Monthly Local Let Maintenance Report For Laredo District As Of May 15, 2013 Page 3 Of 3

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyMAVERICK
Highway FM1021
From 5.3 MI S OF FM 2644, NE BRANCH OF INDIO
To 0.5 MI S OF FM 2366, CUEVAS CREEK
CSJ 6253-28-001
Proj ID BPM - 625328001
Work Type BRIDGE CONCRETE STRUCTURAL REPAIR
 
0.033 93045.00 3980.00 130607.10 99.9
Work Order 02-22-13
Work Began 02-23-13
Work Completed  
Time Computed 02-23-13
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 80
Contractor(s)
L.C. JORDAN & SON
SUBCONTRACTOR(S) FOR CCSJ: 6253-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01132203
Totals 93045.00 3980.00 130607.10 99.9

CountyZAVALA
Highway FM1025
From 0.82 MI EAST OF US 83
To 0.87 MI EAST OF US 83
CSJ 6253-30-001
Proj ID BPM - 625330001
Work Type REHABILITATION OF A BRIDGE FACILITY
 
0.051 115330.24 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-01-13
Work Began 05-06-13
Work Completed  
Time Computed 05-06-13
Contract Working Days 26
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6253-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03132201
Totals 115330.24 0.00 0.00 0.0

CountyWEBB
Highway SH0255T
From SH 255T
To SH 255T
CSJ 6253-31-001
Proj ID SUP - 625331001
Work Type LANDSCAPING MAINTENANCE SERVICE
 
0.001 7644.90 0.00 764.49 10.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 12-28-12
Work Began 01-01-13
Work Completed  
Time Computed 01-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 90
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12122232
Totals 7644.90 0.00 764.49 10.0

CountyLASALLE
Highway IH0035
From IH 35
To SH 97, ETC.
CSJ 6253-32-001
Proj ID SUP - 625332001
Work Type ROADSIDE MOWING
 
194.010 119232.00 0.00 0.00 0.0
Work Order 04-01-13
Work Began 04-01-13
Work Completed  
Time Computed 04-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-32-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03132231
Totals 119232.00 0.00 0.00 0.0

CountyKINNEY
Highway US0090
From US 90
To US 90
CSJ 6253-33-001
Proj ID SUP - 625333001
Work Type PICNIC AREA MAINTENANCE
 
0.001 83382.16 2827.15 12439.46 14.9
Work Order 12-28-12
Work Began 01-01-13
Work Completed  
Time Computed 01-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-33-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12122233
Totals 83382.16 2827.15 12439.46 14.9

CountyWEBB
Highway IH0035
From TIC
To TIC
CSJ 6253-34-001
Proj ID SUP - 625334001
Work Type LANDSCAPING / JANITORIAL / LITTER PICKUP MAI
 
0.001 129634.40 10619.28 41303.22 31.8
Work Order 12-28-12
Work Began 01-01-13
Work Completed  
Time Computed 01-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 120
Percent Time Used 32
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6253-34-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12122234
Totals 129634.40 10619.28 41303.22 31.8

CountyVAL VERDE
Highway US0277
From VARIOUS
To VARIOUS
CSJ 6253-35-001
Proj ID RMC - 625335001
Work Type INSTALL PVT. MARKINGS AND PVT. MARKERS
 
0.001 268978.90 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6253-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04132202
Totals 268978.90 0.00 0.00 0.0

CountyVAL VERDE
Highway US0090
From US 90
To US 277, ETC.
CSJ 6253-36-001
Proj ID SUP - 625336001
Work Type PICNIC AREA MAINTENANCE
 
0.001 58198.64 2044.60 4498.12 7.7
Work Order 02-13-13
Work Began 02-15-13
Work Completed  
Time Computed 02-15-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 75
Percent Time Used 10
Contractor(s)
TIBH INDUSTRIES, INC.
HILL COUNTRY COMMUNITY MHMR CENTER
SUBCONTRACTOR(S) FOR CCSJ: 6253-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01132231
Totals 58198.64 2044.60 4498.12 7.7

CountyWEBB
Highway IH0035
From UNIROYAL INTERSECTION
To LASALLE/FRIO COUNTY LINE
CSJ 6253-37-001
Proj ID RMC - 625337001
Work Type TIRE RUBBER DEBRIS REMOVAL ON ROADWAYS
 
150.000 118634.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ANTHONY SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6253-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05132201
Totals 118634.40 0.00 0.00 0.0

CountyWEBB
Highway IH0035
From IH 35
To FM 255T
CSJ 6253-38-001
Proj ID SUP - 625338001
Work Type ROADSIDE MOWING
 
