AVERAGE LOW BID UNIT PRICE - CONSTRUCTION - LAREDO DISTRICT

Last Update: Thursday, July 30, 2015
ITEMS 100 2001 TO 192 2026
Items Items Bid Code Range
0100 - 0192
0216 - 0292
0310 - 0360
0400 - 0499
0500 - 0552
0610 - 0690
0780 - 0780
1003 - 1150
2280 - 2323
3002 - 3278
5369 - 5445
6001 - 6834
8020 - 8961
100 2001 - 192 2026
Item No Description Units July 31, 2015 Twelve Month Moving Usage
Quantity Avg Bid Quantity Avg Bid
100 2001 PREPARING ROW AC     4.250 30,000.00000 1
100 2002 PREPARING ROW STA     94.440 25,010.05930 2
100 2008 PREPARING ROW (TREE) (0" TO 6" DIA) EA     19.000 390.60000 1
100 2009 PREPARING ROW (TREE) (6" TO 24" DIA) EA     14.000 1,369.60000 1
100 6002 PREPARING ROW STA 1,395.490 365.17488 1,451.490 360.53841 5
104 2001 REMOVING CONC (PAV) SY     4,132.000 7.50000 1
104 2009 REMOVING CONC (RIPRAP) SY     6,035.000 6.82368 2
104 2011 REMOVING CONC (MEDIANS) SY     240.000 6.70000 1
104 2013 REMOVING CONC (FOUNDATIONS) SY     32.000 35.30000 1
104 2015 REMOVING CONC (SIDEWALKS) SY     5,005.000 6.00000 1
104 2017 REMOVING CONC (DRIVEWAYS) SY     5,237.000 6.00000 1
104 2021 REMOVING CONC (CURB) LF     13,732.000 1.20000 1
104 2022 REMOVING CONC (CURB AND GUTTER) LF     20,914.000 1.70000 1
104 2024 REMOVING CONC (RETAINING WALLS) SY     235.000 42.80000 1
104 2032 REMOVING CONC (WHEELCHAIR RAMP) SY     239.000 9.00000 1
104 2037 REMOVE CONC (RAIL) LF     85.000 16.30000 1
104 2040 REMOVING CONC (PAVERS) SY     4,686.000 6.40000 1
104 2044 REMOVING CONC (FLUME) SY     712.000 7.50000 1
104 6001 REMOVING CONC (PAV) SY     279.000 18.25000 1
104 6009 REMOVING CONC (RIPRAP) SY 205.000 15.00000 405.000 16.48148 2
104 6010 REMOVING CONC (RIPRAP) CY     20.000 72.00000 1
104 6015 REMOVING CONC (SIDEWALKS) SY     263.000 11.00000 1
104 6017 REMOVING CONC (DRIVEWAYS) SY     692.080 11.50000 1
104 6022 REMOVING CONC (CURB AND GUTTER) LF 1,687.000 7.00000 1,687.000 7.00000 1
104 6032 REMOVING CONC (WHEELCHAIR RAMP) SY     25.000 11.75000 1
104 6036 REMOVING CONC (SIDEWALK OR RAMP) SY 326.000 14.00000 326.000 14.00000 1
104 6054 REMOVING CONCRETE (MOW STRIP) LF 9,019.000 12.52966 32,760.000 9.11950 7
105 2034 REMOVING STAB BASE AND ASPH PAV (1" - 9") SY     7,014.000 3.50000 1
105 2094 REMOVING STAB BASE & ASPH PAV (12" - 27") SY     70,536.000 6.80000 1
105 6015 REMOVING STAB BASE & ASPH PAV (8" - 10") SY     2,917.000 7.00000 1
105 6016 REMOVING STAB BASE & ASPH PAV (16") SY 4,227.000 10.00000 4,227.000 10.00000 1
105 6022 REMOVING STAB BASE AND ASPH PAV (13") SY 3,244.000 10.00000 3,244.000 10.00000 1
105 6087 REMOVING STAB BASE AND ASPH PAV (8.5") SY     36,457.000 10.00000 1
110 2001 EXCAVATION (ROADWAY) CY     46,531.000 7.50000 1
110 2003 EXCAVATION (SPECIAL) CY     4,485.000 12.00000 1
110 6001 EXCAVATION (ROADWAY) CY 4,341.000 15.18659 15,065.000 10.99623 3
112 6002 SUBGRADE WIDENING (DENS CONT) STA 478.600 621.74310 478.600 621.74310 2
132 2004 EMBANKMENT (FINAL) (DENS CONT) (TY B) CY     178,857.000 14.00000 1
132 2006 EMBANKMENT (FINAL) (DENS CONT) (TY C) CY     3,163.000 13.90000 1
132 2017 EMBANKMENT (VEHICLE) (ORD COMP) (TY A) CY     303.000 15.00000 1
132 6001 EMBANKMENT (FINAL) (ORD COMP) (TY A) CY 4,366.000 17.62156 6,547.000 14.68284 3
134 2001 BACKFILL (TY A) STA     502.000 150.00000 1
134 6001 BACKFILL (TY A) STA 1,553.970 123.07560 6,764.670 99.91181 7
150 2002 BLADING HR     208.000 53.50000 1
150 6002 BLADING HR 84.000 101.58000 84.000 101.58000 3
160 2005 FURNISHING AND PLACING TOPSOIL CY     3,990.000 9.60000 1
162 2002 BLOCK SODDING SY     12,422.000 5.10000 1
162 2003 STRAW OR HAY MULCH SY     50,418.000 .30000 1
164 2026 CELL FBR MLCH SEED (PERM) (URBAN) (SANDY) AC     3.500 2,675.00000 1
164 2030 CELL FBR MLCH SEED (TEMP) (WARM) AC     1.750 2,461.00000 1
164 2032 CELL FBR MLCH SEED (TEMP) (COOL) AC     1.750 2,461.00000 1
164 2041 DRILL SEEDING (TEMP) (WARM) SY     25,209.000 .20000 1
164 2043 DRILL SEEDING (TEMP) (COOL) SY     25,209.000 .20000 1
164 6035 DRILL SEEDING (PERM) (RURAL) (CLAY) SY 4,331.000 .50000 4,331.000 .50000 1
164 6036 DRILL SEEDING (PERM) (RURAL) (CLAY) AC 60.100 701.63228 60.100 701.63228 2
164 6039 DRILL SEEDING (PERM) (URBAN) (CLAY) SY     4.120 2.25000 1
164 6042 DRILL SEEDING (TEMP) (WARM) AC 60.100 485.35108 60.100 485.35108 2
166 2001 FERTILIZER AC     10.420 1,070.00000 1
168 2001 VEGETATIVE WATERING MG     6,278.700 16.10000 1
169 2002 SOIL RETENTION BLANKETS (CL 1) (TY B) SY     33,813.000 1.30000 1
169 2004 SOIL RETENTION BLANKETS (CL 1) (TY D) SY     871.000 4.80000 1
169 2007 SOIL RETENTION BLANKETS (CL 2) (TY G) SY     5,577.000 9.80000 1
170 2001 IRRIGATION SYSTEM LS     1.000 170,130.00000 1
192 2001 PLANT MATERIAL (4" CNTR) EA     200.000 18.20000 1
192 2006 PLANT MATERIAL (30 - GAL) EA     50.000 374.50000 1
192 2026 PLANT MATERIAL (65 GAL) (TREE) EA     27.000 1,230.50000 1