| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | SMITH |
| Highway |
US0069 |
| From |
ANDERSON, CHEROKEE, HENDERSON, RUSK, |
| To |
SMITH, VAN ZANDT, & WOOD CO. |
| CSJ |
6216-38-001 |
| Proj ID |
RMC - 621638001 |
| Work Type |
GUARDRAIL REPAIR / REPLACE DW |
| |
|
0.010 |
361765.09 |
21195.27 |
305648.08 |
87.3 |
| Work Order |
02-01-11 |
| Work Began |
03-09-11 |
| Work Completed |
|
| Time Computed |
03-01-11 |
| Contract Working Days |
255 |
| Addl Days Granted |
255 |
| Working Days Charged |
298 |
| Percent Time Used |
58 |
| Contractor(s) |
| VANN/ELLI, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6216-38-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11104002 |
|
Totals |
361765.09 |
21195.27 |
305648.08 |
87.3 |
|
| County | SMITH |
| Highway |
IH0020 |
| From |
GREGG/HARRISON COUNTY LINE |
| To |
VAN ZANDT/KAUFMAN COUNTY LINE |
| CSJ |
6219-71-001 |
| Proj ID |
RMC - 621971001 |
| Work Type |
IH 20 TOTAL MAINTENANCE |
| |
|
83.600 |
1795419.95 |
36053.04 |
1273743.00 |
70.9 |
| Work Order |
02-25-11 |
| Work Began |
03-09-11 |
| Work Completed |
|
| Time Computed |
03-09-11 |
| Contract Working Days |
255 |
| Addl Days Granted |
255 |
| Working Days Charged |
292 |
| Percent Time Used |
57 |
| Contractor(s) |
| STRIPING TECHNOLOGY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6219-71-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01114015 |
|
Totals |
1795419.95 |
36053.04 |
1273743.00 |
70.9 |
|
| County | SMITH |
| Highway |
US0069 |
| From |
VARIOUS ROADWAYS WITHIN THE TYLER |
| To |
DISTRICT |
| CSJ |
6222-30-001 |
| Proj ID |
RMC - 622230001 |
| Work Type |
LONG LINE THERMO STRIPING |
| |
|
0.100 |
1975520.00 |
131476.81 |
1083699.52 |
54.8 |
| Work Order |
06-23-11 |
| Work Began |
07-01-11 |
| Work Completed |
|
| Time Computed |
07-01-11 |
| Contract Working Days |
255 |
| Addl Days Granted |
0 |
| Working Days Charged |
211 |
| Percent Time Used |
82 |
| Contractor(s) |
| STRIPING TECHNOLOGY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6222-30-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04114006 |
|
Totals |
1975520.00 |
131476.81 |
1083699.52 |
54.8 |
|
| County | SMITH |
| Highway |
US0069 |
| From |
VARIOUS ROADWAYS IN THE TYLER |
| To |
DISTRICT |
| CSJ |
6222-31-001 |
| Proj ID |
RMC - 622231001 |
| Work Type |
PAINT AND BEAD STRIPING |
| |
|
0.100 |
440455.00 |
41379.27 |
249815.89 |
56.7 |
| Work Order |
09-02-11 |
| Work Began |
09-23-11 |
| Work Completed |
|
| Time Computed |
09-06-11 |
| Contract Working Days |
255 |
| Addl Days Granted |
0 |
| Working Days Charged |
166 |
| Percent Time Used |
65 |
| Contractor(s) |
| STRIPING TECHNOLOGY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6222-31-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04114005 |
|
Totals |
440455.00 |
41379.27 |
249815.89 |
56.7 |
|
| County | SMITH |
| Highway |
US0069 |
| From |
VARIOUS ROADWAYS IN THE TYLER DISTRICT |
| To |
TO INCLUDE SEALCOAT ROADS |
| CSJ |
6224-30-001 |
| Proj ID |
RMC - 622430001 |
| Work Type |
SL THERMO AND RAISED PAVEMENT MARKERS |
| |
|
0.010 |
409257.95 |
31433.80 |
279344.40 |
68.2 |
| Work Order |
06-23-11 |
| Work Began |
07-11-11 |
| Work Completed |
|
| Time Computed |
07-11-11 |
| Contract Working Days |
255 |
| Addl Days Granted |
0 |
| Working Days Charged |
206 |
| Percent Time Used |
80 |
| Contractor(s) |
| STRIPING TECHNOLOGY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6224-30-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05114022 |
|
Totals |
409257.95 |
31433.80 |
279344.40 |
68.2 |
|
| County | RUSK |
| Highway |
FM0095 |
| From |
FM 95 |
| To |
1/2 WAY TO NACOGDOCHES COUNTY LINE |
| CSJ |
6229-17-001 |
| Proj ID |
RMC - 622917001 |
| Work Type |
REHAB OF ROADWAY |
| |
|
0.010 |
1538363.36 |
217353.75 |
1143127.80 |
74.3 |
| Work Order |
11-14-11 |
| Work Began |
12-01-11 |
| Work Completed |
|
| Time Computed |
12-01-11 |
| Contract Working Days |
108 |
| Addl Days Granted |
0 |
| Working Days Charged |
67 |
| Percent Time Used |
62 |
| Contractor(s) |
| A. L. HELMCAMP, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6229-17-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08114003 |
