Monthly State Let Construction Report For Dallas District As Of Mar 13, 2024 Page 6 Of 7

Last Update: Wednesday, March 13, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyCOLLIN
HighwayFM 546
FromAT FM 3286 INTERSECTION
To.
CSJ1013-01-038
Proj IDSTP 2023(356)HES
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.8403312753.833322064.8499.9
Work Order02-14-23
Work Began06-12-23
Work Completed
Time Computed06-12-23
Contract Working Days90
Addl Days Granted46
Working Days Charged134
Percent Time Used98
Contractor(s)
A. K. GILLIS & SONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1013-01-038
BAHENA CONSTRUCTION CO.,INC. (7.42)
FORTSON CONTRACTING, INC. (0.20)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (22.80)
SOUTHERN CROSS CONTRACTORS, LLC (0.70)
TEXAS TRAFFIC AND BARRICADE, LLC (0.35)
TEXOP CONSTRUCTION (1.98)
TRP CONSTRUCTION GROUP, LLC (0.71)
WG ENGINEERING & CONSTRUCTION, LLC (6.26)
MEDELLIN HDD LLC (0.07)
A. E. MOORE CONSTRUCTION, INC. (2.89)
WEST TEXAS ROCK RESOURCES, LLC (0.13)
AWP SAFETY (0.06)
Contract #01233220
Totals3312753.8392608.643322064.8499.9

CountyROCKWALL
HighwayFM 548
FromAT PARKER CREEK
To.
CSJ1014-02-043
Proj IDBR 2023(416)
Work TypeBRIDGE REPLACEMENT
 
0.1814090390.333514127.2086.2
Work Order03-06-23
Work Began04-23-23
Work Completed
Time Computed04-05-23
Contract Working Days102
Addl Days Granted0
Working Days Charged118
Percent Time Used115
Contractor(s)
INDUS ROAD & BRIDGE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1014-02-043
PENHALL COMPANY (0.09)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.41)
HERMANOS STEEL, LLC (3.18)
FORTSON CONTRACTING, INC. (1.34)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.59)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (4.72)
WYLIE DRILLING & DRAINAGE, INC. (2.27)
TEXOP CONSTRUCTION (0.48)
DFW REBAR, INC. (0.16)
TRP CONSTRUCTION GROUP, LLC (0.65)
FC TRAFFIC CONTROL, INC. (0.06)
Contract #01233235
Totals4090390.3363493.583514127.2086.2

CountyDALLAS
HighwayFM 1382
FromSH 180
ToIH 20
CSJ1047-03-074
Proj IDSTP 2023(937)MM
Work TypeREHABILITATION OF EXISTING ROAD
 
5.2962358226.462598053.7399.9
CountyDALLAS
HighwayFM 1382
FromAT AVION PARKWAY
To.
CSJ1047-03-081
Proj IDC 1047-3-81
Work TypeSAFETY IMPROVEMENT PROJECTS
 
0.050141700.00141700.0099.9
Work Order06-28-23
Work Began08-07-23
Work Completed
Time Computed07-26-23
Contract Working Days101
Addl Days Granted0
Working Days Charged104
Percent Time Used102
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1047-03-074
MOBILE ENTERPRISES, INC. (2.30)
BARRICADES UNLIMITED (0.62)
TEXAS MATERIALS GROUP, INC. (9.57)
FORTSON CONTRACTING, INC. (1.99)
BRENDA PRICE TRUCKING (1.61)
DUSTROL, INC. (1.74)
MICA CORPORATION (11.61)
ACT SAW CUTTING & REMOVAL (2.09)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.87)
TRAFFIC HIGHWAY MAINTENANCE, LLC (10.12)
Contract #05233026
Totals2499926.46244991.852739753.7399.9

CountyDALLAS
HighwayFM 1382
From700' NORTH OF CAMP WISDOM RD
To400' SOUTH OF W SPINE RD
CSJ1047-03-076
Proj IDSTP 2023(439)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
4.1441018737.20752132.3680.2
CountyDALLAS
HighwayFM 1382
FromNORTH OF PENN BRANCH PKWY
To.
CSJ1047-03-080
Proj IDF 2023(445)
Work TypeCULVERT & STORM DRAINAGE WORK
 
