Monthly State Let Maintenance Report For Waco District As Of Apr 10, 2018 Page 2 Of 3

Last Update: Friday, April 20, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyHAMILTON
HighwaySH0036
FromVARIOUS ROADWAYS IN
ToHAMILTON COUNTY
CSJ6298-30-001
Proj IDRMC - 629830001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.100907239.00691496.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-11-16
Work Began04-28-16
Work Completed10-27-16
Time Computed04-18-16
Contract Working Days36
Addl Days Granted0
Working Days Charged27
Percent Time Used75
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6298-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02164216
Totals907239.000.00691496.00100.0

CountyHILL
HighwayUS0077
FromVARIOUS ROADWAYS
ToIN HILL COUNTY
CSJ6298-31-001
Proj IDRMC - 629831001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.1001971700.001974937.8299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-27-16
Work Began11-01-16
Work Completed
Time Computed11-01-16
Contract Working Days70
Addl Days Granted0
Working Days Charged56
Percent Time Used80
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03164003
Totals1971700.000.001974937.8299.9

CountyLIMESTONE
HighwaySH0164
FromVARIOUS ROADWAYS IN
ToLIMESTONE COUNTY
CSJ6298-32-001
Proj IDRMC - 629832001
Work TypeBASE REPAIR PAVEMENT REPAIR
 
0.0101396943.051298561.73100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-09-16
Work Began09-12-16
Work Completed09-28-17
Time Computed09-12-16
Contract Working Days34
Addl Days Granted15
Working Days Charged39
Percent Time Used79
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6298-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03164004
Totals1396943.050.001298561.73100.0

CountyMCLENNAN
HighwaySH0006
FromVARIOUS ROADWAYS IN
ToMCLENNAN COUNTY
CSJ6298-33-001
Proj IDRMC - 629833001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.0101558756.001552098.30100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-28-16
Work Began10-04-16
Work Completed10-31-17
Time Computed10-04-16
Contract Working Days42
Addl Days Granted0
Working Days Charged42
Percent Time Used100
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6298-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04164222
Totals1558756.000.001552098.30100.0

CountyBELL
HighwayFM2184
FromVAR RDWYS IN BELL, BOSQUE, CORYELL, HILL
ToFALLS, HAMILTON, LIMESTONE & MCLENNAN
CSJ6303-06-001
Proj IDRMC - 630306001
Work TypeSEAL COAT (DISTRICT WIDE)
 
0.0102877967.282762625.65100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-18-17
Work Completed06-06-17
Time Computed03-01-17
Contract Working Days45
Addl Days Granted0
Working Days Charged21
Percent Time Used46
Contractor(s)
F. N. PLOCH CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6303-06-001
D.I.J. CONSTRUCTION, INC (13.83)
Contract #11164021
Totals2877967.280.002762625.65100.0

CountyBELL
HighwayUS0190
FromVARIOUS ROADWAYS IN BELL, CORYELL,
ToFALLS AND LIMESTONE COUNTIES
CSJ6304-35-001
Proj IDRMC - 630435001
Work TypePAVEMENT MARKINGS
 
0.010786813.83337289.8642.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-05-16
Work Began10-18-16
Work Completed
Time Computed10-10-16
Contract Working Days365
Addl Days Granted0
Working Days Charged365
Percent Time Used100
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6304-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08164007
Totals786813.830.00337289.8642.8

CountyMCLENNAN
HighwayUS0084
FromVARIOUS ROADWAYS IN MCLENNAN, FALLS,
ToHILL AND LIMESTONE COUNTIES
CSJ6312-44-001
Proj IDRMC - 631244001
Work TypeMBGF, CABLE BARRIERS & BRIDGE RAIL/REP/I
 
0.010772842.0085162.5011.0
Work Order01-11-18
Work Began01-11-18
Work Completed
Time Computed01-18-18
Contract Working Days365
Addl Days Granted0
Working Days Charged74
Percent Time Used20
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6312-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174202
Totals772842.0047235.0085162.5011.0

CountyBELL
HighwayUS0190
FromVARIOUS ROADWAYS IN BELL,BOSQUE,CORYELL,
To& HAMILTON COUNTIES
CSJ6312-45-001
Proj IDRMC - 631245001
Work TypeMBGF,CABLE BARRIER & BRIDGE RAIL REP/INT
 
0.100469792.50550639.0099.9
Work Order04-28-17
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged329
Percent Time Used90
Contractor(s)
T & L CLEANING SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6312-45-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01174206
Totals469792.5059845.00550639.0099.9

CountyMCLENNAN
HighwaySH0006
FromVARIOUS ROADWAYS IN BELL, CORYELL, FALLS
ToHAMILTON, HILL, LIMESTONE & MCLENNAN
CSJ6312-46-001
Proj IDBPM - 631246001
Work TypeBRIDGE PREVENTIVE MAINTENANCE
 
0.010322992.60445363.43100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-13-17
Work Began06-20-17
Work Completed11-29-17
Time Computed06-20-17
Contract Working Days63
Addl Days Granted0
Working Days Charged44
Percent Time Used69
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6312-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04174008
Totals322992.600.00445363.43100.0

CountyBELL
HighwayUS0190
FromVARIOUS LOCATIONS IN BELL,BOSQUE,CORYELL
ToHAMILTON,HILL,LIMESTONE & MCLENNAN CO.
CSJ6314-14-001
Proj IDRMC - 631414001
Work TypeDISTRICT WIDE MAINTENANCE OF SIGNAL SYS.
 
