Monthly Local Let Maintenance Report For Odessa District As Of Aug 16, 2016 Page 4 Of 7

Last Update: Tuesday, August 16, 2016
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5 | page 6 | page 7

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyREEVES
Highway IH0010
From VARIOUS
To VARIOUS
CSJ 6282-37-001
Proj ID RMC - 628237001
Work Type ROADSIDE MOWING
 
0.001 99090.00 0.00 93162.00 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-03-15
Work Began 06-03-15
Work Completed 04-30-16
Time Computed 06-10-15
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 36
Percent Time Used 75
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 6282-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01150605
Totals 99090.00 0.00 93162.00 100.0

CountyPECOS
Highway IH0010
From VARIOUS
To VARIOUS
CSJ 6282-38-001
Proj ID RMC - 628238001
Work Type ROADSIDE MOWING
 
0.001 132552.00 11426.00 66548.00 68.4
Work Order 05-13-15
Work Began 07-21-15
Work Completed  
Time Computed 07-01-15
Contract Working Days 62
Addl Days Granted 0
Working Days Charged 62
Percent Time Used 100
Contractor(s)
MIJELUM
SUBCONTRACTOR(S) FOR CCSJ: 6282-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01150606
Totals 132552.00 11426.00 66548.00 68.4

CountyREEVES
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6282-66-001
Proj ID RMC - 628266001
Work Type MISCELLANEOUS CONCRETE WORK
 
0.001 240286.50 0.00 238796.50 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-04-15
Work Began 06-08-15
Work Completed 09-14-15
Time Computed 06-08-15
Contract Working Days 40
Addl Days Granted 0
Working Days Charged 51
Percent Time Used 127
Contractor(s)
MARIL ENTERPRISES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6282-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150602
Totals 240286.50 0.00 238796.50 100.0

CountyMIDLAND
Highway FM0307
From COUNTY RD 1130
To COUNTY RD 1130
CSJ 6282-87-001
Proj ID RMC - 628287001
Work Type INSTALLATION OF TRAFFIC SIGNALS
 
0.001 215258.55 0.00 223680.30 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-04-15
Work Began 03-07-16
Work Completed 05-10-16
Time Computed 06-04-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 19
Percent Time Used 31
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 6282-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05150601
Totals 215258.55 0.00 223680.30 100.0

CountyMARTIN
Highway BI0020
From VARIOUS
To VARIOUS
CSJ 6282-89-001
Proj ID RMC - 628289001
Work Type INSTALLATION OF FLASHING BEACONS AND PED
 
0.001 227438.43 10823.62 242877.57 100.0
Work Order 10-30-15
Work Began 01-13-16
Work Completed 08-02-16
Time Computed 01-28-16
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 48
Percent Time Used 80
Contractor(s)
WILLIS ELECTRIC CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 6282-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05150603
Totals 227438.43 10823.62 242877.57 100.0

CountyWARD
Highway SH0018
From MONAHANS MAINTENANCE OFFICE
To MONAHANS MAINTENANCE OFFICE
CSJ 6283-74-001
Proj ID SUP - 628374001
Work Type JANITORIAL AND GROUNDS MAINTENANCE
 
0.001 23276.18 0.00 12668.34 54.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-15
Work Began 03-01-15
Work Completed  
Time Computed 03-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 519
Percent Time Used 70
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6283-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02150631
Totals 23276.18 0.00 12668.34 54.4

CountyECTOR
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6283-79-001
Proj ID SUP - 628379001
Work Type LITTER PICKUP
 
0.001 154395.74 0.00 270045.27 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-01-15
Work Began 02-01-15
Work Completed 01-31-16
Time Computed 02-01-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 363
Percent Time Used 99
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6283-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01150651
Totals 154395.74 0.00 270045.27 100.0

CountyECTOR
Highway BI0020E
From ODESSA DISTRICT COMPLEX
To ODESSA DISTRICT COMPLEX
CSJ 6284-29-001
Proj ID SUP - 628429001
Work Type GROUNDS MAINTENANCE
 
0.001 41890.00 1535.00 15110.00 36.0
Work Order 02-23-15
Work Began 03-10-15
Work Completed  
Time Computed 03-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 519
Percent Time Used 70
Contractor(s)
TIBH INDUSTRIES, INC.
PERMIAN BASIN COMMUNITY CENTERS
SUBCONTRACTOR(S) FOR CCSJ: 6284-29-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02150632
Totals 41890.00 1535.00 15110.00 36.0

CountyREEVES
Highway IH0020
From RM 22
To RM 23
CSJ 6284-49-001
Proj ID RMC - 628449001
Work Type PICNIC AREA MAINTENANCE
 
0.001 63740.00 2720.00 36040.00 56.5
Work Order 06-12-15
Work Began 06-15-15
Work Completed  
Time Computed 06-15-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 412
Percent Time Used 56
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6284-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05150602
Totals 63740.00 2720.00 36040.00 56.5

CountyECTOR
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6284-51-001
Proj ID SUP - 628451001
Work Type LANDSCAPE MAINTENANCE
 
