Monthly Local Let Maintenance Report For San Angelo District As Of Feb 10, 2017 Page 3 Of 4

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountySUTTON
HighwayUS0277
FromVARIOUS ROADS IN SUTTON SCHLEICHER
ToVARIOUS ROADS IN SUTTON SCHLEICHER
CSJ6289-34-001
Proj IDRMC - 628934001
Work TypeRIGHT OF WAY MOWING SUTTON
 
0.011194337.52291506.2899.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days49
Addl Days Granted70
Working Days Charged44
Percent Time Used36
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09150711
Totals194337.520.00291506.2899.9

CountyCROCKETT
HighwaySH0163
FromVARIOUS ROADS IN CROCKETT COUNTY
ToVARIOUS ROADS IN CROCKETT COUNTY
CSJ6289-35-001
Proj IDRMC - 628935001
Work TypeRIGHT OF WAY MOWING IN CROCKETT
 
0.001197499.80296249.7099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-21-15
Work Began00-00-00
Work Completed
Time Computed12-21-15
Contract Working Days30
Addl Days Granted54
Working Days Charged50
Percent Time Used59
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150701
Totals197499.800.00296249.7099.9

CountyKIMBLE
HighwayUS0083
FromVARIOUS LOCATIONS IN JUNCTION AREA OFF
ToVARIOUS LOCATIONS IN JUNCTION AREA OFF
CSJ6291-65-001
Proj IDSUP - 629165001
Work TypePICNIC AREA MAINTENANCE & LANDSCAPE
 
0.001273804.24342612.0599.9
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days365
Addl Days Granted0
Working Days Charged519
Percent Time Used142
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150703
Totals273804.2418502.38342612.0599.9

CountyTOM GREEN
HighwayUS0067
FromPICNIC AREA MAINTENANCE AND SPECIAL LAND
ToPICNIC AREA MAINTENANCE AND SPECIAL LAND
CSJ6291-66-001
Proj IDSUP - 629166001
Work TypePICNIC AREA MAINTENANCE & LANDSC
 
0.001255246.36162739.4963.7
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days730
Addl Days Granted0
Working Days Charged519
Percent Time Used71
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6291-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150704
Totals255246.3610060.96162739.4963.7

CountyREAGAN
HighwayUS0067
FromSTATE USE JANITORIAL
ToBIG LAKE MAINTENANCE
CSJ6292-02-001
Proj IDSUP - 629202001
Work TypeSTATE USE JANITORIAL
 
0.00137306.8013996.8037.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged15
Percent Time Used1
Contractor(s)
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150706
Totals37306.800.0013996.8037.5

CountyCONCHO
HighwayUS0087
FromEDEN MAINTENANCE
ToEDEN MAINTENANCE
CSJ6292-03-001
Proj IDSUP - 629203001
Work TypeSTATE USE JANITORIAL
 
0.00135776.8013996.8039.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged16
Percent Time Used1
Contractor(s)
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150707
Totals35776.800.0013996.8039.1

CountyKIMBLE
HighwayUS0083
FromJUNCTION MNT OFFICE
ToJUNCTION AREA OFFICE
CSJ6292-04-001
Proj IDSUP - 629204001
Work TypeJANITORIAL STATE USE SERVICES
 
0.00137907.1614861.8639.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged16
Percent Time Used1
Contractor(s)
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150708
Totals37907.160.0014861.8639.2

CountyCROCKETT
HighwaySH0163
FromOZONA MAINTENANCE
ToOZONA MAINTENANCE
CSJ6292-05-001
Proj IDSUP - 629205001
Work TypeSTATE USE JANITORIAL SERVICES
 
0.00137117.6813996.8037.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged15
Percent Time Used1
Contractor(s)
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-05-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150709
Totals37117.680.0013996.8037.7

CountyTOM GREEN
HighwaySH0208
FromSAN ANGELO AREA OFFICE
ToSAN ANGELO MAINTENANCE OFFICE
CSJ6292-06-001
Proj IDSUP - 629206001
Work TypeSTATE USE JANITIORAL SERVICIES
 
0.00188678.8038494.8043.4
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged519
Percent Time Used47
Contractor(s)
MHMR SERVICES FOR THE CONCHO VALLEY
SUBCONTRACTOR(S) FOR CCSJ: 6292-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150710
Totals88678.802264.4038494.8043.4

CountySUTTON
HighwayUS0277
FromSONORA MAINT OFFICE
ToSONORA MAINT OFFICE
CSJ6292-07-001
Proj IDSUP - 629207001
Work TypeSTATE USE JANITORIAL
 
