Monthly State Let Construction Report For Lufkin District As Of Jun 08, 2018 Page 3 Of 3

Last Update: Tuesday, June 12, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySHELBY
HighwayCR
FromCR 4059 AT POOR JOE CREEK
To.
CSJ0911-39-038
Proj IDBR 1602(393)
Work TypeBRIDGE REPLACEMENT
 
0.119619833.68549061.7988.5
Work Order09-05-17
Work Began10-13-17
Work Completed
Time Computed10-05-17
Contract Working Days144
Addl Days Granted0
Working Days Charged103
Percent Time Used71
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-038
HODGES AND SON CONSTRUCTION COMPANY, INC. (3.77)
AWP, INC. DBA AREA WIDE PROTECTIVE (1.71)
AMERICAN REMEDIATION OPTIONS, INC. (8.17)
Contract #07173220
Totals619833.68102357.04549061.7988.5

CountySHELBY
HighwayCR
FromCR 4789 AT TRIB OF BLACKWATER CREEK
To.
CSJ0911-39-050
Proj IDBR 1602(396)
Work TypeBRIDGE REPLACEMENT
 
0.104671325.95328182.7948.8
Work Order06-14-17
Work Began09-12-17
Work Completed
Time Computed09-12-17
Contract Working Days127
Addl Days Granted0
Working Days Charged47
Percent Time Used37
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0911-39-050
AMERICAN REMEDIATION OPTIONS, INC. (9.48)
FREDONIA CONSTRUCTION SERVICES (1.48)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.27)
AREA WIDE PROTECTIVE, INC. (0.91)
Contract #05173010
Totals671325.955571.93328182.7948.8

CountyNACOGDOCHES
HighwayFM 1087
FromUS 259
ToFM 95
CSJ0926-05-008
Proj IDSTP 2017(643)HES
Work TypeSFT FIXED OBJ
 
10.916775621.06877581.0199.9
Work Order03-16-17
Work Began05-18-17
Work Completed
Time Computed04-17-17
Contract Working Days137
Addl Days Granted0
Working Days Charged132
Percent Time Used96
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0926-05-008
COLD CREEK CONSTRUCTION, LTD (1.51)
SOUTHWEST ENVIRONMENT SERVICES LLC (2.03)
LONESTAR TRAFFIC SAFETY, LLC (0.97)
Contract #02173004
Totals775621.060.00877581.0199.9

CountyPOLK ETC
HighwayFM 350 ETC
From2.625 MI N OF FM 3152
ToUS 190
CSJ0928-02-020
Proj IDSTP 2018(813)HES
Work TypeIMPROVE GUARDRAIL TO DESIGN STAND
 
49.5761889217.800.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days388
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0928-02-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183243
Totals1889217.800.000.000.0

CountyHOUSTON
HighwayFM 227
From0.5 MI E OF CR 1685
ToSH 21
CSJ0937-02-033
Proj IDSTP 2017(644)
Work TypeRECONSTRUCT AND WIDEN PAVEMENT
 
29.8883134729.032975219.4694.9
Work Order03-15-17
Work Began04-24-17
Work Completed
Time Computed04-24-17
Contract Working Days166
Addl Days Granted45
Working Days Charged135
Percent Time Used63
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0937-02-033
A R BROTHERS CONSTRUCTION SERVICES, INC. (19.28)
INTERSTATE BARRICADES & MARKINGS, INC. (4.89)
COLD CREEK CONSTRUCTION, LTD (7.58)
PANOLA SIGN & BARRICADE, INC. (0.70)
AMERICAN REMEDIATION OPTIONS, INC. (4.69)
USA LANDSCAPE SERVICES EAST TEAST (0.19)
ODUM SERVICES, L.P. (4.57)
Contract #02173046
Totals3134729.0370703.402975219.4694.9

CountyHOUSTON
HighwayFM 227
FromSH 21
ToSH 7
CSJ0937-03-016
Proj IDSTP 1702(636)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
26.6361576406.001065381.4167.5
Work Order09-14-17
Work Began10-10-17
Work Completed
Time Computed10-10-17
Contract Working Days223
Addl Days Granted0
Working Days Charged138
Percent Time Used61
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0937-03-016
ODUM SERVICES, L.P. (7.51)
Contract #08173016
Totals1576406.0048086.451065381.4167.5

CountySAN AUGUSTINE
HighwayFM 705
FromSH 147
To2.49 MI S OF FM 83
CSJ1079-01-031
Proj IDSTP 2015(420)HRR
Work TypeSAFETY TREAT FIXED OBJECTS
 
22.3791266570.981244103.1098.2
Work Order11-02-15
Work Began12-09-15
Work Completed
Time Computed12-02-15
Contract Working Days336
Addl Days Granted0
Working Days Charged325
Percent Time Used96
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1079-01-031
DUSTIN ALLEN, INC. (12.83)
PANOLA SIGN & BARRICADE, INC. (1.57)
Contract #09153226
Totals1266570.980.001244103.1098.2

