Item No Description Units March 31, 2013 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
500 2001 MOBILIZATION LS 1.000 30,000.00000 15.000 28,962.40000 15
502 2001 BARRICADES, SIGNS AND TRAFFIC HANDLING MO 3.000 1,500.00000 54.000 2,150.39630 15
506 2016 CONSTRUCTION EXITS (INSTALL) (TY 1) SY     78.000 16.57000 1
506 2019 CONSTRUCTION EXITS (REMOVE) SY     78.000 4.88000 1
506 2024 BACKHOE WORK (EROSION & SEDM CONT) HR     10.000 107.06000 1
506 2034 TEMPORARY SEDIMENT CONTROL FENCE LF     500.000 3.71000 1
512 2010 PORT CTB (DES SOURCE) (SAFETY SH) (TY 1) LF     240.000 45.00000 1
512 2011 PORT CTB (DES SOURCE) (SAFETY SH) (TY 2) LF     90.000 100.00000 1
512 2019 PORT CTB (MOVE) (SAFETY SH) (TY 1) LF     300.000 15.00000 1
512 2020 PORT CTB (MOVE) (SAFETY SH) (TY 2) LF     90.000 90.00000 1
512 2028 PORT CTB (STKPL) (SAFETY SH) (TY 1) LF     540.000 33.88889 2
512 2029 PORT CTB (STKPL) (SAFETY SH) (TY 2) LF     90.000 100.00000 1
512 2054 PORT CTB (DES SOURCE) (F - SHAPE) (TY 4) LF     750.000 20.00000 1
512 2055 PORT CTB (MOVE) (F - SHAPE) (TY 4) LF     750.000 12.00000 1
512 2056 PORT CTB (STOCKPILE) (F - SHAPE) (TY 4) LF     750.000 20.00000 1
529 2010 CONC CURB AND GUTTER (TY II) (REINF) LF 48.000 45.00000 48.000 45.00000 1
531 2024 CONC SIDEWALK (5") SY 873.000 60.00000 873.000 60.00000 1
531 2054 CURB RAMPS SY 23.900 200.00000 23.900 200.00000 1
540 2002 MTL W - BEAM GD FEN (STEEL POST) LF     1,329.000 22.11889 2
540 2005 TERMINAL ANCHOR SECTION EA     4.000 250.00000 1
540 2011 MTL BEAM GD FEN TRANS (THRIE - BEAM) EA     9.000 1,750.00000 1
542 2001 REMOVING METAL BEAM GUARD FENCE LF     1,413.000 0.98461 2
542 2002 REMOVING TERMINAL ANCHOR SECTION EA     8.000 75.50000 2
542 2003 RM MTL BM GD FEN TRANS (THRIE - BEAM) EA     1.000 100.00000 1
542 2004 REMOVING MTL BM GD FEN TRANS (TL2) LF     100.000 1.50000 1
544 2002 GUARDRAIL END TREATMENT (MOVE & RESET) EA     1.000 1,100.00000 1
544 2013 GDRAIL END TRT (INSTALL) (HBA POST) EA     9.000 2,322.22222 2
545 2001 CRASH CUSH ATTEN (INSTL) EA     2.000 750.00000 1
545 2002 CRASH CUSH ATTEN (MOVE & RESET) EA     2.000 700.00000 1
545 2003 CRASH CUSH ATTEN (REMOVE) EA     2.000 750.00000 1
545 2046 CRASH CUSH ATTEN (INSTAL) (ABSORB 350) EA     1.000 3,500.00000 1
545 2048 CRASH CUSH ATTEN (REMOVE) (ABSORB 350) EA     1.000 2,500.00000 1
545 2049 CRASH CUSH ATTEN (INSTL) (WORK ZONE) EA     2.000 1,300.00000 1
545 2050 CRASH CUSH ATTEN (MOV & RESET) (WORK ZONE) EA     3.000 750.00000 1
545 2051 CRASH CUSH ATTEN (REMOVE) (WORK ZONE) EA     3.000 500.00000 1