0.7292982121.002413193.4380.9
Work Order03-16-23
Work Began05-01-23
Work Completed
Time Computed05-01-23
Contract Working Days97
Addl Days Granted0
Working Days Charged167
Percent Time Used172
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1047-03-076
TITAN UTILITY SERVICES (16.59)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.48)
Contract #02233220
Totals4000858.20180274.143165325.7980.7

CountyDALLAS
HighwayFM 1382
FromCAMP WISDOM INTERSECTION
ToMANSFIELD RD
CSJ1047-03-079
Proj IDSTP 2024(350)TP
Work TypeBICYCLE INFRASTRUCTURE IMPROVEMENTS
 
1.1684250000.000.000.0
Work Order12-13-23
Work Began03-04-24
Work Completed
Time Computed01-12-24
Contract Working Days203
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS-REYES GROUP LTD.
SUBCONTRACTOR(S) FOR CCSJ: 1047-03-079
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (7.91)
SUPERIOR TRAFFIC CONTROL, LLC (0.20)
Contract #11233211
Totals4250000.000.000.000.0

CountyELLIS
HighwayFM 813
FromSIOUX DRIVE
ToSAPPHIRE LANE
CSJ1139-01-048
Proj IDF 2B23(108)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.2051051513.50206500.0019.6
Work Order09-07-23
Work Began11-27-23
Work Completed
Time Computed10-09-23
Contract Working Days100
Addl Days Granted0
Working Days Charged28
Percent Time Used28
Contractor(s)
FNH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1139-01-048
ROAD SOLUTIONS L.L.C. (29.26)
KING GEORGE TRAFFIC SOLUTIONS LLC (1.71)
Contract #08233060
Totals1051513.50143000.00206500.0019.6

CountyDENTON
HighwayFM 1171
FromAT FM 2499 (LONG PRAIRIE ROAD)
To.
CSJ1311-01-060
Proj IDCM 2023(987)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
0.110845850.437950.990.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-03-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days81
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
SEMA CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1311-01-060
ALLIANCE GEOTECHNICAL GROUP, INC. (0.46)
Contract #06233636
Totals845850.430.007950.990.9

CountyDENTON
HighwayFM 1385
FromNORTH OF FM 428
ToFM 455
CSJ1315-01-028
Proj IDF 2023(171)
Work TypeREHABILITATION OF EXISTING ROAD
 
5.0087569742.932024816.3726.7
Work Order12-07-22
Work Began01-11-23
Work Completed
Time Computed01-09-23
Contract Working Days304
Addl Days Granted0
Working Days Charged183
Percent Time Used60
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1315-01-028
BARRICADES UNLIMITED (0.15)
DUSTROL, INC. (0.58)
TEXOP CONSTRUCTION (1.43)
PEACHTREE CONSTRUCTION, LTD. (5.17)
TRP CONSTRUCTION GROUP, LLC (1.01)
Contract #11223213
Totals7569742.9381431.282024816.3726.7

CountyCOLLIN
HighwayFM 1377
From4TH STREET
ToS. OF CR 466
CSJ1391-01-021
Proj IDF 2023(105)
Work TypeREHABILITATION OF EXISTING ROAD
 
5.7867597592.926894766.3090.7
Work Order10-13-22
Work Began11-07-22
Work Completed
Time Computed11-07-22
Contract Working Days236
Addl Days Granted0
Working Days Charged233
Percent Time Used98
Contractor(s)
A. K. GILLIS & SONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1391-01-021
CATOCON, INC. (0.66)
FORTSON CONTRACTING, INC. (0.30)
MICA CORPORATION (0.79)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (19.86)
SOUTHERN CROSS CONTRACTORS, LLC (1.58)
TEXOP CONSTRUCTION (0.93)
TEXAS TRAFFIC AND BARRICADE, LLC (0.27)
BAHENA CONSTRUCTION CO.,INC. (17.52)
DURABLE SPECIALTIES, INC. (0.79)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.97)
J. H. ODEN CONTRACTING COMPANY (0.26)
WEST TEXAS ROCK RESOURCES, LLC (0.08)
Contract #09223237
Totals7597592.9213076.916894766.3090.7