0.001 92724.64 5226.04 69116.48 74.5
Work Order 03-31-15
Work Began 04-06-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 488
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
PERMIAN BASIN COMMUNITY CENTERS
SUBCONTRACTOR(S) FOR CCSJ: 6284-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150631
Totals 92724.64 5226.04 69116.48 74.5

CountyREEVES
Highway BI0020B
From PECOS AREA/MAINTENANCE OFFICE
To PECOS AREA/MAINTENANCE OFFICE
CSJ 6285-37-001
Proj ID SUP - 628537001
Work Type JANITORIAL AND GROUNDS MAINTENANCE
 
0.001 26718.30 774.21 11844.07 44.3
Work Order 04-01-15
Work Began 04-02-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 488
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150632
Totals 26718.30 774.21 11844.07 44.3

CountyREEVES
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6285-59-001
Proj ID SUP - 628559001
Work Type LITTER PICKUP
 
0.001 115881.77 1336.81 52963.90 45.7
Work Order 04-01-15
Work Began 04-06-15
Work Completed  
Time Computed 04-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 487
Percent Time Used 66
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6285-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03150633
Totals 115881.77 1336.81 52963.90 45.7

CountyMIDLAND
Highway BI0020E
From VARIOUS
To VARIOUS
CSJ 6286-89-001
Proj ID SUP - 628689001
Work Type LANDSCAPE MAINTENANCE
 
0.001 137428.68 0.00 123676.34 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-18-15
Work Began 06-01-15
Work Completed 05-31-16
Time Computed 06-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 49
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6286-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05150651
Totals 137428.68 0.00 123676.34 100.0

CountyMIDLAND
Highway SL0250
From VARIOUS
To VARIOUS
CSJ 6286-92-001
Proj ID SUP - 628692001
Work Type LANDSCAPE MAINTENANCE
 
0.001 247983.40 0.00 198783.99 100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-18-15
Work Began 06-01-15
Work Completed 05-27-16
Time Computed 06-01-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 361
Percent Time Used 98
Contractor(s)
TIBH INDUSTRIES, INC.
RELIEF ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6286-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05150652
Totals 247983.40 0.00 198783.99 100.0

CountyMIDLAND
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6287-85-001
Proj ID RMC - 628785001
Work Type EMERGENCY CABLE MEDIAN BARRIER REPAIR
 
0.001 85200.00 0.00 154878.00 100.0
Work Order 08-24-15
Work Began 09-08-15
Work Completed 08-11-16
Time Computed 09-01-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 345
Percent Time Used 94
Contractor(s)
HJC FARMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06150601
Totals 85200.00 0.00 154878.00 100.0

CountyMIDLAND
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6287-86-001
Proj ID RMC - 628786001
Work Type EMERGENCY MBGF REPAIR
 
0.001 246082.00 65980.00 275060.00 100.0
Work Order 08-24-15
Work Began 09-09-15
Work Completed 08-03-16
Time Computed 09-01-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 337
Percent Time Used 92
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6287-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06150602
Totals 246082.00 65980.00 275060.00 100.0

CountyECTOR
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6287-88-001
Proj ID RMC - 628788001
Work Type EMERGENCY MBGF REPAIR
 
0.001 240755.00 7908.00 128506.00 100.0
Work Order 07-31-15
Work Began 09-01-15
Work Completed 08-08-16
Time Computed 08-01-15
Contract Working Days 366
Addl Days Granted 0
Working Days Charged 366
Percent Time Used 100
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6287-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06150603
Totals 240755.00 7908.00 128506.00 100.0

CountyWINKLER
Highway SH0302
From VARIOUS
To VARIOUS
CSJ 6288-83-001
Proj ID SUP - 628883001
Work Type JANITORIAL AND GROUNDS
 
0.001 19218.50 702.55 7951.53 41.3
Work Order 07-01-15
Work Began 07-01-15
Work Completed  
Time Computed 07-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 397
Percent Time Used 54
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-83-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06150631
Totals 19218.50 702.55 7951.53 41.3

CountyCRANE
Highway US0385
From VARIOUS
To VARIOUS
CSJ 6288-88-001
Proj ID SUP - 628888001
Work Type LITTER PICKUP
 
0.001 64904.00 0.00 27702.00 42.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-01-15
Work Began 09-08-15
Work Completed  
Time Computed 09-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 335
Percent Time Used 45
Contractor(s)
TIBH INDUSTRIES, INC.
BOOTSTRAPS OCCUPATIONAL SERVICES INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6288-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05150632
Totals 64904.00 0.00 27702.00 42.6

CountyECTOR
Highway IH0020
From VARIOUS
To VARIOUS
CSJ 6289-86-001
Proj ID SUP - 628986001
Work Type JANITORIAL
 
0.001 99407.20 4777.80 48788.80 49.0
Work Order 08-01-15
Work Began 08-03-15
Work Completed  
Time Computed 08-01-15
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 366
Percent Time Used 50
Contractor(s)
TIBH INDUSTRIES, INC.
PERMIAN BASIN COMMUNITY CENTERS
SUBCONTRACTOR(S) FOR CCSJ: 6289-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07150631
Totals 99407.20 4777.80 48788.80 49.0