0.00141300.5214052.7034.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged13
Percent Time Used1
Contractor(s)
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150711
Totals41300.520.0014052.7034.0

CountySTERLING
HighwayUS0087
FromSTERLING CITY MAINT OFFICE
ToSTERLING CITY MAINT OFFICE
CSJ6292-08-001
Proj IDSUP - 629208001
Work TypeJANITORIAL SERVICES STATE USE
 
0.00134647.3014366.5541.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged13
Percent Time Used1
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150712
Totals34647.300.0014366.5541.4

CountyCOKE
HighwaySH0158
FromROBERT LEE
ToROBERT LEE
CSJ6292-09-001
Proj IDSUP - 629209001
Work TypeSTATE USE JANITORIAL SERVICES
 
0.00135082.1814416.5341.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged13
Percent Time Used1
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150713
Totals35082.180.0014416.5341.0

CountyEDWARDS
HighwayUS0377
FromROCKSPRINGS MAINT
ToROCKSPRINGS MAINT
CSJ6292-10-001
Proj IDSUP - 629210001
Work TypeJANITORIAL STATE USE
 
0.00125226.0410386.6541.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged13
Percent Time Used1
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-10-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150714
Totals25226.040.0010386.6541.1

CountyRUNNELS
HighwayUS0067
FromBALLINGER MAINT OFF
ToBALLINGER MAINT OFF
CSJ6292-11-001
Proj IDSUP - 629211001
Work TypeJANITORIAL SERVICES - STATE USE
 
0.00135146.4414392.0540.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged43
Percent Time Used3
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150715
Totals35146.440.0014392.0540.9

CountyMENARD
HighwayUS0083
FromMENARD MAINT
ToMENARD MAINT
CSJ6292-13-001
Proj IDSUP - 629213001
Work TypeJANTIORIAL STATE USE - MENARD
 
0.00134552.8013996.8040.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged15
Percent Time Used1
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150717
Totals34552.800.0013996.8040.5

CountyTOM GREEN
HighwayUS0067
FromTOM GREEN URBAN
ToTOM GREEN RURAL
CSJ6293-18-001
Proj IDSUP - 629318001
Work TypeLITTER PICKUP TOM GREEN URBAN-RURAL
 
0.001184632.50212753.4599.9
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days365
Addl Days Granted365
Working Days Charged519
Percent Time Used71
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150718
Totals184632.5019943.30212753.4599.9

CountyTOM GREEN
HighwayRM0584
FromSAN ANGELO DISTRICT SHOP
ToSAN ANGELO DISTRICT SHOP
CSJ6294-04-001
Proj IDSUP - 629404001
Work TypeDAY LABOR - OIL CHANGE AND CAR WASH
 
0.00141871.8452781.2299.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days250
Addl Days Granted251
Working Days Charged15
Percent Time Used2
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6294-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08150719
Totals41871.840.0052781.2299.9

CountyKIMBLE
HighwayIH0010
FromVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
ToVARIOUS LOCATIONS IN SAN ANGELO DISTRICT
CSJ6294-63-001
Proj IDRMC - 629463001
Work TypeMETAL BEAM GUARDFENCE
 
0.001302880.00440187.0099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted180
Working Days Charged124
Percent Time Used34
Contractor(s)
D & D ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6294-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150701
Totals302880.000.00440187.0099.9

CountyTOM GREEN
HighwayRM0584
FromSAN ANGELO DISTRICT CAMPUS
ToSAN ANGELO DISTRICT CAMPUS
CSJ6296-97-001
Proj IDSUP - 629697001
Work TypeJANITORIAL STATE USE SAN ANGELO
 
0.001142163.2853386.6837.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-01-15
Work Began00-00-00
Work Completed
Time Computed09-01-15
Contract Working Days1,095
Addl Days Granted0
Working Days Charged13
Percent Time Used1
Contractor(s)
TIBH INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150702
Totals142163.280.0053386.6837.5

CountySTERLING
HighwayUS0087
FromVARIOUS ROADS STERLING GLASSCOCK
ToVARIOUS ROADS STERLING CLASSCOCK
CSJ6305-29-001
Proj IDRMC - 630529001
Work TypeRIGHT OF WAY MOWING STERLING
 
0.001161436.5480446.9749.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-09-16
Work Began00-00-00
Work Completed
Time Computed11-21-16
Contract Working Days65
Addl Days Granted0
Working Days Charged14
Percent Time Used21
Contractor(s)
SQUARE G, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07160701
Totals161436.540.0080446.9749.8