| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | BAILEY |
| Highway |
US 70 |
| From |
UVALDE STREET IN MULESHOE |
| To |
EAST 6TH STREET IN MULESHOE |
| CSJ |
0052-02-033 |
| Proj ID |
NH 2012(201) |
| Work Type |
SALVAGE, BASE TREATMENT AND ACP |
| |
|
2.436 |
6024404.49 |
698081.53 |
3592197.15 |
59.6 |
| Work Order |
02-17-12 |
| Work Began |
04-17-12 |
| Work Completed |
|
| Time Computed |
04-17-12 |
| Contract Working Days |
238 |
| Addl Days Granted |
0 |
| Working Days Charged |
195 |
| Percent Time Used |
81 |
| Contractor(s) |
| J. LEE MILLIGAN, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0052-02-033 WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(1.56%) HIGHWAY TECHNOLOGIES, INC. (0.82%) RAY ELECTRIC COMPANY (0.04%)
|
| Contract # |
01123004 |
|
Totals |
6024404.49 |
698081.53 |
3592197.15 |
59.6 |
|
| County | LAMB |
| Highway |
LP 430 ETC |
| From |
WEST US 84 |
| To |
EAST 84 |
| CSJ |
0052-13-004 |
| Proj ID |
STP 2013(155) |
| Work Type |
SEAL COAT |
| |
|
207.731 |
10295048.31 |
796075.00 |
1370409.00 |
13.3 |
| Work Order |
11-30-12 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
12-16-12 |
| Contract Working Days |
57 |
| Addl Days Granted |
8 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| LIPHAM ASPHALT AND PAVING COMPANY, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 0052-13-004 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11123204 |
|
Totals |
10295048.31 |
796075.00 |
1370409.00 |
13.3 |
|
| County | LUBBOCK |
| Highway |
US 84 |
| From |
5TH STREET |
| To |
IH 27 |
| CSJ |
0053-18-040 |
| Proj ID |
STP 2013(325) |
| Work Type |
UTBHMWC AND PAVEMENT MARKINGS |
| |
|
3.800 |
1521813.12 |
0.00 |
9964.37 |
0.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
03-26-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
27 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| CLARK CONSTRUCTION OF TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0053-18-040 FLOYD TRUCKING, INC. (2.99%)
|
| Contract # |
01133019 |
|
Totals |
1521813.12 |
0.00 |
9964.37 |
0.6 |
|
| County | HALE |
| Highway |
IH 27 |
| From |
NORTH OF US 70 |
| To |
SH 194 |
| CSJ |
0067-04-039 |
| Proj ID |
IM 0277(090) |
| Work Type |
GRAD, ASB, ACP, CONC PAV, STR, BR |
| |
|
1.400 |
4693021.10 |
0.00 |
91221.10 |
1.9 |
| County | HALE |
| Highway |
IH 27 |
| From |
SOUTH FM 3466 |
| To |
NORTH OF US 70 |
| CSJ |
0067-05-042 |
| Proj ID |
IM 0277(090) |
| Work Type |
GRAD, ASB, ACP, CONC PAV, STR, BR |
| |
|
0.927 |
15256193.45 |
315745.90 |
3260596.69 |
21.3 |
| Work Order |
09-13-12 |
| Work Began |
01-14-13 |
| Work Completed |
|
| Time Computed |
01-08-13 |
| Contract Working Days |
340 |
| Addl Days Granted |
0 |
| Working Days Charged |
81 |
| Percent Time Used |
23 |
| Contractor(s) |
| HAYDON BUILDING CORP. |
SUBCONTRACTOR(S) FOR CCSJ: 0067-05-042 WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(0.33%) DUSTROL, INC.(0.41%) NORTH TEXAS REBAR, LLC (2.65%) RICE ENVIRONMENTAL SERVICES(0.30%) SCOTT DERR PAINTING CO, LLC(0.14%) WEST TEXAS PAVING, INC.( 13.40%) FLOYD TRUCKING, INC. (0.00%) WILLIS ELECTRIC CO., LP(2.78%) TOTAL HIGHWAY MAINTENANCE, LLC (1.84%) TRUMBLE CRANE & RIGGING(0.00%) RMI WORLDWIDE, LLC (0.21%) W. W. FOUNDATION DRILLING, LTD.(0.45%) CMT ENGINEERING, INC.(0.00%) MICA CORPORATION (0.24%) EARTH REINFORCEMENT SPECIALISTS(2.66%) DRILL PIER CONSTRUCTION, LLC (0.87%)
|
| Contract # |
07123005 |
