Monthly Local Let Maintenance Report For Brownwood District As Of Apr 10, 2018 Page 2 Of 3

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLAMPASAS
HighwayUS0183
FromVARIOUS
To***
CSJ6297-50-001
Proj IDSUP - 629750001
Work TypeSTATE USE/LITTER/BOOTSTRAPS
 
0.00191193.2476541.11100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-01-15
Work Began12-01-15
Work Completed02-01-18
Time Computed12-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged793
Percent Time Used108
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6297-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11152331
Totals91193.240.0076541.11100.0

CountyEASTLAND
HighwaySH0112
FromEASTLAND AREA/MNT OFFICE
To***
CSJ6298-23-001
Proj IDSUP - 629823001
Work TypeSTATE USE JANITOR-JCI/CFLR
 
0.00155091.9246691.4484.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-01-16
Work Began02-01-16
Work Completed
Time Computed02-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged761
Percent Time Used104
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6298-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11152332
Totals55091.920.0046691.4484.7

CountyEASTLAND
HighwaySH0006
FromVARIOUS
To***
CSJ6301-28-001
Proj IDRMC - 630128001
Work TypeTREE TRIMMING, ETC.
 
0.001278780.00446690.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-30-17
Work Began12-01-16
Work Completed
Time Computed06-06-17
Contract Working Days100
Addl Days Granted100
Working Days Charged63
Percent Time Used31
Contractor(s)
DEKALB TREE SPECIALIST
SUBCONTRACTOR(S) FOR CCSJ: 6301-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162301
Totals278780.000.00446690.0099.9

CountyBROWN
HighwaySH0279
FromVARIOUS
To***
CSJ6301-29-001
Proj IDRMC - 630129001
Work TypeTREE TRIMMING, ETC.
 
0.001278780.00345308.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-06-16
Work Began09-07-16
Work Completed
Time Computed09-13-16
Contract Working Days100
Addl Days Granted0
Working Days Charged55
Percent Time Used55
Contractor(s)
DEKALB TREE SPECIALIST
SUBCONTRACTOR(S) FOR CCSJ: 6301-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162302
Totals278780.000.00345308.0099.9

CountyCOMANCHE
HighwayUS0067
FromVARIOUS
To***
CSJ6301-76-001
Proj IDRMC - 630176001
Work TypeROADSIDE MOWING (WILL-CALL) (AS NEEDED)
 
0.001354857.95411064.2499.9
Work Order06-21-16
Work Began06-23-16
Work Completed
Time Computed06-28-16
Contract Working Days85
Addl Days Granted0
Working Days Charged66
Percent Time Used77
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162301
Totals354857.950.00411064.2499.9

CountyEASTLAND
HighwayIH0020
FromVARIOUS
To***
CSJ6301-77-001
Proj IDRMC - 630177001
Work TypeROADSIDE MOWING (WILL-CALL)(AS NEEDED)
 
0.001331712.00537244.0099.9
Work Order07-05-16
Work Began07-12-16
Work Completed
Time Computed07-12-16
Contract Working Days90
Addl Days Granted0
Working Days Charged98
Percent Time Used108
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6301-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162302
Totals331712.000.00537244.0099.9

CountyMILLS
HighwayUS0084
FromVARIOUS
To***
CSJ6301-78-001
Proj IDRMC - 630178001
Work TypeROADSIDE MOWING (WILL-CALL)(AS NEEDED)
 
0.001314621.06245428.1178.0
Work Order07-12-16
Work Began07-13-16
Work Completed
Time Computed07-19-16
Contract Working Days76
Addl Days Granted0
Working Days Charged28
Percent Time Used36
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6301-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04162303
Totals314621.060.00245428.1178.0

CountyBROWN
HighwayUS0377
FromVARIOUS
To***
CSJ6304-51-001
Proj IDSUP - 630451001
Work TypeALDERSGATE/STATE USE/LITTER REMOVAL
 
0.001157255.90145310.2392.4
Work Order06-01-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged690
Percent Time Used94
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6304-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162330
Totals157255.909859.60145310.2392.4

CountyEASTLAND
HighwaySH0006
FromSH0006 AT LAKE CISCO
To***
CSJ6305-90-001
Proj IDEMC - 630590001
Work TypeBUILD 3 SPAN BRIDGE
 
0.0033343810.503598152.0099.9
Work Order08-08-16
Work Began08-08-16
Work Completed
Time Computed08-08-16
Contract Working Days185
Addl Days Granted0
Working Days Charged308
Percent Time Used166
Contractor(s)
FLATIRON CONSTRUCTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-90-001
BEAIRD DRILLING (7.68)
GRANBURY EXCAVATING, INC. (19.60)
N-LINE TRAFFIC MAINTENANCE, L.P. (0.49)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.82)
HJC FARMS, INC. (2.03)
LONE STAR PAVING COMPANY (5.45)
Contract #07162302
Totals3343810.5024500.003598152.0099.9

CountySAN SABA
HighwayUS0190
FromSAN SABA MAINTENANCE OFFICE
To***
CSJ6307-67-001
Proj IDSUP - 630767001
Work TypeSTATE USE JANITOR CEN TEX MHMR/CFLR
 
