AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - PHARR DISTRICT

Last Update: Friday, April 29, 2016
ITEMS 1003 6001 TO 1011 6001
Items Items Bid Code Range
0100 - 0193
0204 - 0292
0305 - 0360
0400 - 0497
0500 - 0560
0610 - 0688
0730 - 0784
1003 - 1011
4014 - 4035
5001 - 5038
6000 - 6162
7041 - 7041
1003 6001 - 1011 6001
Item No Description Units April 30, 2016 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
1003 6001 TRANSPLANT PLANT MATERIAL EA     159.000 833.39283 2
1003 6002 TRANSPLANT PLANT MATERIAL (TYPE I) EA     34.000 739.50000 1
1007 6001 IRRIGATION GATE (18") EA     2.000 6,631.00000 1
1007 6004 IRRIGATION WELL (24") EA     2.000 8,671.00000 1
1007 6005 IRRIGATION WELL (30") EA     3.000 6,650.00000 1
1007 6006 IRRIGATION GATE (24") EA     12.000 9,394.00000 2
1007 6007 IRRIGATION VALVE (12") EA     12.000 1,530.50000 1
1007 6008 IRRIGATION WELL (48") EA     11.000 19,715.45455 2
1007 6009 IRRIGATION WELL (36") EA     3.000 9,500.00000 1
1008 6001 PRSSR IRRIG PVC PIPE (18") LF     2,346.000 65.58056 3
1008 6002 PRSSR IRRIG PVC PIPE (24") LF     6,712.000 85.26117 3
1008 6003 PRSSR IRRIG PVC PIPE (12") LF     134.000 85.00000 1
1008 6004 PRESSURE IRRIGATION PVC PIPE (10") LF     462.000 46.00000 1
1008 6005 PRSSR IRRIG PVC PIPE (30") LF     104.000 90.00000 1
1011 6001 PRSSR IRRIG DI PIPE (PC 250) (42") LF     49.000 300.00000 1