Monthly State Let Construction Report For Lubbock District As Of Jul 12, 2016 Page 2 Of 2

Last Update: Tuesday, July 12, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyDAWSON
Highway FM 26
From US 87
To FM 828
CSJ 0637-01-011
Proj ID STP 2015(768)
Work Type SUBGRADE WIDENING BASE SC PAVE MRKS
 
5.273 2978473.01 -8026.08 2902210.59 97.7
CountyDAWSON
Highway FM 26
From FM 828
To MARTIN CO LINE
CSJ 1749-01-007
Proj ID C 1749-1-7
Work Type SUBGRADEWIDE BASE SURF TREAT & PVEMRK
 
4.146 2551788.51 19500.00 2581168.94 99.9
Work Order 06-01-15
Work Began 07-06-15
Work Completed  
Time Computed 07-02-15
Contract Working Days 124
Addl Days Granted 0
Working Days Charged 133
Percent Time Used 107
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0637-01-011
E. DIAZ TRUCKING (1.16%)
BARRICADES UNLIMITED (1.29%)
BLACK JACK ENERGY SERVICES ( 49.56%)
W.S. CONSTRUCTION COMPANY(1.84%)
Contract # 03153031
Totals 5530261.52 11473.92 5483379.53 99.3

CountyLUBBOCK
Highway SL 289
From IH 27 (FRONTAGE RDS)
To 0.334 MI W OF FM 1730 (SLIDE RD)
CSJ 0783-01-099
Proj ID NH 1602(203)
Work Type MILL HOTMIX INLAY
 
4.992 7588838.60 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-22-16
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 85
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0783-01-099
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05163233
Totals 7588838.60 0.00 0.00 0.0

CountyLUBBOCK
Highway SL 289
From 1000 FEET NORTH OF US 84
To 1000 FEET SOUTH OF US 84
CSJ 0783-01-100
Proj ID NH 2016(886)
Work Type BRIDGE REPAIR
 
0.378 199534.00 194601.40 194601.40 97.5
Work Order 04-08-16
Work Began 06-07-16
Work Completed  
Time Computed 05-09-16
Contract Working Days 14
Addl Days Granted 0
Working Days Charged 8
Percent Time Used 57
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0783-01-100
BARRICADES UNLIMITED ( 15.14%)
Contract # 03163029
Totals 199534.00 194601.40 194601.40 97.5

CountyHOCKLEY
Highway FM 597
From FM 168
To LUBBOCK COUNTY LINE
CSJ 0874-07-006
Proj ID STP 2015(766)
Work Type MILL, STABILIZE, 2 COURSE SURF TREAT
 
5.302 3845414.81 576360.36 1699849.41 44.2
Work Order 05-08-15
Work Began 07-06-15
Work Completed  
Time Computed 06-08-15
Contract Working Days 139
Addl Days Granted 0
Working Days Charged 99
Percent Time Used 71
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0874-07-006
BARRICADES UNLIMITED (1.29%)
E. DIAZ TRUCKING (6.00%)
Contract # 03153228
Totals 3845414.81 576360.36 1699849.41 44.2

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-074
Proj ID STP 2016(691)
Work Type PAVEMENT MARKERS
 
0.001 3617791.56 560541.48 923780.40 25.5
Work Order 03-15-16
Work Began 05-09-16
Work Completed  
Time Computed 04-14-16
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 32
Percent Time Used 32
Contractor(s)
PMI PAVEMENT MARKING, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-074
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163021
Totals 3617791.56 560541.48 923780.40 25.5

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To THE LUBBOCK DISTRICT
CSJ 0905-00-079
Proj ID STP 1502(337)
Work Type CONSTRUCT CURB RAMPS
 
0.001 2988537.45 398417.96 1479711.28 49.5
Work Order 08-26-15
Work Began 01-18-16
Work Completed  
Time Computed 09-25-15
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 183
Percent Time Used 85
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-079
W.S. CONSTRUCTION COMPANY(9.29%)
ONE WAY CONCRETE ( 55.37%)
Contract # 06153048
Totals 2988537.45 398417.96 1479711.28 49.5

CountyLUBBOCK
Highway VA
From VARIOUS LOCATIONS IN
To ALONG IH 27
CSJ 0905-00-083
Proj ID STP 2015(229)
Work Type PUMP STATION REPAIR
 
