Monthly State Let Construction Report For Lufkin District As Of Aug 16, 2018 Page 2 Of 3

Last Update: Thursday, August 16, 2018
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySAN JACINTO
HighwayUS 59
FromJUST S OF UPRR IN SHEPHERD
ToJUST N OF FM 2914
CSJ0177-02-089
Proj IDSTP 2013(916)
Work TypeADD SB FRTG RD & RECONST MAIN LANES
 
1.6428948536.8511114165.7499.9
Work Order05-14-14
Work Began08-15-14
Work Completed
Time Computed05-30-14
Contract Working Days230
Addl Days Granted189
Working Days Charged409
Percent Time Used97
Contractor(s)
TEXAS STERLING CONSTRUCTION CO.
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-089
FLORIDA TRAFFIC CONTROL DEVICES, INC. (0.88)
DOUBLE OAK CONSTRUCTION, INC. (0.67)
CRABTREE BARRICADE SYSTEMS, INC. (0.91)
SMITH & COMPANY (20.62)
WILLOW CITY SIGN & RAIL, INC. (0.59)
WIMS ENVIRONMENTAL CONSTRUCTION, LTD. (2.33)
BREDA COMPANY, INC. (0.92)
CPAVE, INC. (1.78)
ROY LEE WALKER (0.13)
THOMAS TRACTOR WORKS, INC. (0.16)
NORWEST SERVICES, LLC (0.06)
SOUTHERN CRUSHED CONCRETE LLC (0.86)
SOUTHEAST GRINDING & GROOVING, LLC (0.37)
HOUSTON SAWING & DRILLING (0.03)
DUSTROL, INC. (0.22)
TEXOP CONSTRUCTION (0.23)
WEST TX RUMBLE STRIP (0.09)
A-1 EROSION CONTROL, LLC (0.01)
ROSALES TRUCKING (1.13)
RAY"S THREADING AND FAB SHOP (0.00)
Contract #02143221
Totals8948536.854587.5811114165.7499.9

CountySAN JACINTO
HighwayUS 59
From0.50 MI S OF FM 2914
ToLIBERTY COUNTY LINE
CSJ0177-02-091
Proj IDNH 2016(734)
Work TypeHMA LEVEL-UP AND PFC SURFACE
 
16.4612971066.403064961.5399.9
Work Order04-19-16
Work Began05-23-16
Work Completed
Time Computed05-23-16
Contract Working Days94
Addl Days Granted36
Working Days Charged103
Percent Time Used79
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0177-02-091
STRIPING TECHNOLOGY, L.P. (1.46)
INTERSTATE BARRICADES & MARKINGS, INC. (0.60)
COWBELL TRAFFIC SERVICES, INC. (0.39)
CLARK CONSTRUCTION OF TEXAS, INC. (9.33)
AMERICAN REMEDIATION OPTIONS, INC. (6.84)
DUSTROL, INC. (1.05)
NLG CONSTRUCTION, INC. (0.13)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.03)
WEST TX RUMBLE STRIP (0.01)
HIGHWAY DATA SERVICES (0.04)
Contract #02163033
Totals2971066.400.003064961.5399.9

CountyANGELINA
HighwayUS 69
From0.24 MI NORTH OF FM 841
To1.235 MI S OF FM 1669
CSJ0200-01-083
Proj IDNH 2016(424)
Work TypeRESURFACE WITH THIN OVERLAY MIXTURE
 
6.5871576982.231487701.1694.3
Work Order01-10-18
Work Began04-30-18
Work Completed
Time Computed04-30-18
Contract Working Days37
Addl Days Granted1
Working Days Charged34
Percent Time Used89
Contractor(s)
MOORE BROTHERS CONSTRUCTION COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0200-01-083
AWP, INC. DBA AREA WIDE PROTECTIVE (0.42)
TRP CONSTRUCTION GROUP, LLC (5.46)
NLG CONSTRUCTION, INC. (0.95)
BRYDL CONTRACTING, INC. (0.55)
Contract #12173219
Totals1576982.2315961.981487701.1694.3

CountyANGELINA
HighwayUS 69
FromAT FM 326
To.
CSJ0200-01-089
Proj IDSTP 2018(520)HES
Work TypeINSTALL TRAFFIC SIGNAL
 
