Monthly Local Let Maintenance Report For Laredo District As Of Nov 20, 2014 Page 3 Of 4

Last Update: Thursday, November 20, 2014
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWEBB
Highway IH0035
From IH 35
To US 59, ETC.
CSJ 6266-21-001
Proj ID SUP - 626621001
Work Type PICNIC AREA MAINTENANCE
 
0.001 36251.24 2148.51 32062.47 88.4
Work Order 10-15-13
Work Began 10-15-13
Work Completed  
Time Computed 10-15-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-21-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10132231
Totals 36251.24 2148.51 32062.47 88.4

CountyDUVAL
Highway US0059
From US 59
To SH 44, ETC.
CSJ 6266-23-001
Proj ID SUP - 626623001
Work Type PICNIC AREA MAINTENANCE
 
0.001 38349.48 1604.01 36407.63 94.9
Work Order 10-15-13
Work Began 10-15-13
Work Completed  
Time Computed 10-15-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 365
Percent Time Used 100
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6266-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10132232
Totals 38349.48 1604.01 36407.63 94.9

CountyLASALLE
Highway IH0035
From IH 35
To VARIOUS
CSJ 6268-15-001
Proj ID RMC - 626815001
Work Type CLEANING AND SWEEPING OF HIGHWAYS / LITTER
 
19.800 56805.48 0.00 12974.70 22.8
Work Order 05-16-14
Work Began 06-02-14
Work Completed  
Time Computed 06-02-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 152
Percent Time Used 41
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04142202
Totals 56805.48 0.00 12974.70 22.8

CountyWEBB
Highway IH0035
From IH 35
To VARIOUS
CSJ 6268-16-001
Proj ID SUP - 626816001
Work Type GUARDRAIL REPAIR
 
0.001 560700.00 29089.00 113324.89 20.2
Work Order 09-12-14
Work Began 09-15-14
Work Completed  
Time Computed 09-15-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 47
Percent Time Used 12
Contractor(s)
TIBH INDUSTRIES, INC.
RGR INDUSTRIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07142231
Totals 560700.00 29089.00 113324.89 20.2

CountyWEBB
Highway IH0035
From IH 35
To VARIOUS
CSJ 6268-64-001
Proj ID RMC - 626864001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
292.620 196095.60 29548.20 29548.20 15.0
Work Order 10-10-14
Work Began 10-16-14
Work Completed  
Time Computed 10-16-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 4
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6268-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09142201
Totals 196095.60 29548.20 29548.20 15.0

CountyVAL VERDE
Highway US0277
From VARIOUS
To VARIOUS
CSJ 6268-89-001
Proj ID RMC - 626889001
Work Type INSTALL PAVEMENT MRKGS AND PAVEMENT MRKS
 
0.001 268816.61 113721.52 332931.20 99.9
Work Order 07-23-14
Work Began 07-23-14
Work Completed  
Time Computed 07-23-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 61
Percent Time Used 16
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6268-89-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04142203
Totals 268816.61 113721.52 332931.20 99.9

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6269-73-001
Proj ID RMC - 626973001
Work Type INSTALL PAVEMENT MRKGS AND PAVEMENT MRKR
 
0.001 261912.51 54989.25 340417.76 99.9
Work Order 07-22-14
Work Began 07-22-14
Work Completed  
Time Computed 07-22-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 102
Percent Time Used 27
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04142204
Totals 261912.51 54989.25 340417.76 99.9

CountyWEBB
Highway IH0035
From VARIOUS
To .
CSJ 6269-76-001
Proj ID SUP - 626976001
Work Type JANITORIAL AND GROUNDS MAINTENANCE
 
0.001 80486.56 0.00 77762.16 96.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-01-14
Work Began 02-01-14
Work Completed  
Time Computed 02-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 212
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6269-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01142231
Totals 80486.56 0.00 77762.16 96.6

CountyLASALLE
Highway IH0035
From IH 35
To VARIOUS
CSJ 6269-77-001
Proj ID RMC - 626977001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
192.400 235474.53 0.00 51545.98 21.8
Work Order 06-26-14
Work Began 07-14-14
Work Completed  
Time Computed 07-14-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 110
Percent Time Used 15
Contractor(s)
COASTAL MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6269-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05142204
Totals 235474.53 0.00 51545.98 21.8

CountyMAVERICK
Highway US0277
From US 277
To VARIOUS
CSJ 6270-30-001
Proj ID RMC - 627030001
Work Type CLEANING, SWEEPING AND LITTER PICKUP
 