CountyCOLLIN
HighwayFM 1377
From0.269 MILE SOUTH OF CR 466
ToFM 545
CSJ1391-01-022
Proj IDSTP 2023(107)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.8628279604.087654376.1092.4
Work Order10-13-22
Work Began11-07-22
Work Completed
Time Computed11-07-22
Contract Working Days255
Addl Days Granted0
Working Days Charged256
Percent Time Used100
Contractor(s)
A. K. GILLIS & SONS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1391-01-022
CATOCON, INC. (0.76)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (21.26)
SOUTHERN CROSS CONTRACTORS, LLC (2.76)
TEXOP CONSTRUCTION (0.98)
TRAFFIC HIGHWAY MAINTENANCE, LLC (1.00)
TEXAS TRAFFIC AND BARRICADE, LLC (0.23)
BAHENA CONSTRUCTION CO.,INC. (14.82)
FARR FOUNDATION, INC. (0.90)
J. H. ODEN CONTRACTING COMPANY (0.38)
WEST TEXAS ROCK RESOURCES, LLC (0.11)
Contract #09223030
Totals8279604.08207354.797654376.1092.4

CountyCOLLIN
HighwayFM 1378
FromFM 3286
ToSOUTH OF FM 3286
CSJ1392-01-044
Proj IDCM 2023(702)
Work TypeINTERSECTION & OPERATIONAL IMPRV
 
1.14811745456.811137565.639.6
CountyCOLLIN
HighwayFM 1378
FromFM 3286
ToSOUTH OF FM 3286
CSJ1392-01-049
Proj IDROW 1392-01-049
Work TypeRIGHT OF WAY
 
0.6211893884.43123403.806.5
Work Order06-14-23
Work Began10-16-23
Work Completed
Time Computed10-16-23
Contract Working Days659
Addl Days Granted0
Working Days Charged102
Percent Time Used15
Contractor(s)
ED BELL CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 1392-01-044
ACT SAW CUTTING & REMOVAL (0.13)
BREDA COMPANY, INC. (0.38)
BRENDA PRICE TRUCKING (1.69)
TEX-BRASKA, LLC (0.00)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (1.98)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (0.57)
AWP SAFETY (0.63)
DURABLE SPECIALTIES, INC. (3.82)
SYNERGY SIGNS & SERVICES LLC (0.33)
T-BAR FENCE, INC. (0.24)
TEXOP CONSTRUCTION (1.98)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.92)
VENUS CONSTRUCTION COMPANY (13.03)
Contract #05233209
Totals13639341.24361934.001260969.439.2

CountyKAUFMAN
HighwayFM 1391
FromAT CEDAR CREEK RELIEF NO. 2
To.
CSJ1396-01-013
Proj IDBR 2024(767)
Work TypeBRIDGE REPLACEMENT
 
3454424.450.000.0
CountyKAUFMAN
HighwayFM 1391
FromAT CEDAR CREEK
To.
CSJ1396-01-015
Proj IDBR 2024(743)
Work TypeBRIDGE REPLACEMENT
 
0.0171988899.050.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days123
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HIGHWAY 19 CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 1396-01-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02243217
Totals5443323.500.000.000.0

CountyNAVARRO
HighwayFM 55
FromSH 22
ToELLIS COUNTY LINE
CSJ1451-03-017
Proj IDC 1451-3-17
Work TypeRESTORATION
 
