Contract Identification and Information | Length | Contract Amount | Amount This Estimate | Total Estimate To Date | % Comp |
|
County | VAN ZANDT |
Highway | FM0773 |
From | VARIOUS ROADWAYS |
To | IN VAN ZANDT COUNTY |
CSJ | 6440-57-001 |
Proj ID | RMC - 644057001 |
Work Type | BASE FAILURE PAVEMENT REPAIR |
|
| 0.010 | 1085594.00 | | 682791.60 | 62.8 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-29-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 61 |
Percent Time Used | 16 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6440-57-001 FREDONIA CONSTRUCTION SERVICES (0.00)
|
Contract # | 11234029 |
| Totals | 1085594.00 | 0.00 | 682791.60 | 62.8 |
|
County | RUSK |
Highway | FM1798 |
From | VARIOUS ROADWAYS |
To | IN RUSK COUNTY |
CSJ | 6440-59-001 |
Proj ID | RMC - 644059001 |
Work Type | BASE FAILURE PAVEMENT REPAIR |
|
| 0.010 | 1049287.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
RAYFORD'S TRUCK & TRACTOR |
SUBCONTRACTOR(S) FOR CCSJ: 6440-59-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234039 |
| Totals | 1049287.00 | 0.00 | 0.00 | 0.0 |
|
County | ANDERSON |
Highway | US0079 |
From | VARIOUS ROADWAYS IN |
To | ANDERSON & CHEROKEE COUNTIES |
CSJ | 6444-56-001 |
Proj ID | RMC - 644456001 |
Work Type | MILL AND INLAY |
|
| 0.010 | 2220151.50 | | 2162627.38 | 97.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 21 |
Addl Days Granted | 0 |
Working Days Charged | 14 |
Percent Time Used | 66 |
Contractor(s) |
MADDEN CONTRACTING COMPANY, LLC. |
SUBCONTRACTOR(S) FOR CCSJ: 6444-56-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234218 |
| Totals | 2220151.50 | 2162627.38 | 2162627.38 | 97.4 |
|
County | WOOD |
Highway | US0080 |
From | VARIOUS ROADWAYS IN WOOD, |
To | RUSK, AND VAN ZANDT COUNTIES |
CSJ | 6444-58-001 |
Proj ID | RMC - 644458001 |
Work Type | MILL AND INLAY |
|
| 0.010 | 2900777.00 | | 2863911.03 | 100.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 01-03-24 |
Work Completed | 02-28-24 |
Time Computed | 00-00-00 |
Contract Working Days | 34 |
Addl Days Granted | 0 |
Working Days Charged | 33 |
Percent Time Used | 97 |
Contractor(s) |
DREWERY CONSTRUCTION COMPANY, INCORPORATED |
SUBCONTRACTOR(S) FOR CCSJ: 6444-58-001 PANOLA SIGN & BARRICADE, INC. (0.00)
|
Contract # | 10234027 |
| Totals | 2900777.00 | 1149778.63 | 2863911.03 | 100.0 |
|
County | WOOD |
Highway | US0080 |
From | MINEOLA MTCE SECTION |
To | WOOD COUNTY |
CSJ | 6446-50-001 |
Proj ID | RMC - 644650001 |
Work Type | TREE REMOVAL |
|
| 0.010 | 615616.00 | | 193102.00 | 31.3 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 145 |
Percent Time Used | 19 |
Contractor(s) |
CATOCON, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6446-50-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234041 |
| Totals | 615616.00 | 3741.00 | 193102.00 | 31.3 |
|
County | HENDERSON |
Highway | US0175 |
From | VARIOUS LOCATIONS IN |
To | THE TYLER DISTRICT |
CSJ | 6447-69-001 |
Proj ID | MMC - 644769001 |
Work Type | AGGREGATE |
|
| 0.010 | 3028375.00 | | 946019.60 | 31.2 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 09-30-23 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 173 |
Percent Time Used | 47 |
Contractor(s) |
TOUCHSTONE RESOURCES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6447-69-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 08234043 |
| Totals | 3028375.00 | 93366.00 | 946019.60 | 31.2 |
|
County | SMITH |
Highway | FM3341 |
From | VARIOUS LOCATIONS |
To | IN THE TYLER DISTRICT |
CSJ | 6451-11-001 |
Proj ID | BPM - 645111001 |
Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
|
| 0.010 | 527250.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 85 |
Addl Days Granted | 0 |
Working Days Charged | 10 |
Percent Time Used | 11 |
Contractor(s) |
GARRET SHIELDS INFRASTRUCTURE |
SUBCONTRACTOR(S) FOR CCSJ: 6451-11-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234219 |
| Totals | 527250.00 | 0.00 | 0.00 | 0.0 |
|
County | VAN ZANDT |
Highway | FM2339 |
From | VARIOUS LOCATIONS |
To | IN THE TYLER DISTRICT |
CSJ | 6451-13-001 |
Proj ID | BPM - 645113001 |
Work Type | BRIDGE PREVENTATIVE MAINTENANCE |
|
| 0.010 | 739192.55 | | 118340.59 | 16.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-20-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 102 |
Addl Days Granted | 0 |
Working Days Charged | 29 |
Percent Time Used | 28 |
Contractor(s) |
RED BARON BUILDING COMPANY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6451-13-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234220 |
| Totals | 739192.55 | 101921.87 | 118340.59 | 16.0 |
|
County | SMITH |
Highway | SL0323 |
From | VARIOUS LOCATIONS |
To | IN SMITH AND VAN ZANDT COUNTIES |
