Monthly State Let Maintenance Report For Waco District As Of Feb 14, 2019 Page 3 Of 3

Last Update: Friday, February 15, 2019
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMCLENNAN
HighwayUS0084
FromVAR ROADWAYS IN BELL, CORYELL, FALLS,
ToHAMILTON, HILL, LIMESTONE & MCLENNAN CO
CSJ6324-94-001
Proj IDRMC - 632494001
Work TypeMISCELLANEOUS CONCRETE REPAIRS
 
0.010648174.38457114.5770.5
Work Order04-24-18
Work Began05-14-18
Work Completed
Time Computed05-14-18
Contract Working Days67
Addl Days Granted107
Working Days Charged115
Percent Time Used66
Contractor(s)
DBI SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6324-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184005
Totals648174.3894620.43457114.5770.5

CountyMCLENNAN
HighwaySH0006
FromRDWYS IN BELL, BOSQUE, CORYELL, FALLS,
ToHILL, HAMILTON, LIMESTONE & MCLENNAN
CSJ6326-46-001
Proj IDRMC - 632646001
Work TypeDISTRICT WIDE PAVEMENT MARKINGS
 
0.0101217231.25243524.6020.0
Work Order12-18-18
Work Began01-02-19
Work Completed
Time Computed01-02-19
Contract Working Days365
Addl Days Granted0
Working Days Charged24
Percent Time Used6
Contractor(s)
PMI PAVEMENT MARKING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6326-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10184006
Totals1217231.25243524.60243524.6020.0

CountyBELL
HighwayUS0190
FromVAR RDWYS IN BELL,BOSQUE,FALLS, HILL,
ToCORYELL,HAMILTON,LIMESTONE & MCLENNAN
CSJ6330-19-001
Proj IDRMC - 633019001
Work TypeRAISED PAVEMENT MARKER MAINTENANCE
 
0.010298470.00197680.3966.2
Work Order09-14-18
Work Began10-01-18
Work Completed
Time Computed10-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged113
Percent Time Used30
Contractor(s)
BRYDL CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6330-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184205
Totals298470.0029148.88197680.3966.2

CountyBELL
HighwayUS0190
FromVAR RDWYS IN BELL, BOSQUE, CORYELL AND
ToHAMILTON COUNTIES
CSJ6330-70-001
Proj IDRMC - 633070001
Work TypeMBGF, CABLE BARRIER & BRIDGE RAIL
 
0.010604622.50210035.0034.7
Work Order09-06-18
Work Began09-10-18
Work Completed
Time Computed09-01-18
Contract Working Days365
Addl Days Granted0
Working Days Charged130
Percent Time Used35
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6330-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184006
Totals604622.5048040.00210035.0034.7

CountyBELL
HighwayUS0190
FromVARIOUS RDWYS IN BELL, BOSQUE, CORYELL
ToAND HAMILTON COUNTIES
CSJ6331-03-001
Proj IDRMC - 633103001
Work TypeCLEANING AND SWEEPING HIGHWAYS
 
0.010439827.71126395.4228.7
Work Order09-12-18
Work Began10-02-18
Work Completed
Time Computed10-01-18
Contract Working Days215
Addl Days Granted0
Working Days Charged24
Percent Time Used11
Contractor(s)
EXPERT MAINTENANCE & CONSTRUCTION SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6331-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07184007
Totals439827.7113298.80126395.4228.7

CountyHILL
HighwayFM1946
FromWACO DISTRICT-BELL,BOSQUE,CORYELL,FALLS,
ToHAMILTON,HILL,LIMESTONE & MCLENNAN
CSJ6331-63-001
Proj IDRMC - 633163001
Work TypeHOT APPLICATION CRACK SEAL
 
0.010425926.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-04-19
Work Began00-00-00
Work Completed
Time Computed02-19-19
Contract Working Days101
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
D & M CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6331-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184002
Totals425926.800.000.000.0

CountyBOSQUE
HighwaySH0022
FromVAR RDWYS IN BELL,BOSQUE,CORYELL, FALLS,
ToHAMILTON, HILL, LIMESTONE & MCLENNAN
CSJ6332-83-001
Proj IDRMC - 633283001
Work TypeFLAGGING & WORK ZONE TRAFFIC CONTROL
 
0.0101165160.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6332-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184221
Totals1165160.000.000.000.0

CountyHILL
HighwaySH0022
FromVARIOUS BRIDGES IN HILL, FALLS AND
ToLIMESTONE COUNTIES
CSJ6332-84-001
Proj IDBPM - 633284001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.010478750.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days121
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6332-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12184222
Totals478750.400.000.000.0

CountyHILL
HighwaySH0171
FromWACO DISTRICT - BELL, FALLS, HILL
ToLIMESTONE, AND MCLELLAN COUNTIES.
CSJ6333-46-001
Proj IDRMC - 633346001
Work TypeDRIFTWOOD & DEBRIS REMOVAL
 
0.010410990.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-06-19
Work Began00-00-00
Work Completed
Time Computed02-11-19
Contract Working Days117
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6333-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11184212
Totals410990.000.000.000.0

CountyMCLENNAN
HighwayFM2416
FromCORYELL, FALLS, HAMILTON,HILL,
ToLIMESTONE & MCLENNAN COUNTIES
CSJ6334-22-001
Proj IDRMC - 633422001
Work TypeSEAL COAT (DISTRICT WIDE)
 
0.0102011339.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRANNAN PAVING CO., LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6334-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11184213
Totals2011339.500.000.000.0

CountyMCLENNAN
HighwayUS0084
FromVARIOUS ROADWAYS IN BELL AND
ToMCLENNAN COUNTIES
CSJ6336-61-001
Proj IDRMC - 633661001
Work TypeSPALL & FULL DEPTH CONCRETE REPAIR
 
0.0101496038.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days237
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6336-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01194226
Totals1496038.000.000.000.0

CountyBELL
HighwaySH0317
FromVAR.LOCATIONS BELL,FALLS,LIMESTONE,HILL
ToBOSQUE,HAMLITON,CORYELL & MCLENNAN
CSJ6338-73-001
Proj IDRMC - 633873001
Work TypeDISTRICT WIDE PAVEMENT MARKINGS
 
0.0101169617.240.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-28-19
Work Began00-00-00
Work Completed
Time Computed01-28-19
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6338-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11184211
Totals1169617.240.000.000.0

page 1 | page 2 | page 3