Monthly State Let Construction Report For Laredo District As Of Apr 11, 2014 Page 2 Of 2

Last Update: Friday, April 11, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyZAVALA
Highway FM 1867
From FM 1025
To 3.7 MI NORTH OF DIMMIT CO LINE
CSJ 1799-01-014
Proj ID STP 2013(799)
Work Type GRADE, BASE, STR, ACP, SURF, SIGN, PAV MK
 
9.656 4275164.51 420368.34 1068888.70 25.0
Work Order 08-19-13
Work Began 10-01-13
Work Completed  
Time Computed 09-04-13
Contract Working Days 266
Addl Days Granted 25
Working Days Charged 98
Percent Time Used 33
Contractor(s)
V. K. KNOWLTON CONSTRUCTION AND UTILITIES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1799-01-014
RELMCO, INC. ( 12.39%)
SOIL-TECH, INC.(5.08%)
FLASHER EQUIPMENT COMPANY(2.44%)
SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (2.38%)
BLACK TOPPER TECHNOLOGY, INC.(1.95%)
Contract # 06133224
Totals 4275164.51 420368.34 1068888.70 25.0

CountyWEBB
Highway FM 1472 ETC
From 1.321 MI SOUTH OF SH 255
To PANAMERICAN BLVD
CSJ 2150-04-055
Proj ID STP 2014(425)
Work Type MILL, ACP OVERLAY, SIGNS, PAV MKS
 
29.416 6699784.87 923666.36 923666.36 13.7
Work Order 03-06-14
Work Began 03-14-14
Work Completed  
Time Computed 03-22-14
Contract Working Days 144
Addl Days Granted 0
Working Days Charged 13
Percent Time Used 9
Contractor(s)
ANGEL BROTHERS ENTERPRISES, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 2150-04-055
ALTUS TRAFFIC MANAGEMENT LLC (0.36%)
HIGHWAY BARRICADES AND SERVICES, LLC (3.07%)
LAREDO STRIPING INC. (2.09%)
MPB, INC.(0.26%)
Contract # 02143225
Totals 6699784.87 923666.36 923666.36 13.7

CountyLASALLE
Highway FM 624
From 8.37 MI S OF FM 469
To MCMULLEN COUNTY LINE
CSJ 2373-01-015
Proj ID STP 2013(346)
Work Type OVERLAY, BRIDGE RAIL AND MBGF
 
14.466 4767791.96 95332.30 3053567.25 64.0
Work Order 02-28-13
Work Began 08-30-13
Work Completed  
Time Computed 03-16-13
Contract Working Days 175
Addl Days Granted 0
Working Days Charged 114
Percent Time Used 65
Contractor(s)
ANDERSON COLUMBIA CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 2373-01-015
SCOTT DERR PAINTING CO (0.09%)
PRIMATE CONSTRUCTION, INC. (0.22%)
HIGHWAY BARRICADES AND SERVICES, LLC (0.46%)
PENHALL COMPANY(0.50%)
INTERSTATE BARRICADES & MARKINGS, INC. (2.32%)
DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (6.07%)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.28%)
Contract # 01133017
Totals 4767791.96 95332.30 3053567.25 64.0

CountyDIMMIT
Highway LP 517
From US 277
To US 83
CSJ 2485-02-009
Proj ID STP 2014(629)
Work Type BASE, ACP OVERLAY, SIGNS, PAV MKS
 
3.965 1434456.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
H. L. ZUMWALT CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2485-02-009
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143010
Totals 1434456.10 0.00 0.00 0.0

CountyVAL VERDE
Highway SL 79
From 0.176 MILES EAST OF US 90 NORTH
To 0.332 MILES WEST OF US 90 NORTH
CSJ 3621-01-009
Proj ID STP 2013(939)
Work Type GRADING, BASE, STRUCTURES & SURFACE
 
0.509 5720529.99 660428.55 1511393.21 26.4
Work Order 01-06-14
Work Began 02-17-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 262
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 11
Contractor(s)
REECE ALBERT, INC.
SUBCONTRACTOR(S) FOR CCSJ: 3621-01-009
INCE ENTERPRISES, INC. (1.33%)
GARY A. CRAIN, INC.(0.08%)
STAR OPERATIONS, INC.(5.54%)
D S TEXAS ICON CONSTRUCTION, LLC (0.38%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (1.33%)
INTERSTATE BARRICADES & MARKINGS, INC. (0.24%)
BRUNDAGE-BONE(0.09%)
S & S BRIDGE PAINTING, INC.(0.06%)
ALAMO CRANE SERVICE, INC.(0.94%)
HIGHWAY INFRASTRUCTURE SAFETY SERVICES, INC. (0.34%)
Contract # 09133037
Totals 5720529.99 660428.55 1511393.21 26.4

page 1 | page 2