Monthly State Let Maintenance Report For Bryan District As Of Apr 12, 2024 Page 1 Of 3

Last Update: Friday, April 12, 2024
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWALKER
HighwaySH0075
FromVARIOUS
ToVARIOUS
CSJ6348-24-001
Proj IDRMC - 634824001
Work TypeFLAGGING AND TRAFFIC CONTROL
 
0.0012322131.105861467.9599.9
Work Order06-23-20
Work Began07-01-20
Work Completed
Time Computed07-01-20
Contract Working Days731
Addl Days Granted731
Working Days Charged1,370
Percent Time Used93
Contractor(s)
AREA WIDE PROTECTIVE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6348-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03204002
Totals2322131.10171185.195861467.9599.9

CountyGRIMES
HighwayBS0006S
FromVARIOUS
ToVARIOUS
CSJ6375-83-001
Proj IDRMC - 637583001
Work TypeASPHALT PAVEMENT REPAIR
 
0.0101743869.293403884.4699.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began10-30-22
Work Completed
Time Computed00-00-00
Contract Working Days23
Addl Days Granted25
Working Days Charged47
Percent Time Used97
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6375-83-001
CEN TEX HYDROSEED, INC. (0.00)
STRIPE LINES, INC. (0.00)
Contract #06224413
Totals1743869.290.003403884.4699.9

CountyWALKER
HighwayIH0045
FromMONTGOMERY/WALKER COUNTY LINE
ToFREESTONE/NAVARRO COUNTY LINE
CSJ6395-34-001
Proj IDRMC - 639534001
Work TypePERFORMANCE BASED CONTRACT
 
0.01013514343.007059547.3552.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began07-01-22
Work Completed
Time Computed00-00-00
Contract Working Days1,095
Addl Days Granted0
Working Days Charged640
Percent Time Used58
Contractor(s)
ROY JORGENSEN ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6395-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03224006
Totals13514343.00341320.337059547.3552.2

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6395-61-001
Proj IDRMC - 639561001
Work TypePAVEMENT MARKINGS
 
0.010425505.40327570.9076.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-25-22
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged707
Percent Time Used96
Contractor(s)
PROFESSIONAL TRAFFIC CONTROL LLC
SUBCONTRACTOR(S) FOR CCSJ: 6395-61-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02224206
Totals425505.400.00327570.9076.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6411-55-001
Proj IDRMC - 641155001
Work TypeSPOT PAVEMENT MARKINGS
 
0.010458225.00821824.6299.9
Work Order10-20-22
Work Began10-20-22
Work Completed
Time Computed10-20-22
Contract Working Days365
Addl Days Granted365
Working Days Charged529
Percent Time Used72
Contractor(s)
D. I. J. CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6411-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224023
Totals458225.000.00821824.6299.9

CountyWASHINGTON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6411-81-001
Proj IDRMC - 641181001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010416750.00793955.2599.9
Work Order09-20-22
Work Began10-06-22
Work Completed
Time Computed10-20-22
Contract Working Days365
Addl Days Granted365
Working Days Charged543
Percent Time Used74
Contractor(s)
BK FIELD OPERATIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6411-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224025
Totals416750.0040583.00793955.2599.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6411-83-001
Proj IDRMC - 641183001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010431845.00823061.5599.9
Work Order09-20-22
Work Began10-20-22
Work Completed
Time Computed10-20-22
Contract Working Days365
Addl Days Granted365
Working Days Charged529
Percent Time Used72
Contractor(s)
BK FIELD OPERATIONS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6411-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08224026
Totals431845.0023780.00823061.5599.9

CountyWASHINGTON
HighwayPR0012
FromINTERSECTION AT FM 1155
ToINTERSECTION AT FM 1155
CSJ6414-36-001
Proj IDRMC - 641436001
Work TypeLANDSCAPE MAINTENANCE
 
0.010899167.10958966.4599.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-14-23
Work Completed
Time Computed00-00-00
Contract Working Days92
Addl Days Granted0
Working Days Charged90
Percent Time Used97
Contractor(s)
TEXAS MATERIALS GROUP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6414-36-001
CEN TEX HYDROSEED, INC. (0.00)
BROCK CONSTRUCTION, LLC (0.00)
BAYER CONSTRUCTION ELECTRICAL CONTRACTORS, INC. (0.00)
JASON STORM LLC (0.00)
DAVID & DEIKE INTERESTS, L.L.C. (0.00)
Contract #02234208
Totals899167.1050304.35958966.4599.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6422-49-001
Proj IDRMC - 642249001
Work TypeTHERMOPLASTIC PAVEMENT MARKINGS
 
