|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | WEBB |
| Highway |
IH 35 |
| From |
3.9 MI. NORTH OF MILO INTERCHANGE |
| To |
0.5 MI. NORTH OF UNIROYAL |
| CSJ |
0018-05-062 |
| Proj ID |
NH 2002(79) |
| Work Type |
GRADING, BASE, STRUCTURES & SURFACE |
| |
|
6.030 |
43060986.64 |
1258196.41 |
39488444.60 |
94.3 |
| Work Order |
10-13-03 |
| Work Began |
03-01-04 |
| Work Completed |
|
| Time Computed |
03-01-04 |
| Contract Working Days |
756 |
| Addl Days Granted |
87 |
| Working Days Charged |
1,019 |
| Percent Time Used |
120 |
| Contractor(s) |
| PRICE CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0018-05-062 SUMMIT CONTRACTING, INC. ( 14.37%) W. W. FOUNDATION DRILLING, LTD.(0.88%) ELLIS AND ELLIS(1.20%) SOIL-TECH, INC.(1.00%) LONE STAR TRAFFIC SERVICE, INC.(0.37%) JAVELINA CONSTRUCTION, INC.(0.24%) RIO GRANDE REBAR PLACING, LTD. (0.13%) LAREDO STRIPING INC. (0.86%) STRIPE-A-ZONE, INC.(1.07%) G. O. TRUCKING & EXCAVATING(3.61%) STAR OPERATIONS, INC.(4.60%) S & S PAINTING (0.09%) KOTHMANN, LTD. (0.11%) W.W. WEBBER INC. (1.74%) RONALD R. WAGNER & CO., LP (0.00%) HIGHWAY TECHNOLOGIES, L.P. (0.01%) TRANSMISSION & DISTRIBUTION SOLUTIONS, LTD (0.20%) RAMOS CONCRETE, INC. (0.06%) STRIPES & STOPS COMPANY, INC.(0.12%)
|
| Contract # |
08033205 |
|
Totals |
43060986.64 |
1258196.41 |
39488444.60 |
94.3 |
|
| County | VAL VERDE |
| Highway |
US 90 |
| From |
THE BEGINNING OF THE PECOS RIVER BR |
| To |
THE END OF THE PECOS RIVER BRIDGE |
| CSJ |
0022-06-046 |
| Proj ID |
BR 2008(284) |
| Work Type |
REHABILITATE BRIDGE AND APPROACHES |
| |
|
0.248 |
4259434.07 |
383766.30 |
1227528.83 |
28.8 |
| Work Order |
03-07-08 |
| Work Began |
08-11-08 |
| Work Completed |
|
| Time Computed |
03-23-08 |
| Contract Working Days |
399 |
| Addl Days Granted |
0 |
| Working Days Charged |
55 |
| Percent Time Used |
13 |
| Contractor(s) |
| SCR CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0022-06-046 DUSTROL, INC.(0.25%) FORTSON CONTRACTING, INC.(0.67%) GUAJARDO STEEL (1.10%) HIGHWAY TECHNOLOGIES (0.99%) MICA CORPORATION (1.76%) VOGES DRILLING (0.35%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(0.31%)
|
| Contract # |
01083218 |
|
Totals |
4259434.07 |
383766.30 |
1227528.83 |
28.8 |
|
| County | WEBB |
| Highway |
US 83 |
| From |
SH 359/CORTEZ STREET INTERSECTION |
| To |
CHACON CREEK BRIDGE |
| CSJ |
0038-01-033 |
| Proj ID |
STP 2001(543) |
| Work Type |
GRADING, BASE, STRUCTURES, AND SURF |
| |
|
1.936 |
29556535.65 |
440483.28 |
27667407.85 |
97.5 |
| Work Order |
11-01-05 |
| Work Began |
05-08-06 |
| Work Completed |
|
| Time Computed |
05-08-06 |
| Contract Working Days |
830 |
| Addl Days Granted |
27 |
| Working Days Charged |
848 |
| Percent Time Used |
98 |