0.200164664.8314567.118.8
Work Order03-12-18
Work Began07-23-18
Work Completed
Time Computed06-11-18
Contract Working Days32
Addl Days Granted0
Working Days Charged2
Percent Time Used6
Contractor(s)
THIRD COAST SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 0200-01-089
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02183212
Totals164664.8314567.1114567.118.8

CountyANGELINA
HighwayUS 69
FromHUNTINGTON
ToFM 844
CSJ0200-02-031
Proj IDNH 2013(513)
Work TypeGR STRS BASE & SURF
 
2.1039969131.136502941.7465.2
Work Order07-14-17
Work Began08-17-17
Work Completed
Time Computed08-14-17
Contract Working Days310
Addl Days Granted3
Working Days Charged170
Percent Time Used54
Contractor(s)
PINTO CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0200-02-031
STRIPING TECHNOLOGY, L.P. (1.60)
A R BROTHERS CONSTRUCTION SERVICES, INC. (11.45)
AMERICAN REMEDIATION OPTIONS, INC. (1.33)
MOORE BROTHERS CONSTRUCTION COMPANY (31.91)
TEXAS ALTERNATIVE GRASSER, INC. (0.86)
PANOLA SIGN & BARRICADE, INC. (0.33)
DUSTROL, INC. (1.07)
STRIPING SYSTEMS, INC. (0.01)
AWP, INC. DBA AREA WIDE PROTECTIVE (0.09)
Contract #06173006
Totals9969131.13788255.506502941.7465.2

CountyANGELINA
HighwayUS 69
FromFM 844
ToZAVALLA
CSJ0200-02-039
Proj IDNH 2018(811)
Work TypeGR STRS BASE & SURF
 
11.05271614966.8211096.000.0
Work Order06-14-18
Work Began07-24-18
Work Completed
Time Computed07-16-18
Contract Working Days571
Addl Days Granted0
Working Days Charged11
Percent Time Used1
Contractor(s)
JOHNSON BROS. CORPORATION, A SOUTHLAND COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0200-02-039
AMERICAN REMEDIATION OPTIONS, INC. (0.70)
BOWMAN ENGINEERING & CONSULTING, INC. (0.27)
JB PINNACLE GROUP, LLC (1.23)
SOUTH TEXAS PAINTING COMPANY (0.07)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (2.77)
ANTIGO CONSTRUCTION, INC. (0.02)
ATS DRILLING, INC. (2.34)
STRIPING TECHNOLOGY, L.P. (0.71)
BUYERS BARRICADES HOUSTON, LLC. (0.01)
OVEMAN TRUCKING, LLC (0.18)
Contract #05183206
Totals71614966.8211096.0011096.000.0

CountyANGELINA
HighwayUS 69
FromFM 844
ToZAVALLA
CSJ0200-02-042
Proj IDNH 1702(519)
Work TypeCLEARING AND GRUBBING
 
10.835890456.22819705.6893.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-23-17
Work Began10-09-17
Work Completed
Time Computed09-25-17
Contract Working Days109
Addl Days Granted0
Working Days Charged128
Percent Time Used117
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 0200-02-042
HIGHWAY TRAFFIC CONTROL & SERVICES, LLC (1.06)
LONG LEGACY ENTERPRISES, LLC (8.75)
Contract #07173216
Totals890456.220.00819705.6893.3

CountySAN JACINTO
HighwayUS 190
FromWALKER COUNTY LINE
ToPOLK COUNTY LINE
CSJ0213-02-043
Proj IDSTP 1602(080)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
14.0372543073.002249894.6088.4
Work Order06-27-16
Work Began07-26-16
Work Completed
Time Computed07-26-16
Contract Working Days246
Addl Days Granted0
Working Days Charged241
Percent Time Used97
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 0213-02-043
ODUM SERVICES, L.P. (9.53)
B-N-T SERVICES, LLC (12.07)
Contract #05163008
Totals2543073.0015439.102249894.6088.4

CountyTRINITY
HighwayUS 287
FromSH 94
ToHARRISON AVE IN GROVETON
CSJ0319-01-064
Proj IDSTP 2017(827)
Work TypeRECONSTRUCT EXISTING PAVEMENT
 
