Monthly Local Let Maintenance Report For Brownwood District As Of Apr 12, 2024 Page 6 Of 6

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMCCULLOCH
HighwayUS0377
FromMCCULLOCH COUNTY
ToMCCULLOCH COUNTY
CSJ6455-05-001
Proj IDSUP - 645505001
Work TypePICNIC AREA MAINTENANCE
 
0.010101473.0026864.0026.4
Work Order00-00-00
Work Began09-01-23
Work Completed
Time Computed09-01-23
Contract Working Days735
Addl Days Granted0
Working Days Charged213
Percent Time Used28
Contractor(s)
WORKQUEST
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6455-05-001
CENTRAL TEXAS MHMR CENTER (0.00)
Contract #08232331
Totals101473.003824.0026864.0026.4

CountyMILLS
HighwayUS0084
FromMILLS COUNTY MAINTENANCE OFFICE
To***
CSJ6458-63-001
Proj IDSUP - 645863001
Work TypeJANITORIAL MAINTENANCE
 
0.01028052.407013.1025.0
Work Order00-00-00
Work Began10-01-23
Work Completed
Time Computed12-31-28
Contract Working Days730
Addl Days Granted0
Working Days Charged183
Percent Time Used25
Contractor(s)
WORKQUEST
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6458-63-001
CENTRAL TEXAS MHMR CENTER (0.00)
Contract #10232330
Totals28052.401168.857013.1025.0

CountyBROWN
HighwayUS0377
FromBROWN COUNTY
To***
CSJ6459-82-001
Proj IDMMC - 645982001
Work TypeHOT-MIX COLD-LAID
 
0.010281800.0021258.997.5
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted0
Working Days Charged60
Percent Time Used33
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 6459-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12232302
Totals281800.0021258.9921258.997.5

CountySAN SABA
HighwayUS0190
FromSAN SABA COUNTY
ToSAN SABA COUNTY
CSJ6459-85-001
Proj IDSUP - 645985001
Work TypePICNIC AREA MAINTENANCE
 
0.010106505.0018990.0017.8
Work Order00-00-00
Work Began11-01-23
Work Completed
Time Computed12-31-28
Contract Working Days735
Addl Days Granted0
Working Days Charged152
Percent Time Used20
Contractor(s)
WORKQUEST
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6459-85-001
ALDERSGATE ENRICHMENT CENTER, INC. (0.00)
Contract #10232333
Totals106505.003933.0018990.0017.8

CountyEASTLAND
HighwaySH0112
FromEASTLAND AREA/MAINTENANCE OFFICE AND LAB
To***
CSJ6459-87-001
Proj IDSUP - 645987001
Work TypeJANITORIAL MAINTENANCE
 
0.01063199.364923.287.7
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed12-31-28
Contract Working Days735
Addl Days Granted0
Working Days Charged60
Percent Time Used8
Contractor(s)
WORKQUEST
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6459-87-001
CENTRAL TEXAS MHMR CENTER (0.00)
Contract #01242330
Totals63199.362461.644923.287.7

CountyLAMPASAS
HighwayUS0183
FromLAMPASAS TXDOT AND CENTER MEDIANS
To***
CSJ6464-85-001
Proj IDSUP - 646485001
Work TypeGROUNDS MAINTENANCE
 
0.01033802.400.000.0
Work Order00-00-00
Work Began03-01-24
Work Completed
Time Computed12-31-28
Contract Working Days735
Addl Days Granted0
Working Days Charged31
Percent Time Used4
Contractor(s)
WORKQUEST
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6464-85-001
CENTRAL TEXAS MHMR CENTER (0.00)
Contract #02242330
Totals33802.400.000.000.0

CountyBROWN
HighwayUS0377
FromBROWN COUNTY
ToBROWN COUNTY
CSJ6464-96-001
Proj IDMMC - 646496001
Work TypeHOT MIX
 
0.010217000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed12-31-28
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
VULCAN CONSTRUCTION MATERIALS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6464-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03242301
Totals217000.000.000.000.0

CountyMCCULLOCH
HighwayUS0377
FromMCCULLOCH COUNTY
ToMCCULLOCH COUNTY
CSJ6465-01-001
Proj IDMMC - 646501001
Work TypeHOT-MIX COLD-LAID
 
0.010280000.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6465-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03242302
Totals280000.000.000.000.0

CountyEASTLAND
HighwayIH0020
FromEASTLAND COUNTY
ToEASTLAND COUNTY
CSJ6465-02-001
Proj IDRMC - 646502001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010254147.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days65
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GREG SCRUGGS
SUBCONTRACTOR(S) FOR CCSJ: 6465-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03242303
Totals254147.700.000.000.0

CountyMCCULLOCH
HighwayUS0377
FromMCCULLOCH COUNTY
ToMCCULLOCH COUNTY
CSJ6465-03-001
Proj IDRMC - 646503001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010254610.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days70
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GREG SCRUGGS
SUBCONTRACTOR(S) FOR CCSJ: 6465-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03242304
Totals254610.000.000.000.0