66.480 164236.00 0.00 21914.90 13.3
Work Order 07-18-14
Work Began 07-21-14
Work Completed  
Time Computed 07-21-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 123
Percent Time Used 33
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6270-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06142203
Totals 164236.00 0.00 21914.90 13.3

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6270-92-001
Proj ID RMC - 627092001
Work Type INSTALL RAISED MEDIAN, SIGNING & STRIPIN
 
0.001 298482.30 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILMAR CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6270-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05142201
Totals 298482.30 0.00 0.00 0.0

CountyVAL VERDE
Highway US0090
From VARIOUS
To .
CSJ 6271-94-001
Proj ID SUP - 627194001
Work Type JANITORIAL, GROUNDS, LANDSCAPING
 
0.001 23990.40 0.00 24774.40 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-01-14
Work Began 00-00-00
Work Completed  
Time Computed 04-01-14
Contract Working Days 153
Addl Days Granted 0
Working Days Charged 122
Percent Time Used 79
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6271-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03142231
Totals 23990.40 0.00 24774.40 99.9

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6272-30-001
Proj ID SUP - 627230001
Work Type LITTER PICKUP MAINTENANCE - WEBB / DIMMIT
 
0.001 241170.36 20065.14 142225.94 58.9
Work Order 03-31-14
Work Began 04-01-14
Work Completed  
Time Computed 04-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 214
Percent Time Used 58
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6272-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03142232
Totals 241170.36 20065.14 142225.94 58.9

CountyWEBB
Highway IH0035
From IH 35
To VARIOUS
CSJ 6272-63-001
Proj ID RMC - 627263001
Work Type TIRE RUBBER DEBRIS REMOVAL ON ROADWAYS
 
150.000 245263.68 13656.24 50844.96 20.7
Work Order 07-18-14
Work Began 08-01-14
Work Completed  
Time Computed 08-01-14
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 92
Percent Time Used 25
Contractor(s)
M & M STRIPING & POWER WASHING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-63-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05142206
Totals 245263.68 13656.24 50844.96 20.7

CountyDUVAL
Highway US0059
From US 59
To VARIOUS
CSJ 6272-72-001
Proj ID RMC - 627272001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
331.190 313224.53 0.00 31376.63 10.0
Work Order 07-21-14
Work Began 08-11-14
Work Completed  
Time Computed 08-11-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 11
Contractor(s)
COASTAL MAINTENANCE
SUBCONTRACTOR(S) FOR CCSJ: 6272-72-001
K-BAR SERVICES, INC. ( 26.77%)
Contract # 06142202
Totals 313224.53 0.00 31376.63 10.0

CountyZAVALA
Highway US0083
From VARIOUS
To VARIOUS
CSJ 6273-48-001
Proj ID RMC - 627348001
Work Type MOWING OF HIGHWAYS RIGHT - OF - WAY
 
264.000 255398.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6273-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07142201
Totals 255398.00 0.00 0.00 0.0

CountyWEBB
Highway IH0035
From VARIOUS
To VARIOUS
CSJ 6273-66-001
Proj ID RMC - 627366001
Work Type CLEANING AND CRACK SEALING OF HIGHWAYS
 
400.000 185400.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FYL ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6273-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08142201
Totals 185400.00 0.00 0.00 0.0

CountyMAVERICK
Highway US0277
From VARIOUS
To VARIOUS
CSJ 6273-94-001
Proj ID RMC - 627394001
Work Type CLEANING AND CRACK SEALING OF HIGHWAYS
 
400.000 177000.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 150
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FYL ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6273-94-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08142202
Totals 177000.00 0.00 0.00 0.0

CountyMAVERICK
Highway US0277
From US 277
To US 57, ETC.
CSJ 6275-06-001
Proj ID SUP - 627506001
Work Type PICNIC AREA MAINTENANCE
 
0.001 56309.20 2465.50 9225.80 16.3
Work Order 06-30-14
Work Began 07-01-14
Work Completed  
Time Computed 07-01-14
Contract Working Days 731
Addl Days Granted 0
Working Days Charged 123
Percent Time Used 16
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6275-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06142231
Totals 56309.20 2465.50 9225.80 16.3

CountyVAL VERDE
Highway US0090
From VARIOUS
To .
CSJ 6276-51-001
Proj ID SUP - 627651001
Work Type JANITORIAL, GROUNDS, LANDSCAPING
 
0.001 128326.70 5273.70 5273.70 4.1
Work Order 09-01-14
Work Began 00-00-00
Work Completed  
Time Computed 09-01-14
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 30
Percent Time Used 4
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6276-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08142231
Totals 128326.70 5273.70 5273.70 4.1