CSJ | 6453-97-001 |
Proj ID | RMC - 645397001 |
Work Type | MILL AND INLAY |
|
| 0.010 | 4469287.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 32 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6453-97-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 01244029 |
| Totals | 4469287.00 | 0.00 | 0.00 | 0.0 |
|
County | SMITH |
Highway | US0069 |
From | VARIOUS ROADWAYS IN |
To | SMITH & CHEROKEE COUNTIES |
CSJ | 6456-39-001 |
Proj ID | RMC - 645639001 |
Work Type | PAVEMENT MARKINGS |
|
| 0.010 | 4944538.30 | | 147486.34 | 2.9 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 54 |
Percent Time Used | 7 |
Contractor(s) |
REYNOLDS & KAY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6456-39-001 STRIPING TECHNOLOGY, L.P. (99.97) BRYDL CONTRACTING, LLC (11.03) WEST TEXAS ROCK RESOURCES, LLC (0.40)
|
Contract # | 11234030 |
| Totals | 4944538.30 | 116768.18 | 147486.34 | 2.9 |
|
County | GREGG |
Highway | US0259 |
From | VARIOUS ROADWAYS IN |
To | GREGG & RUSK COUNTIES |
CSJ | 6456-41-001 |
Proj ID | RMC - 645641001 |
Work Type | PAVEMENT MARKINGS |
|
| 0.010 | 5035050.97 | | 77486.36 | 1.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 02-14-24 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 45 |
Percent Time Used | 6 |
Contractor(s) |
REYNOLDS & KAY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6456-41-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234221 |
| Totals | 5035050.97 | 77486.36 | 77486.36 | 1.5 |
|
County | HENDERSON |
Highway | SH0019 |
From | VARIOUS ROADWAYS IN |
To | HENDERSON & ANDERSON COUNTIES |
CSJ | 6456-91-001 |
Proj ID | RMC - 645691001 |
Work Type | PAVEMENT MARKINGS |
|
| 0.010 | 4796393.50 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
TRP CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6456-91-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 02244214 |
| Totals | 4796393.50 | 0.00 | 0.00 | 0.0 |
|
County | WOOD |
Highway | US0080 |
From | VARIOUS ROADWAYS IN |
To | WOOD & VAN ZANDT COUNTIES |
CSJ | 6456-93-001 |
Proj ID | RMC - 645693001 |
Work Type | PAVEMENT MARKINGS |
|
| 0.010 | 4729775.00 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 730 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
STRIPING TECHNOLOGY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6456-93-001 WEST TEXAS ROCK RESOURCES, LLC (0.36) REYNOLDS & KAY, LTD. (1.34) BRYDL CONTRACTING, LLC (13.20)
|
Contract # | 02244013 |
| Totals | 4729775.00 | 0.00 | 0.00 | 0.0 |
|
County | ANDERSON |
Highway | US0079 |
From | VARIOUS LOCATION IN TYLER DISTRICT |
To | TYLER DISTRICT |
CSJ | 6457-46-001 |
Proj ID | MMC - 645746001 |
Work Type | HOT MIX |
|
| 0.010 | 1341800.00 | | 194214.66 | 14.4 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 88 |
Percent Time Used | 24 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6457-46-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234222 |
| Totals | 1341800.00 | 176528.24 | 194214.66 | 14.4 |
|
County | HENDERSON |
Highway | US0175 |
From | VARIOUS LOCATION IN TYLER DISTRICT |
To | TYLER DISTRICT |
CSJ | 6457-59-001 |
Proj ID | MMC - 645759001 |
Work Type | HOT MIX |
|
| 0.010 | 1524500.00 | | 328714.90 | 21.5 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 365 |
Addl Days Granted | 0 |
Working Days Charged | 89 |
Percent Time Used | 24 |
Contractor(s) |
BIG CREEK CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6457-59-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 11234223 |
| Totals | 1524500.00 | 3347.40 | 328714.90 | 21.5 |
|
County | RUSK |
Highway | US0079 |
From | VARIOUS LOCATIONS |
To | IN RUSK COUNTY |
CSJ | 6461-63-001 |
Proj ID | RMC - 646163001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 689948.44 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 110 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
SERVIN MOWING |
SUBCONTRACTOR(S) FOR CCSJ: 6461-63-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 03244024 |
| Totals | 689948.44 | 0.00 | 0.00 | 0.0 |
|
County | WOOD |
Highway | US0069 |
From | VARIOUS LOCATIONS |
To | WOOD COUNTY |
CSJ | 6464-12-001 |
Proj ID | RMC - 646412001 |
Work Type | MOWING HIGHWAY RIGHT OF WAY |
|
| 0.010 | 623147.24 | | 0.00 | 0.0 |
NO CURRENT ESTIMATE AT TIME OF THIS RUN |
Work Order | 00-00-00 |
Work Began | 00-00-00 |
Work Completed | |
Time Computed | 00-00-00 |
Contract Working Days | 106 |
Addl Days Granted | 0 |
Working Days Charged | 0 |
Percent Time Used | 0 |
Contractor(s) |
SOUTHERN EDGE CONTRACTORS LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6464-12-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
Contract # | 04244027 |
| Totals | 623147.24 | 0.00 | 0.00 | 0.0 |
|