Use this interactive Tableau dashboard to display bidding information on projects let through statewide and local district letting for the past 24 months. The Electronic State Business Daily (ESBD), the Electronic Bidding System, and the project proposal are the official sources of advertisement and bidding information for the State and Local Lettings. Bidders should bid the project using the information found therein, including any addenda. These sources take precedence over information from other sources, including TxDOT webpages, which are unofficial and intended for informational purposes only. |
|
April, 2020 (FY 2020) | (see Links) |
SEP 2019 | OCT 2019 | NOV 2019 | DEC 2019 | JAN 2020 | FEB 2020 | MAR 2020 | APR 2020 | MAY 2020 | JUN 2020 | JUL 2020 | AUG 2020 | | |||||||
CCSJ | County/ District | Highway | Let Status | Contract Cost | Fund Cat | Description | DBE Goal |
---|---|---|---|---|---|---|---|
0122-04-039 | Anderson/ Tyler | US 287 | Actual | $1,212,241 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0114-04-073 | Bastrop/ Austin | US 290 | Actual | $987,709 | 6 | BRIDGE MAINTENANCE | 4.5 |
0915-12-601 | Bexar/ San Antonio | VA | Actual | $1,500,000 | 3 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0915-12-594 | Bexar/ San Antonio | VA | Actual | $1,382,725 | 3 | HIKE AND/OR BIKE | 0.0 |
0915-12-585 | Bexar/ San Antonio | CR | Actual | $14,661,235 | 3 | WIDEN ROAD - ADD LANES | 0.0 |
0915-00-201 | Bexar/ San Antonio | VA | Actual | $2,476,284 | 1 | PURCHASE AND INSTALL SIGNS & EQUIP | 5.0 |
0010-12-072 | Bowie/ Atlanta | US 67 | Actual | $1,106,689 | 8 | INSTALL ILLUMINATION | 0.0 |
0111-04-035 | Brazoria/ Houston | FM 521 | Actual | $2,127,646 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0079-01-043 | Brown/ Brownwood | US 67 | Actual | $789,779 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0054-07-084 | Brown/ Brownwood | US 84 | Actual | $1,679,426 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0917-30-055 | Burleson/ Bryan | CR | Actual | $1,536,771 | 6 | BRIDGE REPLACEMENT | 5.0 |
0921-06-288 | Cameron/ Pharr | CS | Actual | $18,808,761 | 3 | WIDEN ROAD - ADD LANES AND SHOULDERS | 0.0 |
0331-04-069 | Cameron/ Pharr | PR 100 | Actual | $7,118,934 | 6 | BRIDGE MAINTENANCE | 3.0 |
1150-02-006 | Cherokee/ Tyler | FM 235 | Actual | $3,380,063 | 8 | HAZARD ELIMINATION & SAFETY | 4.5 |
0054-02-035 | Coleman/ Brownwood | US 84 | Actual | $495,757 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
2247-01-011 | Collin/ Dallas | FM 2194 | Actual | $3,322,783 | 8 | REHABILITATE EXISTING ROADWAY | 10.5 |
0183-01-047 | Comanche/ Brownwood | SH 36 | Actual | $261,984 | 11 | INTERSECTION IMPROVEMENT | 0.0 |
0257-05-046 | Comanche/ Brownwood | SH 6 | Actual | $15,740,237 | 1 | HIGHWAY IMPROVEMENT | 7.5 |
1855-01-028 | Cooke/ Wichita Falls | FM 922 | Actual | $158,712 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0140-11-046 | Crockett/ San Angelo | IH 10 | Actual | $3,098,661 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
0918-45-372 | Dallas/ Dallas | CS | Actual | $2,584,107 | 3 | INTERSECTION IMPROVEMENT | 0.0 |