0.0102175650.001219143.13100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-24-23
Work Completed04-12-24
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged313
Percent Time Used85
Contractor(s)
STRIPE LINES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6422-49-001
SURFACE PREPARATION TECHNOLOGIES, LLC (0.00)
Contract #03234015
Totals2175650.000.001219143.13100.0

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6422-55-001
Proj IDMMC - 642255001
Work TypeHOT MIX
 
0.010453460.001096420.3299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-20-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged437
Percent Time Used80
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6422-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12224018
Totals453460.000.001096420.3299.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6422-91-001
Proj IDMMC - 642291001
Work TypeAGGREGATE
 
0.010671600.00771359.6999.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began05-05-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged332
Percent Time Used61
Contractor(s)
ARCOSA LWS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6422-91-001
JASON STORM LLC (0.00)
Contract #02234019
Totals671600.00228902.43771359.6999.9

CountyBRAZOS
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6424-00-001
Proj IDRMC - 642400001
Work TypeMOWING HIGHWAY RIGHT OF WAY
 
0.010528699.00498829.5094.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began01-16-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged441
Percent Time Used60
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6424-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11224206
Totals528699.000.00498829.5094.3

CountyBURLESON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6427-90-001
Proj IDRMC - 642790001
Work TypeTREE REMOVAL
 
0.010603650.00135099.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-27-23
Work Completed03-26-24
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged340
Percent Time Used93
Contractor(s)
CROSS PLUS CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6427-90-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234021
Totals603650.000.00135099.00100.0

CountyBURLESON
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6427-92-001
Proj IDMMC - 642792001
Work TypeHOT MIX
 
0.010395600.00510084.1499.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-12-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged386
Percent Time Used71
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6427-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234221
Totals395600.0042823.21510084.1499.9

CountyMILAM
HighwaySH0036
FromVARIOUS
ToVARIOUS
CSJ6427-94-001
Proj IDMMC - 642794001
Work TypeHOT MIX
 
0.010381000.00409849.5899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-12-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged386
Percent Time Used71
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6427-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234022
Totals381000.000.00409849.5899.9

CountyROBERTSON
HighwaySH0006
FromVARIOUS
ToVARIOUS
CSJ6427-96-001
Proj IDMMC - 642796001
Work TypeHOT MIX
 
0.010341500.00535110.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-12-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged386
Percent Time Used71
Contractor(s)
KNIFE RIVER CORPORATION - SOUTH
SUBCONTRACTOR(S) FOR CCSJ: 6427-96-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234222
Totals341500.0070434.59535110.5099.9

CountyWALKER
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6428-02-001
Proj IDMMC - 642802001
Work TypeHYDRAULIC CEMENT
 
0.010531725.60378226.2571.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began03-01-23
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted360
Working Days Charged397
Percent Time Used73
Contractor(s)
AKA-MATERIALS
SUBCONTRACTOR(S) FOR CCSJ: 6428-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01234024
Totals531725.605848.13378226.2571.1

CountyWALKER
HighwaySH0030
FromVARIOUS
ToVARIOUS
CSJ6430-26-001
Proj IDRMC - 643026001
Work TypeMETAL BEAM GUARD FENCE REPAIR
 
0.010548925.00407290.7774.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began04-08-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted371
Working Days Charged359
Percent Time Used48
Contractor(s)
GARRET SHIELDS INFRASTRUCTURE
SUBCONTRACTOR(S) FOR CCSJ: 6430-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02234037
Totals548925.0016690.00407290.7774.1

CountyLEON
HighwayIH0045
FromVARIOUS
ToVARIOUS
CSJ6432-72-001
Proj IDMMC - 643272001
Work TypeHOT MIX
 
0.010486600.00366858.7875.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began02-01-24
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged60
Percent Time Used33
Contractor(s)
BIG CREEK CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6432-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12234203
Totals486600.00259803.72366858.7875.3

CountyBRAZOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6436-39-001
Proj IDMMC - 643639001
Work TypeWINTER WEATHER MATERIAL
 
0.010450000.0046689.4010.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began06-04-23
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted365
Working Days Charged302
Percent Time Used41
Contractor(s)
TOUCHSTONE RESOURCES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6436-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04234003
Totals450000.000.0046689.4010.3

page 1 | page 2 | page 3