|
Totals |
19949214.55 |
315745.90 |
3351817.79 |
16.8 |
|
| County | DAWSON |
| Highway |
US 87 |
| From |
MARTIN COUNTY LINE |
| To |
SOUTH Y IN LAMESA |
| CSJ |
0068-05-033 |
| Proj ID |
NH 2013(756) |
| Work Type |
PLANING, REWORK BASE, ACP & ONE CRSE |
| |
|
19.326 |
11239069.78 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
150 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| DUININCK, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0068-05-033 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05133206 |
|
Totals |
11239069.78 |
0.00 |
0.00 |
0.0 |
|
| County | FLOYD |
| Highway |
US 70 |
| From |
HALE COUNTY LINE |
| To |
TEXAS STREET IN FLOYDADA |
| CSJ |
0145-06-023 |
| Proj ID |
STP 2012(256) |
| Work Type |
LEVEL - UP AND OVERLAY |
| |
|
18.017 |
18689402.80 |
1246884.40 |
2995593.90 |
16.0 |
| Work Order |
02-22-12 |
| Work Began |
03-26-13 |
| Work Completed |
|
| Time Computed |
03-09-12 |
| Contract Working Days |
130 |
| Addl Days Granted |
0 |
| Working Days Charged |
99 |
| Percent Time Used |
76 |
| Contractor(s) |
| J. LEE MILLIGAN, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0145-06-023 DUSTROL, INC.(0.22%) WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(1.45%)
|
| Contract # |
01123201 |
|
Totals |
18689402.80 |
1246884.40 |
2995593.90 |
16.0 |
|
| County | TERRY |
| Highway |
US 62 |
| From |
0.336 MILE NORTH OF US 385 |
| To |
INTERSECTION OF US 82 |
| CSJ |
0227-07-039 |
| Proj ID |
NH 2013(326) |
| Work Type |
MILL, REWORK BASE, SC, ACP, CRCP |
| |
|
3.129 |
10645068.78 |
667725.54 |
1565413.75 |
14.7 |
| Work Order |
02-28-13 |
| Work Began |
03-13-13 |
| Work Completed |
|
| Time Computed |
03-13-13 |
| Contract Working Days |
259 |
| Addl Days Granted |
0 |
| Working Days Charged |
35 |
| Percent Time Used |
13 |
| Contractor(s) |
| ALLEN BUTLER CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0227-07-039 TEX OP CONSTRUCTION, LP(2.56%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.19%) CMT ENGINEERING, INC.(0.96%) V-TECH ENVIRONMENTAL SERVICES(0.17%) WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(2.47%) FLOYD TRUCKING, INC. (5.61%)
|
| Contract # |
01133001 |
|
Totals |
10645068.78 |
667725.54 |
1565413.75 |
14.7 |
|
| County | TERRY |
| Highway |
US 62 |
| From |
1500' NORTH OF GAINES COUNTY LINE |
| To |
FM 213 IN WELLMAN |
| CSJ |
0228-01-055 |
| Proj ID |
NH 2013(327) |
| Work Type |
MICROSURFACE OVERLAY AND PVMT MKRS |
| |
|
8.549 |
875983.38 |
0.00 |
207442.34 |
23.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
03-19-13 |
| Work Began |
04-22-13 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
24 |
| Addl Days Granted |
0 |
| Working Days Charged |
3 |
| Percent Time Used |
12 |
| Contractor(s) |
| INTERMOUNTAIN SLURRY SEAL, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0228-01-055 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01133216 |
|
Totals |
875983.38 |
0.00 |
207442.34 |
23.6 |
|
| County | LUBBOCK |
| Highway |
US 62 |
| From |
0.499 MI WEST OF MILWAUKEE AVE |
| To |
0.297 MI EAST OF MILWAUKEE AVE |
| CSJ |
0380-01-081 |
| Proj ID |
NH 2012(767) |
| Work Type |
GRD, ACP, CRCP, TREAT SUBGRD, CG, STR OP |
| |
|
1.393 |
22428061.92 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-10-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
469 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| HAYDON BUILDING CORP. |
