Monthly State Let Construction Report For Laredo District As Of Oct 16, 2017 Page 2 Of 2

Last Update: Monday, October 16, 2017
FTP Icon
page 1 | page 2

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyMAVERICK ETC
HighwayUS 277 ETC
From0.501 M SOUTH OF BU 277(N CEYLON)
ToUS 57
CSJ0299-04-068
Proj IDNH 2017(794)
Work TypeACP OVERLAY AND PAV MRKS
 
14.7256593233.701790917.0227.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order04-24-17
Work Began07-17-17
Work Completed
Time Computed00-00-00
Contract Working Days97
Addl Days Granted0
Working Days Charged54
Percent Time Used55
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0299-04-068
DELGADO"S CONSTRUCTION (4.71)
FLASHER EQUIPMENT COMPANY (2.28)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (6.90)
Contract #03173217
Totals6593233.70273571.631790917.0227.1

CountyMAVERICK ETC
HighwayUS 277 ETC
From@ NORTH ST
To.
CSJ0299-04-070
Proj IDSTP 2016(066)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
1.000315267.29202010.5286.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-22-15
Work Began04-25-16
Work Completed
Time Computed00-00-00
Contract Working Days112
Addl Days Granted0
Working Days Charged234
Percent Time Used208
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0299-04-070
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09153021
Totals315267.29240.00202010.5286.9

CountyMAVERICK
HighwayUS 277
FromUS 57/US 277 INTERSECTION
To0.167 MILE EAST OF FOSTER MALDONADO
CSJ0300-01-080
Proj IDNH 1702(331)
Work TypeGRAD,BASE,STRUCTURE,PAVMRK
 
1.51913203660.340.000.0
CountyMAVERICK
HighwayUS 277
From0.167 MILE EAST OF FOSTER MALDONADO
ToSL 480
CSJ0300-01-100
Proj IDC 300-1-100
Work TypeGRAD,BASE,STRUCTURE,PAVMRK
 
1.2275787204.550.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-18-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days530
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0300-01-080
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173204
Totals18990864.890.000.000.0

CountyMAVERICK ETC
HighwayUS 277 ETC
FromSL 480
To11.960 MI W OF DIMMIT COUNTY LINE
CSJ0300-01-091
Proj IDSTP 1602(174)HESG
Work TypeTEXTURIZE SHOULDERS CENTERLINE TEXT
 
50.697307234.04283379.1292.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order07-29-16
Work Began10-31-16
Work Completed
Time Computed00-00-00
Contract Working Days51
Addl Days Granted0
Working Days Charged34
Percent Time Used66
Contractor(s)
DOUBLE A CONTRACTING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0300-01-091
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06163024
Totals307234.0415543.36283379.1292.2

CountyDIMMIT
HighwayUS 277
FromFM 393
ToSL 517
CSJ0300-03-066
Proj IDNH 2016(478)
Work TypePLANING, ACP, OVERLAY PAV MRK
 
30.5609546333.929168358.0196.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-29-16
Work Began06-27-16
Work Completed
Time Computed00-00-00
Contract Working Days205
Addl Days Granted0
Working Days Charged196
Percent Time Used95
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0300-03-066
CHEROKEE SERVICES (0.34)
FLASHER EQUIPMENT COMPANY (1.83)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (2.00)
DELGADO"S CONSTRUCTION (0.41)
FOUR J TRAFFIC CONTROLS, INC. (0.92)
ALL AMERICAN TRUCKING, INC. (1.29)
PIONEER UTILITIES, INC. (0.00)
Contract #01163217
Totals9546333.92825.509168358.0196.0

CountyLASALLE
HighwaySH 97
FromFRIO RIVER BRIDGE
To.
CSJ0328-08-022
Proj IDBR 1502(514)
Work TypeREPLACEMENT OF EXISTING BRIDGE
 
0.1608315541.285973140.0771.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order10-30-15
Work Began07-06-16
Work Completed
Time Computed00-00-00
Contract Working Days373
Addl Days Granted70
Working Days Charged292
Percent Time Used96
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0328-08-022
FLASHER EQUIPMENT COMPANY (1.14)
D&S TEXAS ICON CONSTRUCTION (1.52)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.59)
AARON CONCRETE CONTRACTORS, L.P. (1.78)
PRIMATE CONSTRUCTION, INC. (0.32)
VOGES DRILLING CO. (4.79)
CUATRO T CONSTRUCTION, INC. (0.67)
RIO GRANDE REBAR RODBUSTERS, LLC. (0.50)
Contract #08153038
Totals8315541.28354531.105973140.0771.8