2374-03-094 | Dallas/ Dallas | IH 20 | Actual | $6,296,941 | 11 | BRIDGE MAINTENANCE | 5.0 |
0918-47-227 | Dallas/ Dallas | CS | Actual | $1,746,955 | 3 | TRAFFIC SIGNAL IMPROVEMENTS | 4.5 |
0918-00-358 | Dallas/ Dallas | VA | Actual | $2,875,000 | 5 | TRANSPORTATION SYSTEM SENSORS | 0.0 |
0918-00-357 | Dallas/ Dallas | VA | Actual | $1,375,000 | 5 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-00-331 | Dallas/ Dallas | VA | Actual | $150,000 | 7 | ADVANCED TRAFFIC MANAGEMENT SYSTEM | 0.0 |
0918-46-315 | Denton/ Dallas | VA | Actual | $3,000,000 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
0918-46-317 | Denton/ Dallas | VA | Actual | $400,000 | 3 | RAILROAD CROSSING IMPROVEMENTS | 0.0 |
0913-17-039 | Dewitt/ Yoakum | CR | Actual | $1,156,924 | 6 | BRIDGE REPLACEMENT | 4.0 |
0924-06-603 | El Paso/ El Paso | VA | Actual | $1,929,431 | 1 | PREVENTIVE MAINTENANCE | 6.0 |
0167-01-120 | El Paso/ El Paso | US 54 | Actual | $1,029,343 | 1 | PREVENTIVE MAINTENANCE | 5.5 |
0167-01-127 | El Paso/ El Paso | US 54 | Actual | $699,747 | 1 | INSTALL INTELLIGENT VEHICLE HIGHWAY SYSTEM | 0.0 |
0808-01-061 | Falls/ Waco | FM 413 | Actual | $2,045,804 | 6 | BRIDGE MAINTENANCE | 7.5 |
1154-01-020 | Fannin/ Paris | FM 824 | Actual | $6,197,935 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0917-20-039 | Freestone/ Bryan | CR | Actual | $482,852 | 6 | BRIDGE REPLACEMENT | 0.0 |
0573-04-017 | Gonzales/ Yoakum | FM 1116 | Actual | $3,865,600 | 1 | ROADWAY REHABILITATION/RECONSTRUCTION WITH NO ADDED CAPACITY | 5.0 |
0091-01-054 | Grayson/ Paris | SH 289 | Actual | $2,650,658 | 1 | PREVENTIVE MAINTENANCE | 0.0 |
2073-01-009 | Gregg/ Tyler | FM 2206 | Actual | $15,228,265 | 1 | WIDEN ROAD - ADD LANES | 6.0 |
2072-01-016 | Gregg/ Tyler | FM 2204 | Actual | $4,811,415 | 8 | INSTALL/UPGRADE DRAINAGE STRUCTURE(S) | 5.0 |
0065-05-153 | Hardin/ Beaumont | US 96 | Actual | $279,713 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
1685-05-123 | Harris/ Houston | SH 6 | Actual | $252,084 | 8 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
1685-05-128 | Harris/ Houston | SH 6 | Actual | $595,166 | 8 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0389-12-092 | Harris/ Houston | SH 146 | Actual | $738,805 | 11 | INTERSECTION IMPROVEMENT | 0.0 |
0912-00-599 | Harris/ Houston | VA | Actual | $5,100,000 | 3 | ENGINEERING DESIGN/STUDY | 0.0 |
0028-01-099 | Harris/ Houston | UA 90 | Actual | $1,535,715 | 1 | SURFACING/ROADWAY RESTORATION | 4.5 |
3545-02-010 | Hays/ Austin | FM 110 | Actual | $7,183,810 | 3 | CONSTRUCT BRIDGE | 9.0 |
0016-02-152 | Hays/ Austin | IH 35 | Actual | $23,219,274 | 1 | CONSTRUCT RAMPS | 11.0 |
0016-02-166 | Hays/ Austin | IH 35 | Actual | $1,962,067 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0921-02-385 | Hidalgo/ Pharr | CS | Actual | $7,265,963 | 3 | TRANSPORTATION NON-ROADWAY | 5.5 |
3370-01-008 | Hopkins/ Paris | FM 3389 | Actual | $4,838,116 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
0911-28-047 | Houston/ Lufkin | CR | Actual | $2,092,203 | 6 | BRIDGE REPLACEMENT | 7.5 |
1495-01-009 | Hunt/ Paris | FM 1566 | Actual | $4,103,077 | 1 | REHABILITATE EXISTING ROADWAY | 0.0 |