0.00121216.0012580.0059.2
Work Order08-01-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged608
Percent Time Used83
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6307-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07162330
Totals21216.00809.0012580.0059.2

CountySTEPHENS
HighwayUS0180
FromVARIOUS
To***
CSJ6312-32-001
Proj IDSUP - 631232001
Work TypeSTATE USE LITTER REMOVAL
 
0.001129291.3559058.9845.6
Work Order02-01-17
Work Began02-01-17
Work Completed
Time Computed02-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged424
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6312-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01172330
Totals129291.351273.2659058.9845.6

CountySAN SABA
HighwayUS0190
FromVARIOUS
To***
CSJ6315-56-001
Proj IDRMC - 631556001
Work TypeROADSIDE MOWING
 
0.001174960.9462481.1635.7
Work Order06-12-17
Work Began06-13-17
Work Completed
Time Computed06-19-17
Contract Working Days65
Addl Days Granted0
Working Days Charged21
Percent Time Used32
Contractor(s)
BUCKSHOT WELDING & FABRICATION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6315-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03172301
Totals174960.940.0062481.1635.7

CountyCOLEMAN
HighwayUS0067
FromVARIOUS
To***
CSJ6315-57-001
Proj IDSUP - 631557001
Work TypeSTATE USE LITTER-ALDERSGATE
 
0.00144712.9621231.4847.4
Work Order05-01-17
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days735
Addl Days Granted0
Working Days Charged335
Percent Time Used45
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04172330
Totals44712.960.0021231.4847.4

CountyCOMANCHE
HighwayUS0067
FromVARIOUS
To***
CSJ6315-58-001
Proj IDSUP - 631558001
Work TypeSTATE USE LITTER-ALDERSGATE
 
0.00189635.2044067.6049.1
Work Order04-20-17
Work Began04-20-17
Work Completed
Time Computed04-20-17
Contract Working Days735
Addl Days Granted0
Working Days Charged346
Percent Time Used47
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04172331
Totals89635.204617.0044067.6049.1

CountyEASTLAND
HighwayIH0020
FromVARIOUS
To***
CSJ6315-59-001
Proj IDSUP - 631559001
Work TypeSTATE USE LITTER-ALDERSGATE
 
0.001163320.3694442.8857.8
Work Order03-01-17
Work Began03-01-17
Work Completed
Time Computed03-01-17
Contract Working Days735
Addl Days Granted0
Working Days Charged396
Percent Time Used53
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172330
Totals163320.3616382.7094442.8857.8

CountyCOMANCHE
HighwaySH0016
FromCOMANCHE MAINTENANCE OFFICE
To***
CSJ6315-71-001
Proj IDSUP - 631571001
Work TypeSTATE USE JANITORIAL-CEN TEX MHMR/JCI
 
0.00132986.2415399.2846.6
Work Order03-01-17
Work Began03-01-17
Work Completed
Time Computed03-01-17
Contract Working Days730
Addl Days Granted0
Working Days Charged396
Percent Time Used54
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6315-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172331
Totals32986.241314.6115399.2846.6

CountyMCCULLOCH
HighwayUS0190
FromVARIOUS
To***
CSJ6318-39-001
Proj IDSUP - 631839001
Work TypeSTATE USE LITTER REMOVAL-ALDERSGATE
 
0.00127129.3213682.2950.4
Work Order06-01-17
Work Began06-01-17
Work Completed
Time Computed06-01-17
Contract Working Days735
Addl Days Granted0
Working Days Charged304
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05172330
Totals27129.327557.2713682.2950.4

CountySAN SABA
HighwayUS0190
FromVARIOUS
To***
CSJ6318-40-001
Proj IDSUP - 631840001
Work TypeSTATE USE LITTER REMOVAL-ALDERSGATE
 
0.00131575.167143.7922.6
Work Order11-06-17
Work Began06-01-17
Work Completed
Time Computed06-01-17
Contract Working Days735
Addl Days Granted0
Working Days Charged304
Percent Time Used41
Contractor(s)
TIBH INDUSTRIES, INC.
ALDERSGATE ENRICHMENT CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6318-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05172331
Totals31575.160.007143.7922.6

CountyCOLEMAN
HighwaySH0206
FromCOLEMAN MAINTENANCE OFFICE
To***
CSJ6319-33-001
Proj IDSUP - 631933001
Work TypeSU JANITORIAL-JCT/CEN TEX MHMR
 
0.00131159.2010387.2033.3
Work Order07-01-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days735
Addl Days Granted0
Working Days Charged274
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6319-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06172332
Totals31159.201263.3010387.2033.3

CountyMCCULLOCH
HighwayUS0377
FromMCCULLOCH COUNTY MAINTENANCE OFFICE
To***
CSJ6319-34-001
Proj IDSUP - 631934001
Work TypeSU JANITORIAL-JCI/CEN TEX MHMR
 
0.00119511.365541.7428.4
Work Order07-01-17
Work Began07-01-17
Work Completed
Time Computed07-01-17
Contract Working Days735
Addl Days Granted0
Working Days Charged274
Percent Time Used37
Contractor(s)
TIBH INDUSTRIES, INC.
CENTRAL TEXAS MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6319-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06172333
Totals19511.36564.405541.7428.4

page 1 | page 2 | page 3