CountyWEBB
HighwayUS 59 ETC
FromCASA DEL SOL
ToIH 35
CSJ0542-01-083
Proj IDSTP 1602(512)HES
Work TypeIMPROVE TRAFFIC SIGNALS
 
16.1691680643.301137764.4967.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-14-16
Work Began05-08-17
Work Completed
Time Computed00-00-00
Contract Working Days145
Addl Days Granted0
Working Days Charged83
Percent Time Used57
Contractor(s)
TRAF-TEX, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0542-01-083
FLASHER EQUIPMENT COMPANY (10.05)
Contract #08163225
Totals1680643.300.001137764.4967.6

CountyDUVAL
HighwaySH 339
FromSH 16
ToSH 359
CSJ0623-01-022
Proj IDSTP 2017(029)
Work TypeSEAL COAT & PAV MRKS
 
30.624948467.82984095.38100.0
CountyDUVAL
HighwaySH 339
FromFM 716
ToBROOKS COUNTY LINE
CSJ0623-02-029
Proj IDC 623-2-29
Work TypeSEAL COAT & PAV MRKS
 
11.286274520.44292780.07100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-17-17
Work Began04-13-17
Work Completed07-13-17
Time Computed00-00-00
Contract Working Days94
Addl Days Granted0
Working Days Charged46
Percent Time Used48
Contractor(s)
RONALD R. WAGNER & CO., LP
SUBCONTRACTOR(S) FOR CCSJ: 0623-01-022
FLASHER EQUIPMENT COMPANY (1.94)
VIZCAINO, L.P. (20.29)
Contract #09163014
Totals1222988.261000.001276875.45100.0

CountyWEBB
HighwayVA
FromDISTRICTWIDE
To.
CSJ0922-00-056
Proj IDSTP 1602(137)
Work TypeUPGRADE RAIL
 
1.3961498321.431112890.4774.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-08-16
Work Began09-19-16
Work Completed
Time Computed00-00-00
Contract Working Days281
Addl Days Granted0
Working Days Charged241
Percent Time Used85
Contractor(s)
CRG
SUBCONTRACTOR(S) FOR CCSJ: 0922-00-056
FLASHER EQUIPMENT COMPANY (0.64)
RPV CONSTRUCTION (22.55)
Contract #05163214
Totals1498321.43123082.911112890.4774.2

CountyWEBB
HighwayVA
FromAT VARIOUS LOCATIONS IN WEBB CNTY
To.
CSJ0922-00-062
Proj IDSTP 1502(256)
Work TypeCONSTRUCT CURB RAMPS
 
0.1001680038.50859973.0551.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-22-17
Work Began05-02-17
Work Completed
Time Computed00-00-00
Contract Working Days184
Addl Days Granted0
Working Days Charged101
Percent Time Used54
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0922-00-062
FLASHER EQUIPMENT COMPANY (1.71)
CLASSIC TEJAS CONSTRUCTION, INC. (5.76)
PAVEMENT MARKINGS INC. (2.94)
Contract #01173008
Totals1680038.50239630.00859973.0551.1

CountyLASALLE
HighwayCS
FromVARIOUS LOCATIONS IN ENCINAL
To.
CSJ0922-20-019
Proj IDSTP 1602(372)TAPS
Work TypeSAFE PATH SIDEWALK PROJECT
 
0.100242635.10201696.1083.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-02-17
Work Began04-06-17
Work Completed
Time Computed00-00-00
Contract Working Days90
Addl Days Granted0
Working Days Charged90
Percent Time Used100
Contractor(s)
JESS CONTRACTING, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0922-20-019
FLASHER EQUIPMENT COMPANY (2.02)
PAVEMENT MARKINGS INC. (1.55)
Contract #01173214
Totals242635.100.00201696.1083.1

CountyDUVAL
HighwayVA
FromVARIOUS LOCATIONS IN SAN DIEGO TX
To.
CSJ0922-23-009
Proj IDSTP 2017(030)TAPS
Work TypeSAFE PATH SIDEWALK PROJECT
 
3.3331157974.50851999.9573.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-22-17
Work Began04-10-17
Work Completed
Time Computed00-00-00
Contract Working Days180
Addl Days Granted0
Working Days Charged117
Percent Time Used65
Contractor(s)
ENCINO LANDSCAPE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0922-23-009
CLASSIC TEJAS CONSTRUCTION, INC. (1.72)
HIGHWAY BARRICADES AND SERVICES, LLC (3.61)
Contract #01173208
Totals1157974.50134593.30851999.9573.5

CountyDIMMIT
HighwayFM 190
FromUS 83
ToSH 85
CSJ0963-01-032
Proj IDSSW 963-1-32
Work TypeBRIDGE REPLACEMENTS,BASE,SURFACING
 