| Contractor(s) |
| PRICE CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0038-01-033 VAN - TECH LANDSCAPING & EROSION CONTROL, INC. (0.22%) ELLIS AND ELLIS(2.47%) FARR FOUNDATION, INC.(2.25%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (1.07%) SUMMIT CONTRACTING, LTD. ( 22.38%) UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(1.15%) STAR OPERATIONS, INC.(7.04%) W. W. FOUNDATION DRILLING, LTD.(2.61%) GIBSON & ASSOCIATES, INC.(0.19%) RIO GRANDE REBAR PLACING, LTD. (0.06%) SOUTH TEXAS INDUSTRIAL COATINGS, L.L.C.(0.19%) HENRY'S CONSTRUCTION, INC. (1.61%) JAVELINA CONSTRUCTION SOUTH, INC.(0.11%) INNOVATIVE CONCRETE DESIGNS(2.42%) W.W. WEBBER, LLC (0.62%) REBAR SPECIALISTS(0.04%) TRANSMISSION & DISTRIBUTION SOLUTIONS, LTD (0.33%)
|
| Contract # |
09053046 |
|
Totals |
29556535.65 |
440483.28 |
27667407.85 |
97.5 |
|
| County | WEBB |
| Highway |
LP 20 |
| From |
0.20 MI SOUTH OF SPUR 400 |
| To |
1.68 MI NORTH OF US 59 |
| CSJ |
0086-14-022 |
| Proj ID |
STP 2005(286) |
| Work Type |
GRAD, BASE, STRUCTURE AND SURF |
| |
|
2.719 |
19208212.61 |
0.00 |
20279641.97 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
08-10-06 |
| Work Began |
02-05-07 |
| Work Completed |
|
| Time Computed |
02-01-07 |
| Contract Working Days |
656 |
| Addl Days Granted |
0 |
| Working Days Charged |
509 |
| Percent Time Used |
77 |
| Contractor(s) |
| KIEWIT TEXAS CONSTRUCTION L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0086-14-022 DFW(0.09%) GILMAR CONSTRUCTION, LTD.(2.19%) JAVELINA CONSTRUCTION SOUTH, INC.(0.26%) J.L. STEEL, L.P. (0.29%) LAREDO STRIPING INC. (0.49%) SCOTT DERR PAINTING CO (0.11%) STAR OPERATIONS, INC.(4.83%) UNITED RENTAL (CORPUS CHRISTI) (1.42%) VAN - TECH LANDSCAPING & EROSION CONTROL, INC. (0.74%) W. W. FOUNDATION DRILLING, LTD.(0.75%) W.W. WEBBER, LLC (0.66%) TRANSMISSION & DISTRIBUTION SOLUTIONS, LTD (0.13%)
|
| Contract # |
06063003 |
|
Totals |
19208212.61 |
0.00 |
20279641.97 |
99.9 |
|
| County | VAL VERDE |
| Highway |
US 277 |
| From |
6.340 MI SOUTH OF US 377 |
| To |
3.264 MI NORTH |
| CSJ |
0160-06-022 |
| Proj ID |
NH 2006(778) |
| Work Type |
GRAD, BASE, STRUCTURE & SURFACE |
| |
|
3.264 |
2272431.29 |
890017.38 |
2128806.69 |
93.6 |
| Work Order |
11-14-07 |
| Work Began |
03-01-08 |
| Work Completed |
|
| Time Computed |
11-30-07 |
| Contract Working Days |
177 |
| Addl Days Granted |
0 |
| Working Days Charged |
113 |
| Percent Time Used |
63 |
| Contractor(s) |
| REECE ALBERT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0160-06-022 ALTEX LANDSCAPE CONSTRUCTION, INC. (0.15%) FLASHER EQUIPMENT COMPANY(0.85%) INTERSTATE BARRICADES & MARKINGS, INC. (0.71%) JAVELINA CONSTRUCTION SOUTH, INC.(1.68%)
|
| Contract # |
10073214 |
|
Totals |