|
Totals |
1538363.36 |
217353.75 |
1143127.80 |
74.3 |
|
| County | VAN ZANDT |
| Highway |
FM0859 |
| From |
FM 859 FROM SH 19 |
| To |
FM 1395 |
| CSJ |
6229-18-001 |
| Proj ID |
RMC - 622918001 |
| Work Type |
REHAB OF ROADWAY |
| |
|
0.010 |
1540738.48 |
178365.28 |
531181.34 |
34.4 |
| Work Order |
01-11-12 |
| Work Began |
02-16-12 |
| Work Completed |
|
| Time Computed |
02-01-12 |
| Contract Working Days |
108 |
| Addl Days Granted |
0 |
| Working Days Charged |
32 |
| Percent Time Used |
29 |
| Contractor(s) |
| TEXANA LAND & ASPHALT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6229-18-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08114004 |
|
Totals |
1540738.48 |
178365.28 |
531181.34 |
34.4 |
|
| County | CHEROKEE |
| Highway |
US0069 |
| From |
VARIOUS ROADS IN HENDERSON, J'VILLE/RUSK |
| To |
AND PALESTINE MAINTENANCE SECTIONS |
| CSJ |
6229-32-001 |
| Proj ID |
RMC - 622932001 |
| Work Type |
TREE REMOVAL |
| |
|
0.010 |
244417.80 |
18470.10 |
61295.85 |
25.0 |
| Work Order |
10-24-11 |
| Work Began |
11-07-11 |
| Work Completed |
|
| Time Computed |
11-01-11 |
| Contract Working Days |
255 |
| Addl Days Granted |
0 |
| Working Days Charged |
126 |
| Percent Time Used |
49 |
| Contractor(s) |
| L & M CLEANING SERVICE |
SUBCONTRACTOR(S) FOR CCSJ: 6229-32-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08114005 |
|
Totals |
244417.80 |
18470.10 |
61295.85 |
25.0 |
|
| County | CHEROKEE |
| Highway |
SH0110 |
| From |
JVILLE/RUSK |
| To |
TYLER MTCE. |
| CSJ |
6230-15-001 |
| Proj ID |
RMC - 623015001 |
| Work Type |
TREE TRIMMING AND BRUSH CONTROL |
| |
|
356.600 |
561645.00 |
131512.50 |
484785.00 |
86.3 |
| Work Order |
10-27-11 |
| Work Began |
12-08-11 |
| Work Completed |
|
| Time Computed |
11-07-11 |
| Contract Working Days |
265 |
| Addl Days Granted |
0 |
| Working Days Charged |
122 |
| Percent Time Used |
46 |
| Contractor(s) |
| TERRY ENTERPRISES |
SUBCONTRACTOR(S) FOR CCSJ: 6230-15-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08114018 |
|
Totals |
561645.00 |
131512.50 |
484785.00 |
86.3 |
|
| County | VAN ZANDT |
| Highway |
SH0243 |
| From |
ATHEN, CANTON |
| To |
PALESTINE MTCE. |
| CSJ |
6230-16-001 |
| Proj ID |
RMC - 623016001 |
| Work Type |
TREE TRIMMING AND BRUSH CONTROL |
| |
|
255.210 |
341463.32 |
8964.40 |
174484.67 |
51.0 |
| Work Order |
12-14-11 |
| Work Began |
01-24-12 |
| Work Completed |
|
| Time Computed |
01-12-12 |
| Contract Working Days |
265 |
| Addl Days Granted |
0 |
| Working Days Charged |
78 |
| Percent Time Used |
29 |
| Contractor(s) |
| ANALYTICAL TECHNOLOGY CONSULTANTS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6230-16-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114039 |
|
Totals |
341463.32 |
8964.40 |
174484.67 |
51.0 |
|
| County | WOOD |
| Highway |
FM2869 |
| From |
HENDERSON, LONGVIEW |
| To |
MINEOLA MTCE. |
| CSJ |
6230-17-001 |
| Proj ID |
RMC - 623017001 |
| Work Type |
TREE TRIMMING AND BRUSH CONTROL |
| |
|
244.410 |
503496.82 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
265 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ANALYTICAL TECHNOLOGY CONSULTANTS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6230-17-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114040 |
|
Totals |
503496.82 |
0.00 |
0.00 |
0.0 |
|
| County | ANDERSON |
| Highway |
US0175 |
| From |
VARIOUS LOCATIONS WITHIN THE TYLER |
| To |
DISTRICT |
| CSJ |
6233-62-001 |
| Proj ID |
RMC - 623362001 |
| Work Type |
MICROSURFACING |
| |
|
0.010 |
772460.00 |
0.00 |
96620.00 |
12.5 |
| ESTIMATE HAS BEEN BY-PASSED |
| Work Order |
02-03-12 |
| Work Began |
02-27-12 |
| Work Completed |
|
| Time Computed |
02-13-12 |
| Contract Working Days |
255 |
| Addl Days Granted |
0 |
| Working Days Charged |
56 |
| Percent Time Used |
21 |
| Contractor(s) |
| NY-MAC ENTERPRISES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6233-62-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12114024 |
|
Totals |
772460.00 |
0.00 |
96620.00 |
12.5 |
|
| County | SMITH |
| Highway |
US0271 |
| From |
745' S OF IH 20 N |
| To |
655' N OF IH 20 |
| CSJ |
6236-71-001 |
| Proj ID |
RMC - 623671001 |
| Work Type |
