Monthly Local Let Maintenance Report For Laredo District As Of Feb 10, 2017 Page 3 Of 4

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWEBB
HighwaySL0020
FromSL 20
ToVARIOUS
CSJ6297-39-001
Proj IDRMC - 629739001
Work TypeLANDSCAPE MAINTENANCE
 
2.000228036.50145090.3563.6
Work Order04-27-16
Work Began04-28-16
Work Completed
Time Computed04-28-16
Contract Working Days365
Addl Days Granted0
Working Days Charged279
Percent Time Used76
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01162206
Totals228036.5034570.95145090.3563.6

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6300-77-001
Proj IDRMC - 630077001
Work TypeMAINTENANCE OF ILLUMINATION SYSTEMS
 
0.001120800.0025000.0020.6
Work Order07-29-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged184
Percent Time Used25
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07162201
Totals120800.005000.0025000.0020.6

CountyVAL VERDE
HighwayUS0090
FromUS 277
ToVARIOUS
CSJ6301-03-001
Proj IDRMC - 630103001
Work TypeUPGRADE OF EXISTING MBGF,
 
0.001312383.64162385.3651.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-08-16
Work Began08-15-16
Work Completed
Time Computed08-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged153
Percent Time Used41
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162203
Totals312383.640.00162385.3651.9

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6301-09-001
Proj IDRMC - 630109001
Work TypeINSTALL PVT. MARKINGS AND PVT.
 
0.001262806.470.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162202
Totals262806.470.000.000.0

CountyVAL VERDE
HighwaySS0239
FromDEL RIO TXDOT COMPLEX
ToDEL RIO TXDOT COMPLEX
CSJ6301-67-001
Proj IDRMC - 630167001
Work TypeLANDSCAPE MAINTENANCE
 
0.00111200.002450.0021.8
Work Order12-01-16
Work Began12-15-16
Work Completed
Time Computed12-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged48
Percent Time Used13
Contractor(s)
DELGADO'S CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6301-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162201
Totals11200.001125.002450.0021.8

CountyDUVAL
HighwayUS0059
FromUS 59
ToVARIOUS
CSJ6301-80-001
Proj IDRMC - 630180001
Work TypeMOWING OF HIGHWAYS RIGHT-OF-WAY
 
331.190174092.0098848.1956.7
Work Order09-21-16
Work Began09-29-16
Work Completed
Time Computed10-03-16
Contract Working Days365
Addl Days Granted0
Working Days Charged125
Percent Time Used34
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6301-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162201
Totals174092.000.0098848.1956.7

CountyKINNEY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6301-95-001
Proj IDBPM - 630195001
Work TypeREHABILITATION OF VARIOUS BRIDGE
 
0.03264877.0058915.0090.8
Work Order11-22-16
Work Began11-22-16
Work Completed
Time Computed11-22-16
Contract Working Days60
Addl Days Granted0
Working Days Charged45
Percent Time Used75
Contractor(s)
DELGADO'S CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6301-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09162201
Totals64877.0026790.0058915.0090.8

CountyMAVERICK
HighwayUS0057
FromVARIOUS
ToVARIOUS
CSJ6302-05-001
Proj IDBPM - 630205001
Work TypeREHABILITATION OF VARIOUS BRIDGE
 
0.304233287.00213033.0091.3
Work Order11-16-16
Work Began11-16-16
Work Completed
Time Computed11-16-16
Contract Working Days90
Addl Days Granted0
Working Days Charged44
Percent Time Used48
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-05-001
FLASHER EQUIPMENT COMPANY (4.01)
Contract #09162202
Totals233287.0046516.00213033.0091.3

CountyDUVAL
HighwaySH0016
FromVARIOUS
ToVARIOUS
CSJ6302-10-001
Proj IDBPM - 630210001
Work TypeREHABILITATION OF VARIOUS BRIDGE
 
0.281220518.0070079.0031.7
Work Order12-16-16
Work Began01-09-17
Work Completed
Time Computed01-09-17
Contract Working Days90
Addl Days Granted0
Working Days Charged14
Percent Time Used15
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-10-001
FLASHER EQUIPMENT COMPANY (5.10)
Contract #10162201
Totals220518.0070079.0070079.0031.7