2272431.29 |
890017.38 |
2128806.69 |
93.6 |
|
| County | MAVERICK |
| Highway |
US 57 |
| From |
0.360 MI NORTH EAST OF FM 481 |
| To |
2,887 MI NORTH EAST OF FM 481 |
| CSJ |
0276-01-033 |
| Proj ID |
CBI 2008(184) |
| Work Type |
GRADE, BASE, STR, SURF & PAV'T MRK |
| |
|
30.965 |
7139448.54 |
646142.47 |
3647801.85 |
51.0 |
| Work Order |
04-16-08 |
| Work Began |
06-24-08 |
| Work Completed |
|
| Time Computed |
07-16-08 |
| Contract Working Days |
268 |
| Addl Days Granted |
0 |
| Working Days Charged |
93 |
| Percent Time Used |
34 |
| Contractor(s) |
| E. E. HOOD & SONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0276-01-033 ALL AMERICAN TRUCKING, INC.( 14.60%) FLASHER EQUIPMENT COMPANY(6.90%) GEOSOURCE, INC.(5.93%) COLD CREEK CONSTRUCTION, LTD (2.05%) TROUT TRUCKING_COMPANY INC.(0.89%) FORTSON CONTRACTING, INC.(0.57%)
|
| Contract # |
03083008 |
|
Totals |
7139448.54 |
646142.47 |
3647801.85 |
51.0 |
|
| County | ZAVALA |
| Highway |
US 57 |
| From |
AT THE INTERSECTION OF US 83 |
| To |
FM 117 INTERSECTION |
| CSJ |
0276-04-022 |
| Proj ID |
STP 2008(183) |
| Work Type |
GRADE, BASE, STR, SURF & PAV'T MRK |
| |
|
27.777 |
7190082.83 |
936026.70 |
4962595.50 |
69.0 |
| Work Order |
11-12-07 |
| Work Began |
02-22-08 |
| Work Completed |
|
| Time Computed |
02-22-08 |
| Contract Working Days |
220 |
| Addl Days Granted |
0 |
| Working Days Charged |
200 |
| Percent Time Used |
90 |
| Contractor(s) |
| RAY FARIS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0276-04-022 COX PAVING COMPANY, L.P. ( 10.88%) HIGHWAY TECHNOLOGIES, L.P. (6.82%) CRAWFORD YANT(4.70%) INTERSTATE CONCRETE & STEEL SERVICES INCORPORATED(3.33%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.83%) EGGEMEYER TREE SERVICE (1.42%)
|
| Contract # |
10073016 |
|
Totals |
7190082.83 |
936026.70 |
4962595.50 |
69.0 |
|
| County | MAVERICK |
| Highway |
US 277 |
| From |
BS US 277 NORTH/US 277 INTERSECTION |
| To |
0.663 MILE EAST OF US 277 |
| CSJ |
0299-04-049 |
| Proj ID |
HP 2007(582) |
| Work Type |
GRAD, BASE, SURF, AND RR GRADE SEPR |
| |
|
0.663 |
18769597.78 |
0.00 |
6010278.94 |
32.0 |
| County | MAVERICK |
| Highway |
US 277 |
| From |
SOUTH END OF SECO CREEK BRIDGE |
| To |
NORTH END OF SECO CREEK BRIDGE |
| CSJ |
0299-04-057 |
| Proj ID |
NH 2007(639) |
| Work Type |
PEDESTRIAN BRIDGE |
| |
|
0.058 |
130889.00 |
0.00 |
5695.00 |
4.3 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
12-18-07 |
| Work Began |
03-17-08 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