292.600 147120.00 0.00 0.00 0.0
Work Order 04-01-13
Work Began 04-01-13
Work Completed  
Time Computed 04-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03132232
Totals 147120.00 0.00 0.00 0.0

CountyDUVAL
Highway SH0016
From SH 16
To SH 16
CSJ 6253-39-001
Proj ID SUP - 625339001
Work Type JANITORIAL SERVICES @ FREER MAINT. OFFIC
 
0.001 12866.40 1374.85 2294.55 17.8
Work Order 01-31-13
Work Began 02-01-13
Work Completed  
Time Computed 02-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01132232
Totals 12866.40 1374.85 2294.55 17.8

CountyMAVERICK
Highway US0277
From US 277
To US 277
CSJ 6253-40-001
Proj ID SUP - 625340001
Work Type JANITORIAL SERVICES FOR EAGLE PASS MAINT
 
0.001 12866.40 459.85 1379.55 10.7
Work Order 01-31-13
Work Began 02-01-13
Work Completed  
Time Computed 02-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 89
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01132233
Totals 12866.40 459.85 1379.55 10.7

CountyDUVAL
Highway US0059
From US 59
To FM 1329, ETC.
CSJ 6253-41-001
Proj ID SUP - 625341001
Work Type ROADSIDE MOWING
 
331.190 146236.08 0.00 0.00 0.0
Work Order 04-01-13
Work Began 04-01-13
Work Completed  
Time Computed 04-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
UPPER VALLEY HELPSOURCE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6253-41-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03132233
Totals 146236.08 0.00 0.00 0.0

CountyVAL VERDE
Highway US0090
From US 90
To US 90
CSJ 6256-00-001
Proj ID SUP - 625600001
Work Type JANITORIAL / GROUNDS / LANDSCAPING MAINTENAN
 
0.001 56598.48 4716.54 4716.54 8.3
Work Order 04-01-13
Work Began 04-01-13
Work Completed  
Time Computed 04-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6256-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02132231
Totals 56598.48 4716.54 4716.54 8.3

CountyZAVALA
Highway US0057
From US 57
To US 57
CSJ 6256-36-001
Proj ID SUP - 625636001
Work Type JANITORIAL MAINTENANCE - LA PRYOR MAINT.
 
0.001 11892.72 436.62 436.62 3.6
Work Order 03-29-13
Work Began 04-01-13
Work Completed  
Time Computed 04-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 4
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-36-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02132232
Totals 11892.72 436.62 436.62 3.6

CountyKINNEY
Highway US0090
From US 90
To US 90
CSJ 6256-38-001
Proj ID SUP - 625638001
Work Type JANITORIAL SERVICES FOR BRACKETTVILE MAI
 
0.001 8857.38 330.06 330.06 3.7
Work Order 03-29-13
Work Began 04-01-13
Work Completed  
Time Computed 04-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 4
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02132233
Totals 8857.38 330.06 330.06 3.7

CountyLASALLE
Highway FM0469
From FM 469
To FM 469
CSJ 6256-39-001
Proj ID SUP - 625639001
Work Type JANITORIAL MAINTENANCE - COTULLA MAINTEN
 
0.001 9312.60 347.82 347.82 3.7
Work Order 03-29-13
Work Began 04-01-13
Work Completed  
Time Computed 04-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 4
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02132234
Totals 9312.60 347.82 347.82 3.7

CountyDIMMIT
Highway US0083
From US 83
To US 83
CSJ 6256-40-001
Proj ID SUP - 625640001
Work Type JANITORIAL MAINTENANCE FOR CARRIZO SPRIN
 
0.001 12684.92 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-30-13
Work Began 05-01-13
Work Completed  
Time Computed 05-01-13
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6256-40-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02132235
Totals 12684.92 0.00 0.00 0.0

CountyWEBB
Highway IH0035
From IH 35
To US 83, ETC.
CSJ 6257-14-001
Proj ID SUP - 625714001
Work Type LITTER PICKUP MAINTENANCE
 
0.001 232405.66 19806.41 19806.41 8.5
Work Order 03-25-13
Work Began 04-01-13
Work Completed  
Time Computed 04-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 8
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-14-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03132234
Totals 232405.66 19806.41 19806.41 8.5

CountyWEBB
Highway LP0020
From LP 20
To LP 20
CSJ 6257-37-001
Proj ID SUP - 625737001
Work Type JANITORIAL MAINTENANCE SERVICES FOR LARE
 
0.001 145709.16 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-29-13
Work Began 04-01-13
Work Completed  
Time Computed 04-01-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6257-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03132235
Totals 145709.16 0.00 0.00 0.0