Monthly Local Let Maintenance Report For Laredo District As Of Jun 12, 2017 Page 2 Of 3

Last Update: Monday, June 12, 2017
FTP Icon
page 1 | page 2 | page 3

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyWEBB
HighwayIH0035
FromVARIOUS
ToVARIOUS
CSJ6295-31-001
Proj IDSUP - 629531001
Work TypePICNIC AREA MAINTENANCE
 
0.00177768.0855261.5571.0
Work Order10-08-15
Work Began10-15-15
Work Completed
Time Computed10-15-15
Contract Working Days731
Addl Days Granted0
Working Days Charged595
Percent Time Used81
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6295-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10152231
Totals77768.082897.0555261.5571.0

CountyVAL VERDE
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6296-98-001
Proj IDRMC - 629698001
Work TypeINSTALL PVT. MARKINGS AND PVT. MARKERS
 
0.001267451.12100301.6437.5
Work Order07-11-16
Work Began07-11-16
Work Completed
Time Computed07-11-16
Contract Working Days365
Addl Days Granted0
Working Days Charged325
Percent Time Used89
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-98-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162201
Totals267451.120.00100301.6437.5

CountyWEBB
HighwayIH0035
FromIH 35
ToUS 83, ETC.
CSJ6297-22-001
Proj IDRMC - 629722001
Work TypeLANDSCAPE MAINTENANCE
 
7.000214488.00109540.0051.0
Work Order04-27-16
Work Began04-28-16
Work Completed
Time Computed04-28-16
Contract Working Days730
Addl Days Granted0
Working Days Charged399
Percent Time Used54
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-22-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01162204
Totals214488.008270.00109540.0051.0

CountyWEBB
HighwaySL0020
FromSL 20
ToVARIOUS
CSJ6297-39-001
Proj IDRMC - 629739001
Work TypeLANDSCAPE MAINTENANCE
 
2.000228036.50229464.3599.9
Work Order04-27-16
Work Began04-28-16
Work Completed
Time Computed04-28-16
Contract Working Days365
Addl Days Granted365
Working Days Charged399
Percent Time Used54
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6297-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01162206
Totals228036.500.00229464.3599.9

CountyWEBB
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6299-31-001
Proj IDRMC - 629931001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
66.010187777.7414831.397.8
Work Order04-28-17
Work Began05-01-17
Work Completed
Time Computed05-01-17
Contract Working Days365
Addl Days Granted0
Working Days Charged31
Percent Time Used8
Contractor(s)
CTX SPECIAL SERVICES CO LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172201
Totals187777.7414831.3914831.397.8

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6299-42-001
Proj IDRMC - 629942001
Work TypeCLEANING AND SWEEPING OF HIGHWAYS
 
85.880299280.0040216.0013.4
Work Order04-01-17
Work Began04-03-17
Work Completed
Time Computed04-03-17
Contract Working Days365
Addl Days Granted0
Working Days Charged61
Percent Time Used16
Contractor(s)
RK POWER DRIVE SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #02172202
Totals299280.0020108.0040216.0013.4

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6300-77-001
Proj IDRMC - 630077001
Work TypeMAINTENANCE OF ILLUMINATION SYSTEMS ALON
 
0.001120800.0045000.0037.2
Work Order07-29-16
Work Began08-01-16
Work Completed
Time Computed08-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged304
Percent Time Used41
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6300-77-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07162201
Totals120800.005000.0045000.0037.2

CountyVAL VERDE
HighwayUS0090
FromUS 277
ToVARIOUS
CSJ6301-03-001
Proj IDRMC - 630103001
Work TypeUPGRADE OF EXISTING MBGF, DOWNSTREAM ANC
 
0.001312383.64212957.9668.1
Work Order08-08-16
Work Began08-15-16
Work Completed
Time Computed08-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged273
Percent Time Used74
Contractor(s)
ELITE CASTLE RESOURCES LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05162203
Totals312383.6413297.66212957.9668.1

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6301-09-001
Proj IDRMC - 630109001
Work TypeINSTALL PVT. MARKINGS AND PVT. MARKERS
 
0.001262806.47181948.6069.2
Work Order04-11-17
Work Began04-11-17
Work Completed
Time Computed04-11-17
Contract Working Days365
Addl Days Granted0
Working Days Charged51
Percent Time Used13
Contractor(s)
PAVEMENT MARKINGS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162202
Totals262806.4786087.80181948.6069.2

CountyVAL VERDE
HighwaySS0239
FromDEL RIO TXDOT COMPLEX
ToDEL RIO TXDOT COMPLEX
CSJ6301-67-001
Proj IDRMC - 630167001
Work TypeLANDSCAPE MAINTENANCE
 
0.00111200.004700.0041.9
Work Order12-01-16
Work Began12-15-16
Work Completed
Time Computed12-15-16
Contract Working Days365
Addl Days Granted0
Working Days Charged168
Percent Time Used46
Contractor(s)
DELGADO'S CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6301-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162201
Totals11200.001125.004700.0041.9

CountyDUVAL
HighwayUS0059
FromUS 59
ToVARIOUS
CSJ6301-80-001
Proj IDRMC - 630180001
Work TypeMOWING OF HIGHWAYS RIGHT-OF-WAY
 