442 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ROSIEK CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0299-04-049 CHOCTAW ERECTORS, INC. (6.00%) LONE STAR TRAFFIC SERVICE, INC.(0.16%) H. L. ZUMWALT CONSTRUCTION, INC. (6.04%) JAVELINA CONSTRUCTION SOUTH, INC.(0.19%) PIPELAYERS, INC. (5.16%) GEOSOURCE, INC.(0.18%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.46%) HIGHWAY TECHNOLOGIES, L.P. (0.75%) GUAJARDO STEEL (0.51%) MICA CORPORATION (1.40%) JMSL, LLC(2.91%) W. W. FOUNDATION DRILLING, LTD.(1.92%) PRIMATE CONSTRUCTION, INC. (0.22%) W.W. WEBBER, LLC (1.08%) S & S PAINTING (0.28%) 90 WEST CONTRACTOR'S, INC. (0.49%)
|
| Contract # |
06073030 |
|
Totals |
18900486.78 |
0.00 |
6015973.94 |
31.8 |
|
| County | LASALLE |
| Highway |
SH 97 |
| From |
FM 624 |
| To |
FM 469 |
| CSJ |
0483-01-039 |
| Proj ID |
STP 2007(583) |
| Work Type |
RESTORATION OF AN EXISTING HIGHWAY |
| |
|
13.971 |
3010299.87 |
372345.55 |
1816940.07 |
60.3 |
| Work Order |
02-20-08 |
| Work Began |
04-01-08 |
| Work Completed |
|
| Time Computed |
03-07-08 |
| Contract Working Days |
159 |
| Addl Days Granted |
0 |
| Working Days Charged |
144 |
| Percent Time Used |
90 |
| Contractor(s) |
| SALINAS CONSTRUCTION TECHNOLOGIES, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0483-01-039 DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (5.33%) FLASHER EQUIPMENT COMPANY(3.19%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(1.57%) PENNTEX MILLING, LLC (0.16%) MURRAY CONSTRUCTION(0.78%)
|
| Contract # |
01083017 |
|
Totals |
3010299.87 |
372345.55 |
1816940.07 |
60.3 |
|
| County | DUVAL |
| Highway |
SH 339 |
| From |
BROOK/DUVAL COUNTY LINE |
| To |
FM 716 |
| CSJ |
0623-02-025 |
| Proj ID |
STP 2008(017) |
| Work Type |
RESTORATION OF AN EXISTING HIGHWAY |
| |
|
26.434 |
7208950.94 |
978268.48 |
4260229.87 |
59.0 |
| Work Order |
01-03-08 |
| Work Began |
01-19-08 |
| Work Completed |
|
| Time Computed |
01-19-08 |
| Contract Working Days |
241 |
| Addl Days Granted |
0 |
| Working Days Charged |
155 |
| Percent Time Used |
64 |
| Contractor(s) |
| BAY LTD |
SUBCONTRACTOR(S) FOR CCSJ: 0623-02-025 VAN - TECH LANDSCAPING & EROSION CONTROL, INC. (2.05%) LISKA CONSTRUCTION COMPANY, INC. (4.51%) STAR OPERATIONS, INC.(1.91%) WRANGLER CONSTRUCTION CO.___(J.S. MERKLEY,INC.)(0.31%) W.W. WEBBER, LLC (0.51%) WOODSTOCK TREE SURGEONS(1.63%) HIGHWAY TECHNOLOGIES (4.60%) TAMEZ-PEARSON CONSTRUCTION, INC. (4.27%)
|
| Contract # |
11073006 |
|
Totals |
7208950.94 |
978268.48 |
4260229.87 |
59.0 |
|
| County | WEBB |
| Highway |
VA |
| From |
DISTRICTWIDE AT VARIOUS LOCATIONS |
| To |
. |
| CSJ |
0922-00-040 |
| Proj ID |
C 922-00-40 |
| Work Type |
NON - SITE SPECIFIC TRAFFIC SIGNALS |
| |
|
0.100 |
959163.55 |
31848.52 |
717895.94 |
78.7 |
| Work Order |
05-16-06 |
| Work Began |
09-15-06 |
| Work Completed |
|
| Time Computed |
06-01-06 |
| Contract Working Days |
480 |
| Addl Days Granted |
0 |
| Working Days Charged |