4.3474964579.984840996.3598.9
Work Order03-16-22
Work Began04-08-22
Work Completed
Time Computed04-08-22
Contract Working Days210
Addl Days Granted0
Working Days Charged285
Percent Time Used135
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1451-03-017
WOLFE CONSTRUCTION GROUP, INCORPORATED (0.89)
WEST TEXAS ROCK RESOURCES, LLC (0.12)
STRIPE-A-ZONE, LLC (0.78)
MASSEY CONTRACTORS, LLC (1.17)
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (0.40)
FORTSON CONTRACTING, INC. (2.39)
COLD CREEK CONSTRUCTION, LTD (0.82)
BEAR CREEK CONSTRUCTION, LLC (8.07)
AREA WIDE PROTECTIVE, INC. (0.02)
HOUSTON CONST TODAY INC (1.13)
Contract #02223003
Totals4964579.980.004840996.3598.9

CountyDENTON
HighwayFM 423
FromNORTH OF OAK STREET
ToSH 121
CSJ1567-02-037
Proj IDF 2023(342)
Work TypeLANDSCAPE & SCENIC ENHANCEMENT
 
252000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-07-23
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days45
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CENTRAL NORTH CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1567-02-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08233062
Totals252000.000.000.000.0

CountyDENTON
HighwayFM 407
FromWISE COUNTY LINE
ToFM 156
CSJ1568-02-014
Proj IDF 2023(563)
Work TypeREHABILITATION OF EXISTING ROAD
 
6.3966653767.013898067.3658.5
CountyDENTON
HighwayFM 407
FromAVERY RANCH WAY
To1M WEST OF FM 156
CSJ1568-02-015
Proj IDSTP 2023(564)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
2.9572316999.901294624.1755.8
Work Order06-28-23
Work Began08-07-23
Work Completed
Time Computed08-07-23
Contract Working Days203
Addl Days Granted0
Working Days Charged114
Percent Time Used56
Contractor(s)
EUROVIA ATLANTIC COAST LLC
SUBCONTRACTOR(S) FOR CCSJ: 1568-02-014
DALLAS LITE AND BARRICADE, INC. (0.31)
FORTSON CONTRACTING, INC. (0.32)
JR WEST TEXAS CONCRETE LLC (19.20)
MARCOMS CONSTRUCTION LLC (0.69)
TEXOP CONSTRUCTION (1.20)
TRP CONSTRUCTION GROUP, LLC (1.14)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (19.40)
WEST TEXAS ROCK RESOURCES, LLC (0.04)
Contract #03233007
Totals8970766.911378322.555192691.5357.8

CountyNAVARRO
HighwayFM 744
FromFM 55
ToFM 1126 WEST
CSJ1663-03-020
Proj IDC 1663-3-20
Work TypeRESTORATION
 
6.0685714506.656045448.3699.9
Work Order10-20-21
Work Began02-08-22
Work Completed
Time Computed01-07-22
Contract Working Days370
Addl Days Granted0
Working Days Charged348
Percent Time Used94
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1663-03-020
BARRICADES UNLIMITED (0.20)
MURRAY CONSTRUCTION (1.37)
J & M CONSTRUCTION COMPANY (0.00)
WOLFE CONSTRUCTION GROUP, INCORPORATED (2.77)
TRP CONSTRUCTION GROUP, LLC (1.42)
J & M CONTRACTING, COMPANY (0.00)
BEAR CREEK CONSTRUCTION, LLC (0.94)
Contract #09213004
Totals5714506.654624.326045448.3699.9

CountyNAVARRO
HighwayFM 2930
FromFM 55 EAST
ToFM 1126 NORTH IN CRYER CREEK
CSJ1724-03-009
Proj IDC 1724-3-9
Work TypeREHABILITATION OF EXISTING ROAD
 
6.25211334814.78563764.654.9
Work Order09-06-23
Work Began11-27-23
Work Completed
Time Computed10-09-23
Contract Working Days315
Addl Days Granted0
Working Days Charged42
Percent Time Used13
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1724-03-009
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (2.35)
MURRAY CONSTRUCTION (0.54)
STRIPE-A-ZONE, LLC (1.54)
TEXAS TRAFFIC AND BARRICADE, LLC (0.15)
COLD CREEK CONSTRUCTION, LTD (0.70)
FORTSON CONTRACTING, INC. (2.60)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.52)
BEAR CREEK CONSTRUCTION, LLC (25.33)
Contract #08233007
Totals11334814.7813500.00563764.654.9