SUBCONTRACTOR(S) FOR CCSJ: 0380-01-081 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02133002 |
|
Totals |
22428061.92 |
0.00 |
0.00 |
0.0 |
|
| County | LUBBOCK |
| Highway |
LP 289 |
| From |
990 FEET EAST OF SLIDE ROAD |
| To |
2585 FEET EAST OF QUAKER AVENUE |
| CSJ |
0783-02-084 |
| Proj ID |
C 783-2-84 |
| Work Type |
GR, BASE, STR, ASB, ACP, OVERPASS |
| |
|
1.620 |
26923572.74 |
950753.13 |
7277838.69 |
27.0 |
| Work Order |
09-24-12 |
| Work Began |
11-12-12 |
| Work Completed |
|
| Time Computed |
11-12-12 |
| Contract Working Days |
581 |
| Addl Days Granted |
0 |
| Working Days Charged |
116 |
| Percent Time Used |
19 |
| Contractor(s) |
| HAYDON BUILDING CORP. |
SUBCONTRACTOR(S) FOR CCSJ: 0783-02-084 RICE ENVIRONMENTAL SERVICES(1.84%) TOM"S TREE PLACE (1.09%) WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(0.31%) TOTAL HIGHWAY MAINTENANCE, LLC (1.14%) DRILL PIER CONSTRUCTION, LLC (0.00%) ARTEX ELECTRIC, INC. (0.01%) MICA CORPORATION (0.95%) A & A CONSTRUCTION (0.36%) BUILDER SERVICES CO. (0.24%) S & S PAINTING (0.12%) TEX OP CONSTRUCTION, LP(0.59%) WEST TEXAS PAVING, INC.( 15.59%) CMT ENGINEERING, INC.(0.07%) FARR FOUNDATION, INC.(0.53%) W. W. FOUNDATION DRILLING, LTD.(1.34%) TRUMBLE CRANE & RIGGING(0.32%) NORTH TEXAS REBAR, LLC (0.00%) WILLIS ELECTRIC CO., LP(5.48%) FLOYD TRUCKING, INC. (0.00%)
|
| Contract # |
07123204 |
|
Totals |
26923572.74 |
950753.13 |
7277838.69 |
27.0 |
|
| County | LAMB |
| Highway |
FM 37 |
| From |
US 385 |
| To |
FM 1072 |
| CSJ |
0884-04-008 |
| Proj ID |
STP 1102(397) |
| Work Type |
BASE CEMENT STAB, & TWO CRSE |
| |
|
5.853 |
2234275.15 |
3264.71 |
1796817.13 |
80.4 |
| Work Order |
08-16-11 |
| Work Began |
05-16-12 |
| Work Completed |
|
| Time Computed |
04-01-12 |
| Contract Working Days |
213 |
| Addl Days Granted |
0 |
| Working Days Charged |
138 |
| Percent Time Used |
64 |
| Contractor(s) |
| REECE ALBERT, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0884-04-008 WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(3.18%) CAMPBELL-WEST, LLC (1.67%) HIGHWAY TECHNOLOGIES, INC. (0.99%) BLACK TOPPER TECHNOLOGY, INC.(2.10%)
|
| Contract # |
07113060 |
|
Totals |
2234275.15 |
3264.71 |
1796817.13 |
80.4 |
|
| County | LUBBOCK |
| Highway |
VA |
| From |
VARIOUS LOCATIONS IN |
| To |
THE LUBBOCK DISTRICT |
| CSJ |
0905-00-063 |
| Proj ID |
STP 2013(391) |
| Work Type |
FY 2013 PAVEMENT MARKERS |
| |
|
0.001 |
2755904.20 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-17-13 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
05-03-13 |
| Contract Working Days |
100 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| L&L COMPANY |
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-063 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02133217 |
|
Totals |
2755904.20 |
0.00 |
0.00 |
0.0 |
|
| County | LUBBOCK |
| Highway |
VA |
| From |
VARIOUS LOCATIONS IN |
| To |
THE LUBBOCK DISTRICT |
| CSJ |
0905-00-067 |
| Proj ID |
STP 2013(392) |
| Work Type |
RRPMS AND SPECIALITY MARKINGS |
| |
|
0.001 |
334626.48 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
05-01-13 |
| Contract Working Days |
80 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| DRS CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-067 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02133015 |
|
Totals |
334626.48 |
0.00 |
0.00 |
0.0 |
|
| County | LUBBOCK |
| Highway |
VA |
| From |
VARIOUS LOCATIONS IN |