4.7001947390.021962842.3699.9
Work Order04-19-17
Work Began05-31-17
Work Completed
Time Computed05-22-17
Contract Working Days80
Addl Days Granted0
Working Days Charged75
Percent Time Used93
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0319-01-064
A R BROTHERS CONSTRUCTION SERVICES, INC. (9.98)
(USE 26352)AWP, INC. (1.02)
STRIPE-A-ZONE, INC. (1.05)
WEST TEXAS RUMBLE STRIP (0.29)
NIXON ENGINEERING, L.L.C. (0.07)
HOUSTON TRUCKING & PAVING CO. (0.84)
Contract #03173009
Totals1947390.020.001962842.3699.9

CountyNACOGDOCHES
HighwaySH 103
FromANGELINA COUNTY LINE
ToSAN AUGUSTINE COUNTY LINE
CSJ0336-06-028
Proj IDSTP 2018(156)HES
Work TypeIMPROVE GUARDRAIL TO DES STANDARDS
 
20.681597891.99714008.0099.9
Work Order11-15-17
Work Began02-05-18
Work Completed
Time Computed12-18-17
Contract Working Days74
Addl Days Granted19
Working Days Charged90
Percent Time Used96
Contractor(s)
3LW CIVIL LLC
SUBCONTRACTOR(S) FOR CCSJ: 0336-06-028
AREA WIDE PROTECTIVE, INC. (1.84)
Contract #10173013
Totals597891.9929953.25714008.0099.9

CountyTRINITY
HighwayUS 287
FromHOUSTON COUNTY LINE
ToSH 94
CSJ0340-02-025
Proj IDSTP 1602(082)HES
Work TypeSAFETY TREAT FIXED OBJECTS
 
22.2511687891.221638574.6997.0
Work Order07-11-16
Work Began09-26-16
Work Completed
Time Computed08-10-16
Contract Working Days178
Addl Days Granted1
Working Days Charged172
Percent Time Used96
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0340-02-025
N-LINE TRAFFIC MAINTENANCE, L.P. (0.84)
DUSTIN ALLEN, INC. (6.67)
COLD CREEK CONSTRUCTION, LTD (7.93)
USA LANDSCAPE SERVICES EAST TEAST (1.94)
Contract #05163028
Totals1687891.228682.001638574.6997.0

CountySAN JACINTO
HighwayFM 224
FromSH 156 (N)
ToSH 156 (S)
CSJ0403-02-019
Proj IDSTP 1802(329)HES
Work TypeIMPROVE GUARDRAIL TO DES STANDARDS
 
16.594516228.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-15-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days206
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0403-02-019
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07183244
Totals516228.100.000.000.0

CountyPOLK
HighwayFM 356
From1.12 MI N OF US 190
ToUS 190
CSJ0475-11-031
Proj IDSTP 1602(273)
Work TypeGR,STR,CURB,GUTTER,BASE,SURF
 
1.0797653712.007577182.3699.0
Work Order09-15-16
Work Began11-14-16
Work Completed
Time Computed10-17-16
Contract Working Days162
Addl Days Granted62
Working Days Charged228
Percent Time Used101
Contractor(s)
SMITH & COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 0475-11-031
CEN TEX HYDROSEED, INC. (1.83)
J & M CONTRACTING COMPANY (42.30)
ROADSAFE TRAFFIC SYSTEMS, INC. (0.62)
WATERS CONSTRUCTION CO., INC. (1.41)
WILLOW CITY SIGN & RAIL, INC. (1.53)
THIRD COAST SERVICES LLC (1.23)
TEXAS LAND CLEARING SERVICE (0.97)
TEXOP CONSTRUCTION (0.93)
Contract #07163039
Totals7653712.000.007577182.3699.0

CountyNACOGDOCHES
HighwayFM 95
FromAT TERRAPIN CREEK
To.
CSJ0706-04-019
Proj IDBR 2018(426)
Work TypeBRIDGE REPLACEMENT
 
0.2321145849.40786699.6068.6
Work Order02-14-18
Work Began03-19-18
Work Completed
Time Computed03-19-18
Contract Working Days141
Addl Days Granted0
Working Days Charged89
Percent Time Used63
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0706-04-019
AMERICAN REMEDIATION OPTIONS, INC. (5.35)
DUSTROL, INC. (0.67)
FLEX SUPPLY, LLC (0.63)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.85)
STRIPING TECHNOLOGY, L.P. (2.63)
BOWMAN ENGINEERING & CONSULTING, INC (0.22)
Contract #01183218
Totals1145849.40115072.25786699.6068.6