0.010371098.6787253.8323.5
Work Order00-00-00
Work Began12-18-17
Work Completed
Time Computed09-12-17
Contract Working Days365
Addl Days Granted0
Working Days Charged195
Percent Time Used53
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174201
Totals371098.679758.8487253.8323.5

CountyMCLENNAN
HighwayUS0084
FromVAR RDWYS IN BELL,BOSQUE,FALLS, HILL,
ToCORYELL, HAMILTON, LIMESTONE, MCLENNAN
CSJ6314-15-001
Proj IDRMC - 631415001
Work TypeDISTRICT WIDE ILLUMINATION SYSTEMS
 
0.010287880.1068461.4423.7
Work Order00-00-00
Work Began11-15-17
Work Completed
Time Computed10-10-17
Contract Working Days365
Addl Days Granted0
Working Days Charged259
Percent Time Used70
Contractor(s)
AMERICAN LIGHTING AND SIGNALIZATION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6314-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05174002
Totals287880.105843.6068461.4423.7

CountyCORYELL
HighwaySH0036
FromVARIOUS AREAS ON SH 36
ToIN CORYELL COUNTY
CSJ6315-72-001
Proj IDRMC - 631572001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.010305221.20373185.9199.9
Work Order12-03-17
Work Began12-28-17
Work Completed
Time Computed12-11-17
Contract Working Days30
Addl Days Granted0
Working Days Charged20
Percent Time Used66
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6315-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174202
Totals305221.20114242.26373185.9199.9

CountyHAMILTON
HighwaySH0036
FromVARIOUS ROADWAYS IN HAMILTON COUNTY:
ToSH 36, US 281N, AND FM 932
CSJ6315-73-001
Proj IDRMC - 631573001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.010510941.81545602.1599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-16-17
Work Completed
Time Computed10-02-17
Contract Working Days40
Addl Days Granted0
Working Days Charged49
Percent Time Used122
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6315-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174001
Totals510941.810.00545602.1599.9

CountyHILL
HighwayFM0933
FromVARIOUS ROADWAYS IN HILL COUNTY: FM 933,
ToUS 77,FM 1243,FM 1242,FM 1946,FM 934
CSJ6315-74-001
Proj IDRMC - 631574001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.010995053.00442250.8944.4
Work Order02-01-18
Work Began02-08-18
Work Completed
Time Computed02-05-18
Contract Working Days45
Addl Days Granted0
Working Days Charged23
Percent Time Used51
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6315-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05174003
Totals995053.00361008.51442250.8944.4

CountyLIMESTONE
HighwaySH0164
FromVARIOUS ROADWAYS IN
ToLIMESTONE COUNTY
CSJ6315-77-001
Proj IDRMC - 631577001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.010209620.00207784.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-10-17
Work Began12-07-17
Work Completed12-18-17
Time Computed11-06-17
Contract Working Days40
Addl Days Granted0
Working Days Charged26
Percent Time Used65
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6315-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05174203
Totals209620.000.00207784.00100.0

CountyBELL
HighwayUS0190
FromVARIOUS ROADWAYS IN BELL COUNTY: US 190,
ToBU 190 F, SH 36 AND OTHERS AS DETERMINED
CSJ6315-78-001
Proj IDRMC - 631578001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.010940401.15800414.1585.1
Work Order09-28-17
Work Began10-08-17
Work Completed
Time Computed10-02-17
Contract Working Days45
Addl Days Granted0
Working Days Charged13
Percent Time Used28
Contractor(s)
OLDCASTLE MATERIALS TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6315-78-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06174002
Totals940401.150.00800414.1585.1

CountyMCLENNAN
HighwaySH0006
FromVARIOUS ROADWAYS IN
ToMCLENNAN COUNTY
CSJ6315-79-001
Proj IDRMC - 631579001
Work TypeBASE FAILURE PAVEMENT REPAIR
 
0.0101145761.00166947.65100.0
Work Order10-10-17
Work Began10-31-17
Work Completed03-31-18
Time Computed10-30-17
Contract Working Days50
Addl Days Granted14
Working Days Charged44
Percent Time Used68
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6315-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05174204
Totals1145761.0055659.00166947.65100.0

CountyMCLENNAN
HighwaySH0006
FromVARIOUS ROADWAYS IN BOSQUE,
ToHAMILTON, HILL AND MCLENNAN COUNTIES
CSJ6316-07-001
Proj IDRMC - 631607001
Work TypeDISTRICT WIDE PAVEMENT MARKINGS
 
0.010748474.30794560.4599.9
Work Order10-10-17
Work Began11-01-17
Work Completed
Time Computed11-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged145
Percent Time Used39
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6316-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07174014
Totals748474.3010199.88794560.4599.9

CountyBELL
HighwaySH0317
FromVARIOUS LOCATIONS IN BELL, CORYELL,
ToFALLS & LIMESTONE COUNTIES
CSJ6316-08-001
Proj IDRMC - 631608001
Work TypeDISTRICT WIDE PAVEMENT MARKINGS
 
0.010728653.50295650.5640.5
Work Order00-00-00
Work Began10-16-17
Work Completed
Time Computed10-16-17
Contract Working Days365
Addl Days Granted0
Working Days Charged161
Percent Time Used44
Contractor(s)
BATTERSON, LLP
SUBCONTRACTOR(S) FOR CCSJ: 6316-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08174013
Totals728653.5092589.20295650.5640.5

CountyMCLENNAN
HighwayFM3051
FromFM 3051 AND KEYS CREEK
ToAMD AVON
CSJ6316-23-001
Proj IDRMC - 631623001
Work TypeADD LEFT TURN LANE
 
0.010342755.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6316-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04184017
Totals342755.300.000.000.0

page 1 | page 2 | page 3