0.001 2141840.00 1067890.00 1656320.00 77.3
Work Order 07-16-15
Work Began 10-09-15
Work Completed  
Time Computed 08-16-15
Contract Working Days 190
Addl Days Granted 0
Working Days Charged 140
Percent Time Used 73
Contractor(s)
AUSTIN ENGINEERING CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-083
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06153263
Totals 2141840.00 1067890.00 1656320.00 77.3

CountyLUBBOCK
Highway CS
From NORTH UNIVERSITY, FROM AMHERST ST.
To US 82 IN LUBBOCK
CSJ 0905-06-090
Proj ID STP 2014(148)TE
Work Type SIDEWALKS, C & G, RAMPS AND LIGHTING
 
0.437 940883.20 2000.00 522271.43 55.5
Work Order 01-29-16
Work Began 02-29-16
Work Completed  
Time Computed 02-29-16
Contract Working Days 82
Addl Days Granted 0
Working Days Charged 78
Percent Time Used 95
Contractor(s)
TI-ZACK CONCRETE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-090
SPEEDY PAVING(6.60%)
ARTEX ELECTRIC, INC. ( 31.19%)
Contract # 08153224
Totals 940883.20 2000.00 522271.43 55.5

CountySWISHER
Highway VA
From HALE COUNTY LINE
To RANDALL COUNTY LINE
CSJ 0905-17-013
Proj ID NH 2016(692)
Work Type REMOVAL & INSTALL OF LG GUIDE SIGNS
 
30.700 280506.80 75240.00 195359.50 69.6
Work Order 03-18-16
Work Began 03-29-16
Work Completed  
Time Computed 04-18-16
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 34
Percent Time Used 37
Contractor(s)
ODUM SERVICES, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0905-17-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02163216
Totals 280506.80 75240.00 195359.50 69.6

CountyLUBBOCK
Highway FM 400
From 0.25 MILES NORTH OF NFDMF BRAZOS
To 0.25 MILES SOUTH OF NFDMF BRAZOS
CSJ 1041-02-039
Proj ID BR 1502(582)
Work Type REMOVE AND REPLACE BRIDGE
 
0.500 2349749.85 596871.47 596871.47 25.4
Work Order 11-24-15
Work Began 06-01-16
Work Completed  
Time Computed 06-01-16
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 30
Contractor(s)
KIEWIT INFRASTRUCTURE SOUTH CO.
SUBCONTRACTOR(S) FOR CCSJ: 1041-02-039
BARRICADES UNLIMITED (0.23%)
V-TECH ENVIRONMENTAL SERVICES(0.66%)
W. W. FOUNDATION DRILLING, LTD.(7.11%)
COMEN ENTERPRISE (1.28%)
MCL CONTRACTING, LLC (0.00%)
LONE STAR HIGHWAY PRODUCTS, INC. (2.93%)
Contract # 08153042
Totals 2349749.85 596871.47 596871.47 25.4

CountyLUBBOCK
Highway FM 1730
From 200 FEET NORTH OF 98TH ST.
To 1000 FEET SOUTH OF FM 1585
CSJ 1344-02-019
Proj ID STP 2014(479)MM
Work Type GRAD, BASE, ACP, STR, SET, C & G
 
2.246 14189419.37 904769.65 11680384.18 82.0
Work Order 05-14-14
Work Began 06-02-14
Work Completed  
Time Computed 07-10-14
Contract Working Days 340
Addl Days Granted 167
Working Days Charged 463
Percent Time Used 91
Contractor(s)
ALLEN BUTLER CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 1344-02-019
ARTEX ELECTRIC CO. (1.06%)
BARRICADES UNLIMITED (1.39%)
CMT ENGINEERING, INC.(0.40%)
TEX OP CONSTRUCTION, LP(0.54%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.99%)
FLOYD TRUCKING, INC. (5.10%)
V-TECH ENVIRONMENTAL SERVICES(0.48%)
VANN/ELLI, INC.(0.78%)
TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (0.16%)
DOUBLE R LAWN AND LANDSCAPE(0.02%)
UTILITY CONTRACTORS OF AMERICA, LTD(6.67%)
ROYAL CONCRETE (0.47%)
CEMTECH CONCRETE (0.49%)
Contract # 03143002
Totals 14189419.37 904769.65 11680384.18 82.0

page 1 | page 2