CountyNACOGDOCHES
HighwayFM 226
FromSH 21
ToSH 103
CSJ0893-01-034
Proj IDSTP 2018(812)HES
Work TypeIMPROVE GUARDRAIL AND SAFETY TREAT
 
23.0201084003.29261254.3924.1
Work Order06-11-18
Work Began07-03-18
Work Completed
Time Computed07-03-18
Contract Working Days208
Addl Days Granted0
Working Days Charged19
Percent Time Used9
Contractor(s)
A R BROTHERS CONSTRUCTION SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0893-01-034
DUSTIN ALLEN, INC. (13.65)
J. H. ODEN CONTRACTING COMPANY (4.97)
PANOLA SIGN & BARRICADE, INC. (1.48)
Contract #05183237
Totals1084003.29261254.39261254.3924.1

CountyANGELINA
HighwayVA
FromVARIOUS LOCATIONS
To.
CSJ0911-00-075
Proj IDSTP 2018(936)
Work TypeCONSTRUCT CURB RAMPS
 
4.5672105750.300.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-19-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days250
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-00-075
CLASSIC TEJAS CONSTRUCTION, INC. (2.44)
Contract #06183209
Totals2105750.300.000.000.0

CountyPOLK
HighwayCR
FromHOLLY-GROVE OVER MENARD CREEK
To.
CSJ0911-04-046
Proj IDBR 2008(917)
Work TypeREPLACE BRIDGE AND APPROACHES
 
0.068480182.55121963.2525.3
Work Order05-14-18
Work Began07-02-18
Work Completed
Time Computed07-02-18
Contract Working Days59
Addl Days Granted0
Working Days Charged20
Percent Time Used33
Contractor(s)
STATELINE CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0911-04-046
HODGES AND SON CONSTRUCTION COMPANY, INC. (28.38)
SOUTHWEST ENVIRONMENT SERIVES, LLC (0.65)
DUSTIN ALLEN, INC. (4.84)
PENHALL COMPANY (0.77)
PANOLA SIGN & BARRICADE, INC. (1.23)
BOWMAN ENGINEERING & CONSULTING, INC. (0.89)
Contract #04183029
Totals480182.55121963.25121963.2525.3

CountySAN JACINTO
HighwayVA
FromVARIOUS LOCATIONS
ToWITHIN THE CITY OF COLDSPRING
CSJ0911-07-038
Proj IDSTP 2017(251)
Work TypeCONSTRUCT CURB RAMPS
 
0.100646827.00623015.2796.3
Work Order01-10-17
Work Began02-09-17
Work Completed
Time Computed02-09-17
Contract Working Days116
Addl Days Granted11
Working Days Charged76
Percent Time Used59
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-07-038
INTERSTATE BARRICADES & MARKINGS, INC. (1.21)
LONESTAR TRAFFIC SAFETY, LLC (0.63)
HOUSTON TREE & LAWN SERVICE (0.46)
WASHBURN PAVING COMPANY (1.68)
Contract #11163021
Totals646827.000.00623015.2796.3

CountyHOUSTON
HighwayCR
FromCR 2245 @ BIG ELKHART CREEK
To.
CSJ0911-28-041
Proj IDBR 1602(208)
Work TypeBRIDGE REPLACEMENT
 
0.088264168.180.000.0
CountyHOUSTON
HighwayCR
FromCR 1515 SULLIVAN RD AT FLAT BRANCH
To.
CSJ0911-28-042
Proj IDBR 1602(209)
Work TypeBRIDGE REPLACEMENT
 
0.062319948.470.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-09-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
LONGVIEW BRIDGE AND ROAD, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0911-28-041
AMERICAN REMEDIATION OPTIONS, INC. (10.36)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (13.45)
PANOLA SIGN & BARRICADE, INC. (1.40)
Contract #06183228
Totals584116.650.000.000.0

CountyANGELINA
HighwayCR
FromROBINSON LN AT GILLILAND CREEK
To.
CSJ0911-38-069
Proj IDBR 1702(558)
Work TypeBRIDGE REPLACEMENT
 
0.053388000.540.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-11-18
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days43
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TREVWAY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0911-38-069
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05183005
Totals388000.540.000.000.0

page 1 | page 2 | page 3