Monthly Local Let Maintenance Report For Odessa District As Of Nov 22, 2017 Page 1 Of 4

Last Update: Wednesday, November 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyECTOR
HighwayLP0338
FromODESSA MAINTENANCE OFFICE
ToODESSA MAINTENANCE OFFICE
CSJ6173-64-001
Proj IDSUP - 617364001
Work TypeGROUNDS MAINTENANCE
 
0.0017717.506615.0085.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-26-08
Work Began03-11-08
Work Completed
Time Computed03-01-08
Contract Working Days730
Addl Days Granted0
Working Days Charged730
Percent Time Used100
Contractor(s)
TIBH INDUSTRIES, INC.
PERMIAN BASIN COMMUNITY CENTERS
SUBCONTRACTOR(S) FOR CCSJ: 6173-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01080631
Totals7717.500.006615.0085.7

CountyMARTIN
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6197-11-001
Proj IDRMC - 619711001
Work TypeROADSIDE MOWING
 
234.30083691.9668030.0781.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-03-10
Work Began06-09-10
Work Completed
Time Computed06-09-10
Contract Working Days56
Addl Days Granted0
Working Days Charged19
Percent Time Used33
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6197-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01100606
Totals83691.960.0068030.0781.2

CountyWINKLER
HighwaySH0302
FromVARIOUS
ToVARIOUS
CSJ6234-97-001
Proj IDRMC - 623497001
Work TypeROADSIDE MOWING
 
0.00146995.260.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days26
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
KRAFT WERKS
SUBCONTRACTOR(S) FOR CCSJ: 6234-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05120601
Totals46995.260.000.000.0

CountyTERRELL
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6293-72-001
Proj IDRMC - 629372001
Work TypePICNIC AREA MAINTENANCE
 
0.00163840.0055460.0086.8
Work Order01-25-16
Work Began02-01-16
Work Completed
Time Computed02-01-16
Contract Working Days731
Addl Days Granted0
Working Days Charged639
Percent Time Used87
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6293-72-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10150605
Totals63840.002740.0055460.0086.8

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6293-79-001
Proj IDRMC - 629379001
Work TypeROADSIDE MOWING
 
0.001262431.00183768.0070.0
Work Order06-09-16
Work Began06-28-16
Work Completed
Time Computed07-07-16
Contract Working Days108
Addl Days Granted0
Working Days Charged46
Percent Time Used42
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6293-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160601
Totals262431.000.00183768.0070.0

CountyREEVES
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6294-27-001
Proj IDRMC - 629427001
Work TypeROADSIDE MOWING
 
0.001211200.00155700.0073.7
Work Order06-06-16
Work Began06-13-16
Work Completed
Time Computed06-15-16
Contract Working Days70
Addl Days Granted0
Working Days Charged35
Percent Time Used50
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6294-27-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160602
Totals211200.000.00155700.0073.7

CountyTERRELL
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6294-53-001
Proj IDRMC - 629453001
Work TypeROADSIDE MOWING
 
0.001150016.00126102.0085.2
Work Order06-13-16
Work Began07-19-16
Work Completed
Time Computed07-18-16
Contract Working Days39
Addl Days Granted0
Working Days Charged24
Percent Time Used61
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6294-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160603
Totals150016.000.00126102.0085.2

CountyANDREWS
HighwayUS0385
FromVARIOUS
ToVARIOUS
CSJ6295-04-001
Proj IDRMC - 629504001
Work TypeROADSIDE MOWING
 
0.001129480.0096280.00100.0
Work Order05-18-16
Work Began06-15-16
Work Completed11-10-17
Time Computed06-13-16
Contract Working Days54
Addl Days Granted0
Working Days Charged54
Percent Time Used100
Contractor(s)
MARKO CONTRACTING & MAINTENANCE LLC
SUBCONTRACTOR(S) FOR CCSJ: 6295-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160604
Totals129480.0014700.0096280.00100.0

CountyECTOR
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6295-24-001
Proj IDRMC - 629524001
Work TypeROADSIDE MOWING
 
0.001266703.00289996.0099.9
Work Order03-07-16
Work Began05-04-16
Work Completed
Time Computed03-16-16
Contract Working Days78
Addl Days Granted0
Working Days Charged72
Percent Time Used92
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6295-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160606
Totals266703.0033031.50289996.0099.9

CountyMARTIN
HighwaySH0137
FromSTANTON MAINTENANCE OFFICE
ToSTANTON MAINTENANCE OFFICE
CSJ6296-58-001
Proj IDSUP - 629658001
Work TypeJANITORIAL MAINTENANCE
 
0.00113380.7212823.1995.8
Work Order12-01-15
Work Began12-01-15
Work Completed
Time Computed12-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged701
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11150651
Totals13380.72557.5312823.1995.8

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6296-59-001
Proj IDSUP - 629659001
Work TypePICNIC AREA MAINTENANCE
 