CountyKAUFMAN
HighwayFM 1895
FromFM 1836
ToBUS US 175 IN KEMP
CSJ1975-02-013
Proj IDC 1975-2-13
Work TypeREHABILITATION OF EXISTING ROAD
 
7.55011181793.392197684.1619.6
Work Order11-16-22
Work Began02-27-23
Work Completed
Time Computed02-20-23
Contract Working Days324
Addl Days Granted0
Working Days Charged197
Percent Time Used60
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1975-02-013
BARRICADES UNLIMITED (0.10)
COLD CREEK CONSTRUCTION, LTD (0.57)
DUSTIN ALLEN, INC. (0.42)
MARCOM"S MOWING SERVICE, LLC (1.03)
TRP CONSTRUCTION GROUP, LLC (1.21)
WOLFE CONSTRUCTION GROUP, INCORPORATED (1.29)
J & M CONTRACTING, COMPANY (15.23)
J. H. ODEN CONTRACTING COMPANY (0.32)
Contract #10223007
Totals11181793.39137168.142197684.1619.6

CountyCOLLIN
HighwayFM 2551
FromFM 2514
ToFM 2170
CSJ2056-01-042
Proj IDC 2056-1-42
Work TypeWIDEN NON-FREEWAY
 
3.40245570230.012302254.465.0
CountyCOLLIN
HighwayFM 2551
FromFM 2514
ToFM 2170
CSJ2056-01-043
Proj IDROW 2056-1-43
Work TypeRIGHT OF WAY
 
3.402763711.500.000.0
Work Order07-26-23
Work Began11-27-23
Work Completed
Time Computed11-27-23
Contract Working Days648
Addl Days Granted0
Working Days Charged14
Percent Time Used2
Contractor(s)
HARPER BROTHERS CONSTRUCTION LLC
SUBCONTRACTOR(S) FOR CCSJ: 2056-01-042
MARCOMS CONSTRUCTION LLC (0.11)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.41)
BARRICADES UNLIMITED (0.33)
ACT SAW CUTTING & REMOVAL (0.30)
MICA CORPORATION (2.56)
REYNOLDS ASPHALT & CONSTRUCTION COMPANY (10.99)
TRAFFIC HIGHWAY MAINTENANCE, LLC (0.56)
BREDA COMPANY, INC. (0.91)
1 PRIORITY ENVIRONMENTAL SERVICES, LLC (0.09)
TEXAS AUGER BORING LLC (0.19)
FREIGHT OPERATION SERVICES, LLC, DBA FOS BROKERAGE SERVICES (1.67)
Contract #04233202
Totals46333941.516338.002302254.464.9

CountyCOLLIN
HighwayFM 2478
FromNORTH OF FM 1461
ToFM 455
CSJ2351-02-017
Proj IDSTP 2B23(110)HES
Work TypeSAFETY IMPROVEMENT PROJECTS
 
5.9489301659.255308488.9957.0
Work Order09-06-23
Work Began09-25-23
Work Completed
Time Computed09-25-23
Contract Working Days215
Addl Days Granted0
Working Days Charged84
Percent Time Used39
Contractor(s)
FOUTSCO PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 2351-02-017
WEST TEXAS ROCK RESOURCES, LLC (0.12)
IBCTX, LLC (0.66)
KING GEORGE TRAFFIC SOLUTIONS LLC (0.14)
MARCOMS CONSTRUCTION LLC (0.49)
LINEAR TRAFFIC MARKINGS LLC (1.13)
SOUTHERN CROSS CONTRACTORS, LLC (1.22)
LOLLAR CONSTRUCTION GROUP LLC (20.48)
USA SWPPP INSPECTIONS, INC.DBA USA EROSION (0.62)
Contract #08233013
Totals9301659.25913670.235308488.9957.0

page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7