CountyANGELINA
HighwayFM 841
FromAT BILOXI CREEK
To.
CSJ1157-01-014
Proj IDBR 2018(614)
Work TypeBRIDGE REPLACEMENT
 
0.2071023277.6426156.642.5
Work Order04-13-18
Work Began05-29-18
Work Completed
Time Computed05-14-18
Contract Working Days64
Addl Days Granted0
Working Days Charged3
Percent Time Used4
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 1157-01-014
PANOLA SIGN & BARRICADE, INC. (0.64)
TEXOP CONSTRUCTION (0.62)
HODGES AND SON CONSTRUCTION COMPANY, INC. (9.41)
PENHALL COMPANY (0.37)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.88)
STRIPING TECHNOLOGY, L.P. (0.77)
DUSTIN ALLEN, INC. (4.19)
ISAACS CONSTRUCTION SERVICES, LLC. (1.73)
BOWMAN ENGINEERING & CONSULTING, INC. (0.39)
Contract #03183010
Totals1023277.6426156.6426156.642.5

CountyNACOGDOCHES
HighwayFM 1638
FromFM 698
ToUS 59/SL 224
CSJ1407-02-023
Proj IDSTP 2018(814)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
4.2132498804.120.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-05-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days123
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1407-02-023
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183034
Totals2498804.120.000.000.0

CountySAN AUGUSTINE
HighwayFM 711
FromSHELBY COUNTY LINE
ToUS 96
CSJ1680-01-016
Proj IDSTP 2018(428)
Work TypeRECONSTRUCT AND WIDEN PAVEMENT
 
11.3315195793.421615753.2231.0
Work Order02-14-18
Work Began03-12-18
Work Completed
Time Computed03-12-18
Contract Working Days175
Addl Days Granted0
Working Days Charged53
Percent Time Used30
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1680-01-016
AMERICAN REMEDIATION OPTIONS, INC. (4.16)
PANOLA SIGN & BARRICADE, INC. (0.64)
STRIPING TECHNOLOGY, L.P. (1.94)
FREDONIA CONSTRUCTION SERVICES (0.19)
DREWERY BROS TREE SERVICE, INC. (0.34)
Contract #01183027
Totals5195793.42837761.891615753.2231.0

CountySAN JACINTO
HighwayFM 1127
FromUS 59
ToEND OF PAVEMENT
CSJ1681-01-012
Proj IDSTP 2017(500)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
13.9661585479.801392669.6788.2
Work Order02-15-17
Work Began03-15-17
Work Completed
Time Computed03-15-17
Contract Working Days153
Addl Days Granted0
Working Days Charged162
Percent Time Used105
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 1681-01-012
ODUM SERVICES, L.P. (2.89)
PIPE WHOLESALERS OF TEXAS, INC. (8.80)
Contract #01173234
Totals1585479.8015821.141392669.6788.2

CountyNACOGDOCHES
HighwayFM 1878
FromAT LA NANA CREEK
To.
CSJ1810-01-032
Proj IDBR 2017(829)
Work TypeBRIDGE REPLACEMENT
 
0.1171774829.452019541.2099.9
Work Order04-24-17
Work Began05-25-17
Work Completed
Time Computed05-24-17
Contract Working Days115
Addl Days Granted33
Working Days Charged158
Percent Time Used106
Contractor(s)
DREWERY CONSTRUCTION COMPANY, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 1810-01-032
PANOLA SIGN & BARRICADE, INC. (2.73)
TEX OP CONSTRUCTION, LP (0.58)
AMERICAN REMEDIATION OPTIONS, INC. (2.01)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.38)
STRIPING TECHNOLOGY, L.P. (0.52)
BOWMAN ENGINEERING & CONSULTING, INC (0.21)
FREDONIA CONSTRUCTION SERVICES (0.56)
Contract #03173037
Totals1774829.45935.162019541.2099.9

CountyTRINITY
HighwayFM 2262
FromFM 2501
ToSH 94
CSJ2387-01-017
Proj IDSTP 2017(647)
Work TypeRECONSTRUCT AND WIDEN PAVEMENT
 
14.1664311589.972461535.7557.0
Work Order11-10-17
Work Began01-08-18
Work Completed
Time Computed12-11-17
Contract Working Days129
Addl Days Granted0
Working Days Charged94
Percent Time Used72
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2387-01-017
A R BROTHERS CONSTRUCTION SERVICES, INC. (3.40)
PANOLA SIGN & BARRICADE, INC. (0.68)
STRIPING TECHNOLOGY, L.P. (2.23)
AMERICAN REMEDIATION OPTIONS, INC. (1.15)
Contract #10173216
Totals4311589.97474714.422461535.7557.0

CountyHOUSTON
HighwayFM 2967
FromFM 132
ToSH 21
CSJ3034-01-005
Proj IDC 3034-1-5
Work TypeRECONSTRUCT AND WIDEN PAVEMENT
 
2.8001499731.080.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days40
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 3034-01-005
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06183029
Totals1499731.080.000.000.0

page 1 | page 2 | page 3