1552-01-011 | Karnes/ Corpus Christi | FM 1020 | Actual | $1,946,400 | 6 | BRIDGE REPLACEMENT | 8.5 |
0133-01-052 | King/ Childress | US 82 | Actual | $1,419,413 | 1 | HIGHWAY IMPROVEMENT | 3.0 |
0251-04-026 | Lampasas/ Brownwood | US 281 | Actual | $811,494 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0593-01-122 | Liberty/ Beaumont | SH 321 | Actual | $1,129,194 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
1819-01-015 | Lipscomb/ Amarillo | FM 1920 | Actual | $15,850,525 | 11 | HAZARD ELIMINATION & SAFETY | 0.0 |
0905-00-081 | Lubbock/ Lubbock | VA | Actual | $2,027,598 | 1 | INSTALL/REPLACE SIGNS | 0.0 |
0052-07-071 | Lubbock/ Lubbock | US 84 | Actual | $7,138,870 | 8 | HAZARD ELIMINATION & SAFETY | 3.5 |
0053-01-126 | Lubbock/ Lubbock | US 84 | Actual | $2,156,196 | 8 | HAZARD ELIMINATION & SAFETY | 3.0 |
2506-01-042 | Mclennan/ Waco | FM 1695 | Actual | $722,722 | 10 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 7.0 |
0675-08-111 | Montgomery/ Houston | IH 45 | Actual | $2,365,922 | 5 | ADVANCED TRAFFIC MANAGEMENT SYSTEM | 7.0 |
0092-06-107 | Navarro/ Dallas | IH 45 | Actual | $1,200,859 | 1 | REPAIR ROADWAY | 0.0 |
0916-00-091 | Nueces/ Corpus Christi | VA | Actual | $1,264,697 | 1 | INSTALL/REPLACE SIGNS | 5.0 |
0090-02-053 | Oldham/ Amarillo | IH 40 | Actual | $4,479,165 | 8 | HAZARD ELIMINATION & SAFETY | 6.0 |
1286-01-018 | Orange/ Beaumont | FM 1078 | Actual | $705,343 | 8 | HAZARD ELIMINATION & SAFETY | 4.0 |
0924-07-017 | Presidio/ El Paso | CS | Actual | $490,999 | 3 | CONSTRUCT PEDESTRIAN INFRASTRUCTURE | 0.0 |
2451-03-017 | Reeves/ Odessa | RM 652 | Actual | $19,019,375 | 11 | HIGHWAY IMPROVEMENT | 6.5 |
0371-03-131 | Refugio/ Corpus Christi | US 77 | Actual | $791,756 | 1 | HAZARD ELIMINATION & SAFETY | 0.0 |
0495-04-070 | Smith/ Tyler | IH 20 | Actual | $2,457,559 | 1 | SURFACING/ROADWAY RESTORATION | 0.0 |
0492-04-039 | Smith/ Tyler | FM 346 | Actual | $212,802 | 11 | TRAFFIC SIGNAL IMPROVEMENTS | 0.0 |
0191-01-092 | Smith/ Tyler | US 69 | Actual | $2,870,315 | 11 | RESURFACE ROADWAY | 2.0 |
0008-16-042 | Tarrant/ Ft Worth | IH 20 | Actual | $24,136,520 | 1 | CONSTRUCT NEW ROADWAY LANES | 11.5 |
0902-90-170 | Tarrant/ Ft Worth | VA | Actual | $504,390 | 3 | TRANSPORTATION NON-ROADWAY | 0.0 |
0747-04-076 | Tarrant/ Ft Worth | FM 157 | Actual | $4,001,218 | 1 | RESURFACE ROADWAY | 4.0 |
0683-02-080 | Travis/ Austin | RM 620 | Actual | $516,439 | 1 | INSTALL RAISED MEDIAN | 0.0 |
0015-10-063 | Travis/ Austin | IH 35 | Actual | $8,504,174 | 11 | CONSTRUCT RAMPS | 7.5 |
0151-06-149 | Travis/ Austin | US 183 | Actual | $4,073,719 | 1 | SURFACING/ROADWAY RESTORATION | 9.5 |
0703-01-067 | Tyler/ Beaumont | FM 92 | Actual | $8,195,290 | 11 | SURFACING/ROADWAY RESTORATION | 2.0 |
0543-01-066 | Waller/ Houston | FM 359 | Actual | $86,197 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0043-09-142 | Wichita/ Wichita Falls | US 287 | Actual | $896,187 | 8 | REMOVE/REPLACE BRIDGE RAIL | 0.0 |
0204-02-033 | Williamson/ Austin | US 79 | Actual | $789,461 | 8 | HAZARD ELIMINATION & SAFETY | 0.0 |
0015-09-177 | Williamson/ Austin | IH 35 | Actual | $926,980 | 6 | BRIDGE MAINTENANCE | 3.5 |
|