08-07-23
Contract Working Days913
Addl Days Granted0
Working Days Charged391
Percent Time Used42
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-351
ROAD MASTER STRIPING, LLC (1.85)
JR WEST TEXAS CONCRETE LLC (0.18)
SALCOMM, LLC (0.20)
Contract #09223209
Totals4521287.5026389.951417220.6731.3

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-00-365
Proj IDSTP 2024(788)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
328723.320.000.0
CountyDENTON
HighwayFM 423
FromUS 380
ToFM 720
CSJ1315-02-015
Proj IDSTP 2024(793)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
41520.000.000.0
CountyDENTON
HighwayFM 423
FromFM 720
ToMAIN STREET
CSJ1567-01-043
Proj IDSTP 2024(793)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
35412.500.000.0
CountyDENTON
HighwayFM 423
FromMAIN STREET
ToLEBANON RD
CSJ1567-02-038
Proj IDSTP 2024(793)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
40487.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-03-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days50
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-365
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03243230
Totals446143.320.000.000.0

CountyDALLAS
HighwayVA
FromVARIOUS LOCATION
ToIN THE DALLAS DISTRICT
CSJ0918-00-380
Proj IDF 2024(016)
Work TypeTRAFFIC CONTROL DEVICES
 
4157640.25212805.005.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-23-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days913
Addl Days Granted0
Working Days Charged53
Percent Time Used5
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-380
ROAD MASTER STRIPING, LLC (2.17)
Contract #09233017
Totals4157640.2511442.00212805.005.1

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT.
CSJ0918-00-392
Proj IDC 918-00-392
Work TypeTRAFFIC CONTROL DEVICES
 
4859646.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days913
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-392
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09243019
Totals4859646.000.000.000.0

CountyDALLAS
HighwayVA
FromVARIOUS LOCATIONS
ToIN DALLAS COUNTY
CSJ0918-00-430
Proj IDC 918-00-430
Work TypeREHABILITATION OF EXISTING ROAD
 
4441943.110.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days153
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STRIPE-A-ZONE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-00-430
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05243026
Totals4441943.110.000.000.0

CountyKAUFMAN
HighwayVA
FromVARIOUS LOCATIONS
ToIN THE DALLAS DISTRICT
CSJ0918-11-110
Proj IDC 918-11-110
Work TypePEDESTRIAN, SIDEWALKS & CURB RAMPS
 
3012842.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days172
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-11-110
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243013
Totals3012842.000.000.000.0

CountyNAVARRO
HighwayCR
FromAT MILL CREEK
To.
CSJ0918-18-133
Proj IDBR 2022(309)
Work TypeBRIDGE REPLACEMENT
 
945715.80988290.5699.9
CountyNAVARRO
HighwayCR
FromAT RUSH CREEK TRIBUTARY
To.
CSJ0918-18-136
Proj IDBR 2022(311)
Work TypeBRIDGE REPLACEMENT
 
529117.9044250.008.3
CountyNAVARRO
HighwayCR
FromAT PIN OAK CREEK
To.
CSJ0918-18-137
Proj IDBR 2022(308)
Work TypeBRIDGE REPLACEMENT
 
875988.9044250.005.0
CountyNAVARRO
HighwayCR
FromAT RUSH CREEK
To.
CSJ0918-18-138
Proj IDBR 2022(314)
Work TypeBRIDGE REPLACEMENT
 
1028699.7097350.009.4
Work Order04-18-24
Work Began06-17-24
Work Completed
Time Computed06-17-24
Contract Working Days210
Addl Days Granted0
Working Days Charged51
Percent Time Used24
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-18-133
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.00)
MORRIS COUNTY CONTRACTORS, L.L.C. (0.00)
TORO BRAVO CONSTRUCTION, LLC (0.00)
TRP CONSTRUCTION GROUP, LLC (0.00)
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.00)
Contract #03243210
Totals3379522.30526893.561174140.5634.7

CountyCOLLIN
HighwayCR
FromCR 696 AT BRUSHY CREEK
To.
CSJ0918-24-254
Proj IDBR 2022(370)
Work TypeBRIDGE REPLACEMENT
 