412 |
| Percent Time Used |
85 |
| Contractor(s) |
| STAR OPERATIONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0922-00-040 PAVEMENT MARKINGS INC. ( 11.86%)
|
| Contract # |
04063211 |
|
Totals |
959163.55 |
31848.52 |
717895.94 |
78.7 |
|
| County | WEBB |
| Highway |
CR |
| From |
AT MINES ROAD AT ESPADA CREEK |
| To |
. |
| CSJ |
0922-33-013 |
| Proj ID |
BR 96(623) |
| Work Type |
REPLACE STRUCTURES AND APPROACHES |
| |
|
0.755 |
333045.60 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
56 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| MPB, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0922-33-013 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10083019 |
|
Totals |
333045.60 |
0.00 |
0.00 |
0.0 |
|
| County | DUVAL |
| Highway |
FM 716 |
| From |
SH 359 |
| To |
SH 339 |
| CSJ |
1083-02-014 |
| Proj ID |
STP 2007(481) |
| Work Type |
REHAB EXT HWY & ADD SHOULDERS |
| |
|
9.376 |
2356105.74 |
6393.00 |
2218869.94 |
94.1 |
| Work Order |
11-02-07 |
| Work Began |
01-02-08 |
| Work Completed |
|
| Time Computed |
11-18-07 |
| Contract Working Days |
223 |
| Addl Days Granted |
0 |
| Working Days Charged |
182 |
| Percent Time Used |
81 |
| Contractor(s) |
| BALLENGER CONSTRUCTION COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 1083-02-014 HIGHWAY TECHNOLOGIES (2.92%) SUNBELT EXPRESS SERVICES, INC. (5.36%) VAN - TECH LANDSCAPING & EROSION CONTROL, INC. (3.26%) TONY A. ENTERPRISES, INC.(6.39%)
|
| Contract # |
09073223 |
|
Totals |
2356105.74 |
6393.00 |
2218869.94 |
94.1 |
|
| County | KINNEY |
| Highway |
FM 1908 |
| From |
MAVERICK COUNTY LINE |
| To |
SH 131 |
| CSJ |
1814-01-010 |
| Proj ID |
C 1814-1-10 |
| Work Type |
CEMENT BASE, SURFACING AND STRIPPING |
| |
|
10.491 |
2364468.55 |
257968.26 |
1446120.40 |
61.1 |
| County | MAVERICK |
| Highway |
FM 1908 |
| From |
AT THE INT OF FM 1591 |
| To |
MAVERICK/KINNEY COUNTY LINE |
| CSJ |
1814-02-014 |
| Proj ID |
C 1814-2-14 |
| Work Type |
RESTORATION OF AN EXISTING HIGHWAY |
| |
|
9.459 |
1195348.45 |
0.00 |
0.00 |
0.0 |
| Work Order |
02-13-08 |
| Work Began |
03-17-08 |
| Work Completed |
|
| Time Computed |
02-29-08 |
| Contract Working Days |
379 |
| Addl Days Granted |
0 |
| Working Days Charged |
154 |
| Percent Time Used |
40 |
| Contractor(s) |
| GLENN FUQUA, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1814-01-010 INTERSTATE BARRICADES & MARKINGS, INC. (4.41%)
|
| Contract # |
01083208 |
|
Totals |
3559817.00 |
257968.26 |
1446120.40 |
40.6 |
|
| County | DUVAL |
| Highway |
FM 1329 |
| From |
3.149 MI N OF FM 716 WEST |
| To |
0.021 MI S OF FM 716 WEST |
| CSJ |
1982-01-016 |
| Proj ID |
STP 2008(420) |
| Work Type |
RESTORATION OF AN EXISTING HIGHWAY |
| |
|
3.170 |