0.00191170.0081655.0089.5
Work Order12-15-15
Work Began01-01-16
Work Completed
Time Computed01-01-16
Contract Working Days731
Addl Days Granted0
Working Days Charged670
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
PERMIAN BASIN COMMUNITY CENTERS
SUBCONTRACTOR(S) FOR CCSJ: 6296-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12150631
Totals91170.003955.0081655.0089.5

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6296-84-001
Proj IDRMC - 629684001
Work TypeLANDSCAPE MAINTENANCE
 
0.001104567.2072371.2569.2
Work Order02-11-16
Work Began06-01-16
Work Completed
Time Computed06-01-16
Contract Working Days731
Addl Days Granted0
Working Days Charged518
Percent Time Used70
Contractor(s)
CM COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6296-84-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160607
Totals104567.205319.6072371.2569.2

CountyMIDLAND
HighwayBI0020E
FromVARIOUS
ToVARIOUS
CSJ6297-51-001
Proj IDRMC - 629751001
Work TypePUMP STATION MAINTENANCE
 
0.001162164.00139126.0085.7
Work Order02-26-16
Work Began08-22-16
Work Completed
Time Computed04-01-16
Contract Working Days731
Addl Days Granted0
Working Days Charged579
Percent Time Used79
Contractor(s)
CLEAN SERVE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160610
Totals162164.000.00139126.0085.7

CountyWARD
HighwayBI0020D
FromVARIOUS
ToVARIOUS
CSJ6297-63-001
Proj IDRMC - 629763001
Work TypeRETROREFLECTIVITY MEASUREMENT
 
0.00121323.8721323.88100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-16-16
Work Began05-16-16
Work Completed01-31-17
Time Computed05-16-16
Contract Working Days60
Addl Days Granted0
Working Days Charged59
Percent Time Used98
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160602
Totals21323.870.0021323.88100.0

CountyPECOS
HighwayUS0190
FromVARIOUS
ToVARIOUS
CSJ6299-60-001
Proj IDSUP - 629960001
Work TypePICNIC AREA MAINTENANCE
 
0.00140240.0031554.5078.4
Work Order03-29-16
Work Began04-01-16
Work Completed
Time Computed04-01-16
Contract Working Days731
Addl Days Granted0
Working Days Charged579
Percent Time Used79
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-60-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02160631
Totals40240.001710.0031554.5078.4

CountyWARD
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6299-63-001
Proj IDRMC - 629963001
Work TypeROADSIDE MOWING
 
0.001285440.00195488.0068.4
Work Order05-23-16
Work Began05-24-16
Work Completed
Time Computed06-01-16
Contract Working Days731
Addl Days Granted0
Working Days Charged526
Percent Time Used71
Contractor(s)
L&L COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6299-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03160603
Totals285440.000.00195488.0068.4

CountyWARD
HighwaySH0018
FromVARIOUS
ToVARIOUS
CSJ6299-79-001
Proj IDSUP - 629979001
Work TypePICNIC AREA MAINTENANCE
 
0.00115134.4012123.4880.1
Work Order03-30-16
Work Began04-01-16
Work Completed
Time Computed04-01-16
Contract Working Days731
Addl Days Granted0
Working Days Charged579
Percent Time Used79
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160632
Totals15134.40714.9412123.4880.1

CountyANDREWS
HighwayUS0385
FromANDREWS MAINTENANCE_OFFICE
ToANDREWS MAINTENANCE OFFICE
CSJ6300-28-001
Proj IDSUP - 630028001
Work TypeJANITORIAL MAINTENANCE
 
0.00115088.0013252.0087.8
Work Order01-25-16
Work Began02-02-16
Work Completed
Time Computed02-02-16
Contract Working Days731
Addl Days Granted0
Working Days Charged639
Percent Time Used87
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6300-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01160633
Totals15088.00812.0013252.0087.8

CountyMIDLAND
HighwayIH0020
FromVARIOUS
ToVARIOUS
CSJ6302-12-001
Proj IDRMC - 630212001
Work TypeCALLOUT TRAFFIC CONTROL SERVICES
 
0.001262850.00853187.0099.9
Work Order07-05-16
Work Began07-06-16
Work Completed
Time Computed07-06-16
Contract Working Days366
Addl Days Granted365
Working Days Charged488
Percent Time Used66
Contractor(s)
BARRICADES UNLIMITED
SUBCONTRACTOR(S) FOR CCSJ: 6302-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06160601
Totals262850.00100079.75853187.0099.9

CountyPECOS
HighwayIH0010
FromVARIOUS
ToVARIOUS
CSJ6302-25-001
Proj IDSUP - 630225001
Work TypeLITTER PICKUP
 
0.001102582.1250949.9449.6
Work Order01-23-17
Work Began09-06-16
Work Completed
Time Computed01-23-17
Contract Working Days731
Addl Days Granted0
Working Days Charged426
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
FRESH START OF MONROE INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-25-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04160631
Totals102582.124443.5850949.9449.6

page 1 | page 2 | page 3 | page 4