11.4714902990.221687396.6234.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order03-08-17
Work Began04-17-17
Work Completed
Time Computed00-00-00
Contract Working Days228
Addl Days Granted0
Working Days Charged123
Percent Time Used53
Contractor(s)
IOC COMPANY LLC
SUBCONTRACTOR(S) FOR CCSJ: 0963-01-032
PAVEMENT MARKINGS INC. (1.96)
HOUSTON SAWING & DRILLING (0.11)
W. W. FOUNDATION DRILLING, LTD. (4.85)
CERTIFIED PLACERS LLC (0.65)
Contract #02173035
Totals4902990.22448192.831687396.6234.4

CountyZAVALA
HighwayFM 1025
FromUS 83
ToFM 117
CSJ1279-01-036
Proj IDSTP 1302(036)
Work TypeGRADE,WIDEN,STR,SURF TREAT,PAV MRKS
 
19.8557134438.216229081.8687.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order08-03-16
Work Began09-12-16
Work Completed
Time Computed00-00-00
Contract Working Days322
Addl Days Granted0
Working Days Charged220
Percent Time Used68
Contractor(s)
RAY FARIS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1279-01-036
MURRAY CONSTRUCTION (0.84)
D&S TEXAS ICON CONSTRUCTION (1.46)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.60)
MV HENKE COMPANY, LLC (2.01)
FLASHER EQUIPMENT COMPANY (2.56)
RELMCO, INC. (8.40)
Contract #06163208
Totals7134438.21422667.476229081.8687.3

CountyLASALLE
HighwayFM 468
FromFM 469
ToDIMMIT COUNTY LINE
CSJ1545-02-021
Proj IDSTP 1502(456)
Work TypeGRADING,BASE,SURFACING & PAV MRKS
 
27.9239571743.109585232.78100.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-11-15
Work Began11-02-15
Work Completed08-28-17
Time Computed00-00-00
Contract Working Days223
Addl Days Granted20
Working Days Charged239
Percent Time Used98
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 1545-02-021
ALTUS TRAFFIC MANAGEMENT LLC (0.46)
CHEROKEE SERVICES (0.10)
FLASHER EQUIPMENT COMPANY (1.90)
ROADWAY SPECIALTIES, INC. (1.96)
CLARK CONSTRUCTION OF TEXAS, INC. (6.47)
Contract #07153046
Totals9571743.100.009585232.78100.0

CountyWEBB
HighwayFM 1472
From7.854 MI N OF FM 1472/SH 255 INT
To2.00 MILES NORTH
CSJ2150-03-025
Proj IDC 2150-3-25
Work TypeGRAD,BASE,STRUCTURES AND SURFACE
 
2.0002940497.269200.000.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order06-14-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days200
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
ANGEL BROTHERS HOLDINGS CORP.
SUBCONTRACTOR(S) FOR CCSJ: 2150-03-025
D&S TEXAS ICON CONSTRUCTION (5.41)
FLASHER EQUIPMENT COMPANY (1.48)
HIGHWAY BARRICADES AND SERVICES, LLC (2.38)
MV HENKE COMPANY, LLC (1.51)
Contract #05173243
Totals2940497.269200.009200.000.3

CountyWEBB
HighwayFM 1472
FromKILLAM INDUSTRIAL BLVD_NB
To0.3 MI N OF MUELLER BLVD
CSJ2150-04-067
Proj IDSTP 1602(520)MM
Work TypeBASE, GRADE, CONCRETE PAVEMENT, ETC
 
1.0524677325.894570961.6397.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-26-16
Work Began01-20-17
Work Completed
Time Computed00-00-00
Contract Working Days136
Addl Days Granted0
Working Days Charged136
Percent Time Used100
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2150-04-067
D&S TEXAS ICON CONSTRUCTION (4.19)
FLASHER EQUIPMENT COMPANY (1.51)
REIM CONSTRUCTION, INC. (42.59)
THE LEVY COMPANY, L.P. (3.00)
LIGHT IT UP ELECTRIC (0.22)
ROVAN TEXAS, LLC (3.41)
CERTIFIED PLACERS LLC (0.19)
Contract #08163210
Totals4677325.89220502.734570961.6397.7

CountyVAL VERDE
HighwaySL 79
FromUS 277 SOUTH
To3.16 MILES NORTH OF US 277 SOUTH
CSJ3621-01-012
Proj IDSTP 1702(690)
Work TypeBASE,GRADE,ACP,PAVMRK,ILLUMINATION
 
3.1615023548.030.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order09-20-17
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days115
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
HUNTER INDUSTRIES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 3621-01-012
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08173008
Totals5023548.030.000.000.0