1089606.631021559.3693.7
CountyCOLLIN
HighwayFM 547
FromAT SABINE CREEK BRANCH NO 1
To.
CSJ1014-01-014
Proj IDBR 2023(917)
Work TypeBRIDGE REPLACEMENT
 
0.0852029755.731341666.4866.0
CountyCOLLIN
HighwayFM 547
FromAT SABINE CREEK
To.
CSJ1014-01-015
Proj IDBR 2023(917)
Work TypeBRIDGE REPLACEMENT
 
0.0781779478.781046188.7258.7
Work Order07-19-23
Work Began08-29-23
Work Completed
Time Computed08-29-23
Contract Working Days290
Addl Days Granted0
Working Days Charged248
Percent Time Used85
Contractor(s)
INDUS ROAD & BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-24-254
WYLIE DRILLING & DRAINAGE, INC. (4.44)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.62)
DUSTROL, INC. (0.53)
HERMANOS STEEL, LLC (0.78)
ODUM SERVICES, LLC (1.35)
PEACHTREE CONSTRUCTION, LTD. (6.60)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.45)
HILBASH INVESTMENT LLC (10.40)
FC TRAFFIC CONTROL, INC. (0.39)
PENHALL COMPANY (0.48)
DFW REBAR, INC. (0.10)
Contract #06233223
Totals4898841.14330794.693409414.5669.5

CountyCOLLIN ETC
HighwayCS
FromRENNER RD AT SHILOH RD
ToIN THE CITY OF RICHARDSON
CSJ0918-24-266
Proj IDSTP 2022(621)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.9413050705.85759064.2924.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-15-22
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days480
Addl Days Granted0
Working Days Charged283
Percent Time Used58
Contractor(s)
DURABLE SPECIALTIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0918-24-266
JR WEST TEXAS CONCRETE LLC (11.45)
ROAD MASTER STRIPING, LLC (4.00)
SALCOMM, LLC (0.83)
Contract #06223220
Totals3050705.85105541.17759064.2924.8

CountyCOLLIN ETC
HighwayCS ETC
FromON FRANKFORD AT DALLAS PKWY
ToIN THE CITY OF DALLAS
CSJ0918-24-267
Proj IDSTP 2024(742)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4872332.750.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-12-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days220
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-24-267
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243224
Totals4872332.750.000.000.0

CountyCOLLIN
HighwayCS
FromAT HEDGECOXE RD
ToIN THE CITY OF ALLEN
CSJ0918-24-272
Proj IDSTP 2023(857)HESG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.4002574587.50415019.1016.1
Work Order10-06-23
Work Began03-20-24
Work Completed
Time Computed02-03-24
Contract Working Days440
Addl Days Granted0
Working Days Charged131
Percent Time Used29
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-24-272
AAA DRILLING FOUNDATION COMPANY, INC. (0.81)
Contract #06233021
Totals2574587.508500.00415019.1016.1

CountyCOLLIN
HighwayCS
FromON JUPITER RD AT RENNER RD
ToIN THE CITY OF RICHARDSON
CSJ0918-24-278
Proj IDSTP 2B24(164)VRUG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
602317.980.000.0
CountyDALLAS
HighwayCS
FromON CAMPBELL RD AT PLANO RD
ToIN THE CITY OF RICHARDSON
CSJ0918-47-400
Proj IDSTP 2B24(164)VRUG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
628156.300.000.0
CountyDALLAS
HighwayCS
FromON ELAM RD AT SHEPHERD LANE
ToIN THE CITY OF BALCH SPRINGS
CSJ0918-47-417
Proj IDSTP 2B24(458)VRUG
Work TypeSAFETY IMPROVEMENT PROJECTS
 
543810.780.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-22-24
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days80
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
YUNEX LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-24-278
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06243040
Totals1774285.060.000.000.0

CountyCOLLIN ETC
HighwayCS ETC
FromAT ALLEN HEIGHTS
ToIN THE CITY OF ALLEN
CSJ0918-24-290
Proj IDSTP 2B24(339)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.3002208225.170.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0918-24-290
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08243236
Totals2208225.170.000.000.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7 | page 8