| Item No |
Description |
Units |
January 31, 2012 |
Twelve Month Moving |
Usage |
| Quantity |
Avg Bid |
Quantity |
Avg Bid |
| 500 2001 |
MOBILIZATION |
LS |
2.000 |
87,472.15000 |
14.000 |
79,000.85857 |
14 |
| 502 2001 |
BARRICADES, SIGNS AND TRAFFIC HANDLING |
MO |
9.000 |
3,459.26000 |
49.000 |
3,651.44367 |
11 |
| 502 2124 |
BARRICADES, SIGNS AND TRAFFIC HANDLING |
EA |
18.000 |
100.00000 |
31.000 |
138.71226 |
3 |
| 502 2125 |
BARR, SIGNS & TRF HANDLING ALT 1X |
EA |
1.000 |
100.00000 |
3.000 |
3,966.00000 |
3 |
| 502 2126 |
BARR, SIGNS & TRF HANDLING ALT 2X |
EA |
1.000 |
100.00000 |
3.000 |
5,929.00000 |
3 |
| 502 2127 |
BARR, SIGNS & TRF HANDLING ALT 3X |
EA |
1.000 |
100.00000 |
2.000 |
300.00000 |
2 |
| 502 2128 |
BARR, SIGNS & TRF HANDLING ALT 4X |
EA |
1.000 |
100.00000 |
2.000 |
300.00000 |
2 |
| 502 2129 |
BARR, SIGNS & TRF HANDLING ALT 5X |
EA |
1.000 |
100.00000 |
2.000 |
300.00000 |
2 |
| 502 2130 |
BARR, SIGNS & TRF HANDLING ALT 6X |
EA |
1.000 |
100.00000 |
2.000 |
300.00000 |
2 |
| 506 2002 |
ROCK FILTER DAMS (INSTALL) (TY 2) |
LF |
|
|
36.000 |
32.45000 |
1 |
| 506 2003 |
ROCK FILTER DAMS (INSTALL) (TY 3) |
LF |
295.000 |
35.40000 |
827.000 |
49.45526 |
3 |
| 506 2009 |
ROCK FILTER DAMS (REMOVE) |
LF |
295.000 |
19.43000 |
696.000 |
13.30553 |
2 |
| 506 2016 |
CONSTRUCTION EXITS (INSTALL) (TY 1) |
SY |
156.000 |
24.28000 |
1,092.000 |
31.75429 |
3 |
| 506 2019 |
CONSTRUCTION EXITS (REMOVE) |
SY |
156.000 |
12.95000 |
1,092.000 |
16.85000 |
3 |
| 506 2024 |
BACKHOE WORK (EROSION & SEDM CONT) |
HR |
98.000 |
50.33000 |
181.000 |
65.03503 |
3 |
| 506 2034 |
TEMPORARY SEDIMENT CONTROL FENCE |
LF |
3,895.000 |
1.35000 |
7,473.000 |
2.58565 |
5 |
| 510 2001 |
ONE - WAY TRAFFIC CONTROL |
HR |
1,100.000 |
13.07000 |
3,500.000 |
63.06120 |
8 |
| 512 2005 |
PORT CTB (FUR & INST) (SNGL SLP) (TY 2) |
LF |
|
|
2,040.000 |
9.40000 |
1 |
| 512 2014 |
PORT CTB (DES SOURCE) (SNGL SLP) (TY 2) |
LF |
360.000 |
10.71000 |
360.000 |
10.71000 |
1 |
| 512 2023 |
PORT CTB (MOVE) (SNGL SLP) (TY 2) |
LF |
1,080.000 |
8.92000 |
7,710.000 |
7.39794 |
2 |
| 512 2032 |
PORT CTB (STKPL) (SNGL SLP) (TY 2) |
LF |
360.000 |
10.71000 |
2,400.000 |
6.02650 |
2 |
| 529 2004 |
CONC CURB & GUTTER (TY II) |
LF |
|
|
40.000 |
36.50000 |
1 |
| 529 2006 |
CONC CURB (MONO) (TY II) |
LF |
|
|
67.000 |
36.50000 |
1 |
| 530 2007 |
DRIVEWAYS (CONC) |
EA |
1.000 |
3,555.51000 |
1.000 |
3,555.51000 |
1 |
| 530 2008 |
DRIVEWAYS (ACP) |
EA |
|
|
15.000 |
3,000.00000 |
1 |
| 530 2014 |
TURNOUTS (ACP) |
EA |
|
|
3.000 |
5,100.00000 |
1 |
| 530 2015 |
TURNOUTS (SURF TREAT) |
EA |
16.000 |
2,781.40000 |
16.000 |
2,781.40000 |
1 |
| 531 2020 |
CURB RAMPS (TY 2) (MOD) |
EA |
|
|
1.000 |
2,435.00000 |
1 |
| 531 2023 |
CURB RAMPS (TY 1) (SPL) |
EA |
|
|
2.000 |
1,825.00000 |
1 |
| 531 2047 |
CURB RAMPS (TY 5) (MOD) |
EA |
|
|
1.000 |
1,825.00000 |
1 |
| 531 2062 |
CURB RAMPS (TY 21) (MOD) |
EA |
|
|
1.000 |
1,825.00000 |
1 |
| 533 2001 |
SHOULDER TEXTURING (MILLED) |
STA |
|
|
749.000 |
15.00000 |
1 |
| 540 2001 |
MTL W - BEAM GD FEN (TIM POST) |
LF |
1,100.000 |
18.50000 |
7,162.500 |
17.32461 |
3 |
| 540 2005 |
TERMINAL ANCHOR SECTION |
EA |
|
|
2.000 |
622.60000 |
1 |
| 540 2013 |
MTL BEAM GD FEN TRANS (T101) |
EA |
8.000 |
960.00000 |
16.000 |
897.50000 |
2 |
| 542 2001 |
REMOVING METAL BEAM GUARD FENCE |
LF |
800.000 |
2.50000 |
5,408.000 |
2.07396 |
2 |
| 542 2002 |
REMOVING TERMINAL ANCHOR SECTION |
EA |
8.000 |
160.00000 |
22.000 |
128.18182 |
2 |
| 544 2001 |
GUARDRAIL END TREATMENT (INSTALL) |
EA |
8.000 |
2,115.00000 |
40.000 |
2,011.00000 |
2 |
| 544 2003 |
GUARDRAIL END TREATMENT (REMOVE) |
EA |
|
|
18.000 |
240.00000 |
1 |
| 544 2004 |
GDRAIL END TRT (INST) (WOOD POST) (TY I) |
EA |
|
|
2.000 |
2,128.50000 |
1 |
| 545 2001 |
CRASH CUSH ATTEN (INSTL) |
EA |
2.000 |
2,500.00000 |
10.000 |
7,288.00000 |
2 |
| 545 2002 |
CRASH CUSH ATTEN (MOVE & RESET) |
EA |
6.000 |
2,250.00000 |
32.000 |
1,433.43750 |
2 |
| 545 2003 |
CRASH CUSH ATTEN (REMOVE) |
EA |
2.000 |
850.00000 |
10.000 |
610.00000 |
2 |
| 560 2019 |
MAILBOX INSTALL - S (WC - POST) TY 3FND - AB |
EA |
33.000 |
75.00000 |
33.000 |
75.00000 |
1 |
| 560 2020 |
MAILBOX INSTALL - M (WC - POST) TY 3FND - AB |
EA |
19.000 |
275.00000 |
19.000 |
275.00000 |
1 |