331.190174092.00173038.3699.3
Work Order09-21-16
Work Began09-29-16
Work Completed
Time Computed10-03-16
Contract Working Days365
Addl Days Granted0
Working Days Charged245
Percent Time Used67
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6301-80-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162201
Totals174092.0074190.17173038.3699.3

CountyKINNEY
HighwayUS0090
FromVARIOUS
ToVARIOUS
CSJ6301-95-001
Proj IDBPM - 630195001
Work TypeREHABILITATION OF VARIOUS BRIDGE FACILIT
 
0.03264877.0071329.5099.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order11-22-16
Work Began11-22-16
Work Completed
Time Computed11-22-16
Contract Working Days60
Addl Days Granted0
Working Days Charged51
Percent Time Used85
Contractor(s)
DELGADO'S CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6301-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09162201
Totals64877.000.0071329.5099.9

CountyDUVAL
HighwaySH0016
FromVARIOUS
ToVARIOUS
CSJ6302-10-001
Proj IDBPM - 630210001
Work TypeREHABILITATION OF VARIOUS BRIDGE FACILIT
 
0.281220518.00370631.3199.9
Work Order12-16-16
Work Began01-09-17
Work Completed
Time Computed01-09-17
Contract Working Days90
Addl Days Granted0
Working Days Charged89
Percent Time Used98
Contractor(s)
BECK-REIT & SONS, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-10-001
FLASHER EQUIPMENT COMPANY (5.10)
Contract #10162201
Totals220518.0036671.03370631.3199.9

CountyKINNEY
HighwayUS0090
FromUS 90
ToVARIOUS
CSJ6302-58-001
Proj IDRMC - 630258001
Work TypeUPGRADE OF EXISTING BRIDGE RAIL
 
0.001194084.0081318.3641.8
Work Order01-23-17
Work Began01-23-17
Work Completed
Time Computed01-23-17
Contract Working Days60
Addl Days Granted0
Working Days Charged17
Percent Time Used28
Contractor(s)
DELGADO'S CONSTRUCTION
SUBCONTRACTOR(S) FOR CCSJ: 6302-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11162202
Totals194084.004445.3681318.3641.8

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6302-74-001
Proj IDRMC - 630274001
Work TypeCLEANING & CRACK SEALING OF HIGHWAYS
 
500.000238003.00255614.00100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order12-08-16
Work Began12-12-16
Work Completed06-02-17
Time Computed12-12-16
Contract Working Days150
Addl Days Granted0
Working Days Charged140
Percent Time Used93
Contractor(s)
FYL ENTERPRISES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6302-74-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162202
Totals238003.000.00255614.00100.0

CountyWEBB
HighwayIH0035
FromIH 35
ToVARIOUS
CSJ6305-19-001
Proj IDSUP - 630519001
Work TypeLITTER PICKUP MAINTENANCE
 
0.001276022.22237643.4986.0
Work Order06-28-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged335
Percent Time Used91
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-19-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162231
Totals276022.2218115.71237643.4986.0

CountyMAVERICK
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6305-28-001
Proj IDSUP - 630528001
Work TypePICNIC AREA MAINTENANCE
 
0.00160934.8027815.0045.6
Work Order06-28-16
Work Began07-01-16
Work Completed
Time Computed07-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged335
Percent Time Used45
Contractor(s)
TIBH INDUSTRIES, INC.
WORLD TECHNICAL SERVICES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6305-28-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06162232
Totals60934.803172.1527815.0045.6

CountyDIMMIT
HighwayUS0083
FromUS 83
ToVARIOUS
CSJ6305-70-001
Proj IDRMC - 630570001
Work TypeMOWING OF HIGHWAYS RIGHT-OF-WAY
 
246.200271941.57118622.3443.6
Work Order10-18-16
Work Began10-24-16
Work Completed
Time Computed10-24-16
Contract Working Days365
Addl Days Granted0
Working Days Charged220
Percent Time Used60
Contractor(s)
R&M INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6305-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162202
Totals271941.5747755.17118622.3443.6

CountyVAL VERDE
HighwayUS0277
FromUS 277
ToVARIOUS
CSJ6307-52-001
Proj IDRMC - 630752001
Work TypeINSTALL TRAFFIC SIG., FLASH BEACONS PVT
 
0.001168873.2541383.5524.5
Work Order11-22-16
Work Began11-22-16
Work Completed
Time Computed11-22-16
Contract Working Days365
Addl Days Granted0
Working Days Charged191
Percent Time Used52
Contractor(s)
TRIPLE H FIELD SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6307-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10162204
Totals168873.250.0041383.5524.5

CountyVAL VERDE
HighwaySL0025
FromVARIOUS
To.
CSJ6308-23-001
Proj IDSUP - 630823001
Work TypeJANITORIAL AND GROUNDS
 
0.001140119.2023158.5916.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-25-16
Work Began00-00-00
Work Completed
Time Computed09-01-16
Contract Working Days720
Addl Days Granted0
Working Days Charged122
Percent Time Used16
Contractor(s)
TIBH INDUSTRIES, INC.
E.Q.U.I.P. ENTERPRISES
SUBCONTRACTOR(S) FOR CCSJ: 6308-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08162203
Totals140119.200.0023158.5916.5

page 1 | page 2 | page 3