1035734.65 |
414555.04 |
724499.29 |
69.9 |
| Work Order |
04-14-08 |
| Work Began |
07-01-08 |
| Work Completed |
|
| Time Computed |
04-30-08 |
| Contract Working Days |
99 |
| Addl Days Granted |
0 |
| Working Days Charged |
65 |
| Percent Time Used |
65 |
| Contractor(s) |
| J. CARROLL WEAVER, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 1982-01-016 HIGHWAY TECHNOLOGIES (1.28%) VAN - TECH LANDSCAPING & EROSION CONTROL, INC. (1.33%) INTERSTATE BARRICADES & MARKINGS, INC. (2.24%)
|
| Contract # |
03083217 |
|
Totals |
1035734.65 |
414555.04 |
724499.29 |
69.9 |
|
| County | WEBB |
| Highway |
FM 1472 |
| From |
0.4 MI N OF IH 35 WEST FRONTAGE RD |
| To |
IH 35 W FRONTAGE RD (DOT #446697K) |
| CSJ |
2150-04-034 |
| Proj ID |
STP 2005(828)RGS |
| Work Type |
GRAD, BASE, SURF, AND RR GRADE SEPR |
| |
|
0.719 |
31017779.79 |
252718.04 |
20622290.71 |
69.2 |
| Work Order |
09-27-05 |
| Work Began |
03-31-06 |
| Work Completed |
|
| Time Computed |
06-01-06 |
| Contract Working Days |
682 |
| Addl Days Granted |
359 |
| Working Days Charged |
733 |
| Percent Time Used |
70 |
| Contractor(s) |
| ROSIEK CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2150-04-034 PRICE CONSTRUCTION, LTD. ( 15.58%) REBAR SPECIALISTS(0.39%) SCOTT DERR PAINTING CO (0.14%) VIKING CONSTRUCTION, INC.(0.81%) CHOCTAW ERECTORS, INC. ( 10.14%) LONE STAR TRAFFIC SERVICE, INC.(0.12%) MICA CORPORATION (5.77%) PRIMATE CONSTRUCTION, INC. (0.08%) SOIL-TECH, INC.(0.15%) SOUTHWEST ROAD & SAFETY CONTRACTORS, LLC (0.17%) W. W. FOUNDATION DRILLING, LTD.(1.16%) HENRY'S CONSTRUCTION, INC. (1.26%) W.W. WEBBER, LLC (0.63%) UNITED RENTAL (CORPUS CHRISTI) (0.43%) CAMINO AGAVE, INC. (0.00%) JAVELINA CONSTRUCTION SOUTH, INC.(0.01%) GUAJARDO STEEL (0.35%) BATTEN DRILLING(0.11%) LAREDO CONCRETE CUTTING(0.08%) RAMOS CONCRETE, INC. (0.06%)
|
| Contract # |
08053006 |
|
Totals |
31017779.79 |
252718.04 |
20622290.71 |
69.2 |
|
| County | DIMMIT |
| Highway |
FM 2644 |
| From |
US 277 |
| To |
DIMMIT/MAVERICK COUNTY LINE |
| CSJ |
2636-02-007 |
| Proj ID |
STP 2006(488) |
| Work Type |
REHABILITATION OF AN EXISTING HWY |
| |
|
14.876 |
6353642.33 |
766595.42 |
2008531.82 |
31.6 |
| Work Order |
10-18-07 |
| Work Began |
01-09-08 |
| Work Completed |
|
| Time Computed |
01-09-08 |
| Contract Working Days |
252 |
| Addl Days Granted |
0 |
| Working Days Charged |
102 |
| Percent Time Used |
40 |
| Contractor(s) |
| E. E. HOOD & SONS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2636-02-007 FLASHER EQUIPMENT COMPANY(1.85%) DEPENDABLE FENCE & WELDING CO. (DEPENDABLE ENTERPRISES,INC.) (1.08%) VAN - TECH LANDSCAPING & EROSION CONTROL, INC. (0.44%)
|
| Contract # |
09073005 |
|
Totals |
6353642.33 |
766595.42 |
2008531.82 |
31.6 |
|