| To |
THE LUBBOCK DISTRICT |
| CSJ |
0905-00-068 |
| Proj ID |
STP 2012(485) |
| Work Type |
PAVEMENT REPAIR |
| |
|
11.737 |
2091830.24 |
0.00 |
359575.85 |
17.1 |
| Work Order |
04-17-12 |
| Work Began |
09-04-12 |
| Work Completed |
|
| Time Computed |
08-01-12 |
| Contract Working Days |
60 |
| Addl Days Granted |
0 |
| Working Days Charged |
15 |
| Percent Time Used |
25 |
| Contractor(s) |
| J. LEE MILLIGAN, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-068 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03123227 |
|
Totals |
2091830.24 |
0.00 |
359575.85 |
17.1 |
|
| County | LUBBOCK |
| Highway |
VA |
| From |
VARIOUS LOCATIONS IN |
| To |
THE LUBBOCK DISTRICT |
| CSJ |
0905-00-070 |
| Proj ID |
STP 2013(154) |
| Work Type |
FY 2013 ADA COMPLIANCE |
| |
|
0.001 |
1488393.00 |
249276.52 |
446223.43 |
29.9 |
| Work Order |
01-17-13 |
| Work Began |
03-11-13 |
| Work Completed |
|
| Time Computed |
02-02-13 |
| Contract Working Days |
188 |
| Addl Days Granted |
0 |
| Working Days Charged |
38 |
| Percent Time Used |
20 |
| Contractor(s) |
| TI-ZACK CONCRETE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0905-00-070 ONE WAY CONCRETE ( 41.09%) WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(0.63%) HIGHWAY TECHNOLOGIES, INC. (0.97%)
|
| Contract # |
11123015 |
|
Totals |
1488393.00 |
249276.52 |
446223.43 |
29.9 |
|
| County | LUBBOCK |
| Highway |
CS |
| From |
SLIDE ROAD, FROM US 84 |
| To |
MARSHALL STREET |
| CSJ |
0905-06-081 |
| Proj ID |
STP 2013(019)MM |
| Work Type |
GRAD, BASE, C & G, ACP, STR |
| |
|
1.482 |
5440142.31 |
0.00 |
1381847.72 |
25.4 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-19-13 |
| Work Began |
03-11-13 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
148 |
| Addl Days Granted |
0 |
| Working Days Charged |
36 |
| Percent Time Used |
24 |
| Contractor(s) |
| DUININCK, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0905-06-081 TEXAS ALTERNATIVE GRASSER, INC.(0.52%) FLOYD TRUCKING, INC. (1.23%) LONE STAR HIGHWAY PRODUCTS, INC. (4.72%) CAMPBELL-WEST INFRASTRUCTURE CONSTRUCTION, LLC (5.79%) HIGHWAY TECHNOLOGIES, INC. (0.17%) RURAL ELECTRIC, INC. (6.60%) TEX OP CONSTRUCTION, LP(0.23%) TOTAL HIGHWAY MAINTENANCE, LLC (0.69%) W.O.E. CONSTRUCTION(0.54%) PEREZ REBAR CONSTRUCTION (0.00%)
|
| Contract # |
12123225 |
|
Totals |
5440142.31 |
0.00 |
1381847.72 |
25.4 |
|
| County | LUBBOCK |
| Highway |
FM 2255 |
| From |
1500 FT WEST OF UPLAND AVE |
| To |
500 FT WEST OF FM 2528 |
| CSJ |
2256-01-019 |
| Proj ID |
STP 1102(398) |
| Work Type |
GRAD, BASE, C & G, ACP, STR |
| |
|
2.193 |
7401462.21 |
29402.31 |
6388204.35 |
86.4 |
| Work Order |
08-11-11 |
| Work Began |
09-06-11 |
| Work Completed |
|
| Time Computed |
09-06-11 |
| Contract Working Days |
282 |
| Addl Days Granted |
30 |
| Working Days Charged |
273 |
| Percent Time Used |
87 |
| Contractor(s) |
| ALLEN BUTLER CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 2256-01-019 ARTEX ELECTRIC, INC. (2.70%) BACK TO NATURE (1.17%) WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(2.19%) CMT ENGINEERING, INC.(0.93%) TEXAS ENVIRONMENTAL MANAGEMENT - SAN ANTONIO, INC. (1.29%) TOTAL HIGHWAY MAINTENANCE, LLC (1.21%) V-TECH ENVIRONMENTAL SERVICES(0.27%) HUGO REED & ASSOCIATES, INC. (0.33%) TEX OP CONSTRUCTION, LP(0.96%) WILLIS ELECTRIC CO., LP(1.41%)
|
| Contract # |
07113240 |
|
Totals |
7401462.21 |
29402.31 |
6388204.35 |
86.4 |
|