CountyKINNEY
HighwayUS0090
FromUS 90
ToVARIOUS
CSJ6302-58-001
Proj IDRMC - 630258001
Work TypeUPGRADE OF EXISTING BRIDGE RAIL
 
0.001194084.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days60
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
DELGADO'S CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6302-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162202
Totals194084.000.000.000.0

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6302-74-001
Proj IDRMC - 630274001
Work TypeCLEANING & CRACK SEALING OF
 
500.000238003.00240858.0099.9
Work Order12-08-16
Work Began12-12-16
Work Completed
Time Computed12-12-16
Contract Working Days150
Addl Days Granted0
Working Days Charged51
Percent Time Used34
Contractor(s)
FYL ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6302-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162202
Totals238003.00240858.00240858.0099.9

CountyVAL VERDE
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6302-88-001
Proj IDRMC - 630288001
Work TypeCLEANING & CRACK SEALING OF
 
500.000252503.00148218.5058.6
Work Order12-05-16
Work Began12-12-16
Work Completed
Time Computed12-12-16
Contract Working Days150
Addl Days Granted0
Working Days Charged51
Percent Time Used34
Contractor(s)
FYL ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6302-88-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162203
Totals252503.000.00148218.5058.6

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6305-19-001
Proj IDSUP - 630519001
Work TypeLITTER PICKUP MAINTENANCE
 
0.001276022.22151512.7854.8
Work Order06-28-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged215
Percent Time Used58
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162231
Totals276022.2221954.58151512.7854.8

CountyMAVERICK
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6305-28-001
Proj IDSUP - 630528001
Work TypePICNIC AREA MAINTENANCE
 
0.00160934.8017832.4529.2
Work Order06-28-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged215
Percent Time Used29
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162232
Totals60934.802598.7517832.4529.2

CountyDIMMIT
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6305-70-001
Proj IDRMC - 630570001
Work TypeMOWING OF HIGHWAYS RIGHT-OF-WAY
 
246.200271941.5770867.1726.0
Work Order10-18-16
Work Began10-24-16
Work Completed
Time Computed10-24-16
Contract Working Days365
Addl Days Granted0
Working Days Charged100
Percent Time Used27
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6305-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162202
Totals271941.570.0070867.1726.0

CountyVAL VERDE
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6307-52-001
Proj IDRMC - 630752001
Work TypeINSTALL TRAFFIC SIG., FLASH BEACONS
 
0.001168873.251666.650.9
Work Order11-22-16
Work Began11-22-16
Work Completed
Time Computed11-22-16
Contract Working Days365
Addl Days Granted0
Working Days Charged71
Percent Time Used19
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162204
Totals168873.250.001666.650.9

CountyVAL VERDE
HighwaySL0025
FromVARIOUS
To.
CSJ6308-23-001
Proj IDSUP - 630823001
Work TypeJANITORIAL AND GROUNDS
 
0.001140119.2023158.5916.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days720
Addl Days Granted0
Working Days Charged122
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162203
Totals140119.200.0023158.5916.5

CountyWEBB
HighwayIH0035
FromVARIOUS
To.
CSJ6308-24-001
Proj IDSUP - 630824001
Work TypeJANITORIAL AND GROUNDS
 
0.001311469.1052480.4116.8
Work Order08-25-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged123
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162204
Totals311469.1013226.7752480.4116.8

CountyZAVALA
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6309-73-001
Proj IDRMC - 630973001
Work TypeMOWING OF HIGHWAYS RIGHT-OF-WAY
 
0.001345279.8086378.8125.0
Work Order12-21-16
Work Began12-21-16
Work Completed
Time Computed12-21-16
Contract Working Days730
Addl Days Granted0
Working Days Charged62
Percent Time Used8
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6309-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162203
Totals345279.800.0086378.8125.0

CountyVAL VERDE
HighwaySS0239
FromDEL RIO AREA/MAINTENANCE COMPLEX
ToDEL RIO AREA/MAINTENANCE COMPLEX
CSJ6310-71-001
Proj IDSUP - 631071001
Work TypeJANITORIAL MAINTENANCE @ DEL RIO
 
0.00137664.522601.476.9
Work Order12-01-16
Work Began12-01-16
Work Completed
Time Computed12-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged62
Percent Time Used8
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6310-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162231
Totals37664.521172.282601.476.9

page 1 | page 2 | page 3 | page 4