Monthly State Let Maintenance Report For Bryan District As Of Aug 16, 2018 Page 2 Of 2

Last Update: Thursday, August 16, 2018
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyLEON
HighwayUS0079
FromTRM OFFSET 426 + 0.894
ToTRM OFFSET 434 + 0.858
CSJ6320-46-001
Proj IDRMC - 632046001
Work TypeOVERLAY, PLANING, MBGF, BRIDGE RAIL
 
5.0592153409.702089771.8197.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began11-16-17
Work Completed
Time Computed00-00-00
Contract Working Days55
Addl Days Granted18
Working Days Charged68
Percent Time Used93
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6320-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09174008
Totals2153409.7038218.002089771.8197.0

CountyMADISON
HighwaySH0021
From0.37 MI WEST OF FM 2158
To1.76 MI EAST OF FM 2548
CSJ6322-17-001
Proj IDRMC - 632217001
Work TypeOVERLAY, OCST, PLANING, MBGF, STRUCTURES
 
2.7931063526.9950427.404.7
Work Order06-21-18
Work Began07-03-18
Work Completed
Time Computed06-29-18
Contract Working Days31
Addl Days Granted0
Working Days Charged19
Percent Time Used61
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6322-17-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04184220
Totals1063526.9950427.4050427.404.7

CountyWALKER
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6323-01-001
Proj IDRMC - 632301001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.0012426407.50101957.174.2
Work Order06-14-18
Work Began06-14-18
Work Completed
Time Computed07-02-18
Contract Working Days731
Addl Days Granted0
Working Days Charged48
Percent Time Used6
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-01-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04184007
Totals2426407.50101957.17101957.174.2

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6323-02-001
Proj IDRMC - 632302001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.0011969791.50486072.7924.6
Work Order01-18-18
Work Began01-10-18
Work Completed
Time Computed01-26-18
Contract Working Days731
Addl Days Granted0
Working Days Charged191
Percent Time Used26
Contractor(s)
ALTUS TRAFFIC MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6323-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11174006
Totals1969791.5078153.62486072.7924.6

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6323-03-001
Proj IDRMC - 632303001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.0011078338.50270456.4825.0
Work Order04-25-18
Work Began04-10-18
Work Completed
Time Computed05-03-18
Contract Working Days731
Addl Days Granted0
Working Days Charged93
Percent Time Used12
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6323-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02184008
Totals1078338.5099471.05270456.4825.0

CountyBRAZOS
HighwayBS0006R
FromVARIOUS
ToVARIOUS
CSJ6328-21-001
Proj IDRMC - 632821001
Work TypeHMA MILL AND INLAY
 
0.001629253.100.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-13-18
Work Began08-13-18
Work Completed
Time Computed08-14-18
Contract Working Days66
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6328-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184207
Totals629253.100.000.000.0

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6328-22-001
Proj IDRMC - 632822001
Work TypeHMA MILL AND INLAY
 
0.001642696.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days66
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6328-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184208
Totals642696.000.000.000.0

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6328-23-001
Proj IDRMC - 632823001
Work TypeHMA MILL AND INLAY
 
0.001616781.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days66
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
CORNERSTONE PAVING AND CONSTRUCTION, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6328-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184209
Totals616781.000.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6328-29-001
Proj IDRMC - 632829001
Work TypeSPOT BASE REPAIR
 
0.001802085.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days118
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GLENN FUQUA, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6328-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184009
Totals802085.000.000.000.0

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6328-30-001
Proj IDRMC - 632830001
Work TypeSPOT BASE REPAIR
 
0.001799315.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days118
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6328-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184010
Totals799315.000.000.000.0

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6328-31-001
Proj IDRMC - 632831001
Work TypeSPOT BASE REPAIR
 
0.001766590.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days118
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6328-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184011
Totals766590.000.000.000.0

CountyBRAZOS
HighwayBS0006R
FromVARIOUS
ToVARIOUS
CSJ6332-10-001
Proj IDRMC - 633210001
Work TypeHMA MILL AND INLAY
 
6.5332477766.490.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days38
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6332-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06184023
Totals2477766.490.000.000.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6332-47-001
Proj IDRMC - 633247001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.001747333.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
T&L CLEANING SERVICES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6332-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184206
Totals747333.000.000.000.0

CountyWASHINGTON
HighwayUS0290
FromVARIOUS
ToVARIOUS
CSJ6332-48-001
Proj IDRMC - 633248001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.001883851.500.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days731
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ISI CONTRACTING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6332-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08184005
Totals883851.500.000.000.0

page 1 | page 2