ROADWAY REHAB |
| |
|
0.010 |
609487.86 |
0.00 |
0.00 |
1.7 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-25-12 |
| Work Began |
05-02-12 |
| Work Completed |
|
| Time Computed |
05-02-12 |
| Contract Working Days |
40 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| REYNOLDS & KAY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6236-71-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03124006 |
|
Totals |
609487.86 |
0.00 |
0.00 |
1.7 |
|
| County | GREGG |
| Highway |
IH0020 |
| From |
4 LOCATIONS ON IH 20 |
| To |
EB & WB IN GREGG CO. |
| CSJ |
6236-83-001 |
| Proj ID |
BPM - 623683001 |
| Work Type |
BRIDGE RAIL AND MBGF |
| |
|
0.427 |
400229.84 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
49 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| RAY FARIS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6236-83-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04124003 |
|
Totals |
400229.84 |
0.00 |
0.00 |
0.0 |
|
| County | ANDERSON |
| Highway |
US0175 |
| From |
US 175 IN FRANKSTON |
| To |
JACKSONVILLE MAINTENANCE SECTION |
| CSJ |
6237-73-001 |
| Proj ID |
RMC - 623773001 |
| Work Type |
MICROSURFACE US 175 |
| |
|
3.603 |
922410.89 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-07-12 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
05-16-12 |
| Contract Working Days |
22 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| NY-MAC ENTERPRISES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6237-73-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01124035 |
|
Totals |
922410.89 |
0.00 |
0.00 |
0.0 |
|
| County | GREGG |
| Highway |
LP0281 |
| From |
750' NW OF FM 2205 SOUTHEAST |
| To |
338' WEST OF ESTES PARKWAY |
| CSJ |
6238-95-001 |
| Proj ID |
RMC - 623895001 |
| Work Type |
PFC OVERLAY |
| |
|
3.337 |
1201821.28 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
34 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| REYNOLDS & KAY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6238-95-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03124005 |
|
Totals |
1201821.28 |
0.00 |
0.00 |
0.0 |
|
| County | GREGG |
| Highway |
SP0063 |
| From |
105' NORTH OF US 80 NORTH |
| To |
350' SOUTH OF LP 281 |
| CSJ |
6238-96-001 |
| Proj ID |
RMC - 623896001 |
| Work Type |
PFC OVERLAY |
| |
|
2.904 |
1122109.82 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
34 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| REYNOLDS & KAY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6238-96-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03124024 |
|
Totals |
1122109.82 |
0.00 |
0.00 |
0.0 |
|
| County | SMITH |
| Highway |
US0069 |
| From |
VARIOUS ROADWAYS WITHIN THE TYLER |
| To |
DISTRICT |
| CSJ |
6239-37-001 |
| Proj ID |
RMC - 623937001 |
| Work Type |
LONG LINE THERMO STRIPING |
| |
|
0.100 |
2098690.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
255 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| STRIPING TECHNOLOGY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6239-37-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04124004 |
|
Totals |
2098690.00 |
0.00 |
0.00 |
0.0 |
|
| County | SMITH |
| Highway |
US0069 |
| From |
VARIOUS ROADWAYS IN THE TYLER |
| To |
DISTRICT |
| CSJ |
6240-11-001 |
| Proj ID |
RMC - 624011001 |
| Work Type |
PAINT AND BEAD STRIPING |
| |
|
0.100 |
422400.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
255 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| STRIPING TECHNOLOGY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6240-11-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05124013 |
|
Totals |
422400.00 |
0.00 |
0.00 |
0.0 |
|
| County | CHEROKEE |
| Highway |
US0175 |
| From |
US 175 979'W OF PENIDA ST., EAST |
| To |
849'E OF PENIDA ST. |
| CSJ |
6240-12-001 |
| Proj ID |
RMC - 624012001 |
| Work Type |
WIDENING FOR TURNING LANE |
| |
|
0.346 |
365100.30 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
45 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| REYNOLDS & KAY, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6240-12-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
04124019 |
|
Totals |
365100.30 |
0.00 |
0.00 |
0.0 |
|