Monthly State Let Maintenance Report For Fort Worth District As Of Nov 9, 2016 Page 2 Of 3

Last Update: Wednesday, November 9, 2016
FTP Icon
page 1 | page 2 | page 3

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTARRANT
Highway IH0820
From VARIOUS ROADWAYS WITHIN
To SOUTH TARRANT & JOHNSON COUNTY
CSJ 6272-53-001
Proj ID RMC - 627253001
Work Type REFLECTORIZED PAVEMENT MARKINGS
 
0.010 1427188.62 0.00 1147593.52 83.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-04-15
Work Began 05-11-15
Work Completed  
Time Computed 05-11-15
Contract Working Days 98
Addl Days Granted 0
Working Days Charged 166
Percent Time Used 169
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08144001
Totals 1427188.62 0.00 1147593.52 83.6

CountyERATH
Highway US0281
From VARIOUS ROADWAYS WITHIN
To HOOD/SOMMERVELL ERATH COUNTIES
CSJ 6273-55-001
Proj ID RMC - 627355001
Work Type CLEANING & SEALING JOINTS & CRACKS
 
0.010 603719.00 0.00 748436.80 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-10-15
Work Began 02-11-15
Work Completed  
Time Computed 02-17-15
Contract Working Days 57
Addl Days Granted 14
Working Days Charged 25
Percent Time Used 35
Contractor(s)
BICK'S CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12144006
Totals 603719.00 0.00 748436.80 99.9

CountyJOHNSON
Highway SH0171
From VARIOUS ROADWAYS IN
To JOHNSON COUNTY
CSJ 6281-09-001
Proj ID RMC - 628109001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 639283.20 0.00 3119697.30 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-25-15
Work Began 00-00-00
Work Completed  
Time Computed 04-01-15
Contract Working Days 25
Addl Days Granted 25
Working Days Charged 50
Percent Time Used 100
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12144011
Totals 639283.20 0.00 3119697.30 99.9

CountyTARRANT
Highway IH0820
From VARIOUS ROADWAYS IN
To NORTH TARRANT COUNTY
CSJ 6281-24-001
Proj ID RMC - 628124001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 659900.00 0.00 1550104.14 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 23
Percent Time Used 92
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6281-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12144211
Totals 659900.00 0.00 1550104.14 99.9

CountyTARRANT
Highway IH0035W
From VARIOUS BRIDGES IN
To THE FORT WORTH DISTRICT
CSJ 6283-26-001
Proj ID BPM - 628326001
Work Type BRIDGE REPAIR
 
0.010 689452.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 184
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
SCOTT TUCKER CONSTRUCTION COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6283-26-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08164003
Totals 689452.00 0.00 0.00 0.0

CountyTARRANT
Highway US0377
From VARIOUS LOCATIONS IN TARRANT, JOHNSON,
To AND PARKER COUNTIES
CSJ 6284-11-001
Proj ID RMC - 628411001
Work Type TARFFIC SIGNAL MAINTENANCE
 
0.020 580600.00 0.00 53549.60 9.2
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-20-16
Work Began 00-00-00
Work Completed  
Time Computed 07-25-16
Contract Working Days 302
Addl Days Granted 1
Working Days Charged 69
Percent Time Used 22
Contractor(s)
STAR OPERATIONS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6284-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08154007
Totals 580600.00 0.00 53549.60 9.2

CountyTARRANT
Highway SH0121
From SYLVANIA BRIDGE OVER SH 121
To IN NORTH TARRANT COUNTY
CSJ 6287-32-001
Proj ID RMC - 628732001
Work Type BRIDGE REPAIR
 
0.010 368879.50 0.00 370980.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-26-16
Work Began 09-26-16
Work Completed  
Time Computed 09-26-16
Contract Working Days 32
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 62
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6287-32-001
CROSSROADS, L.P. (5.81%)
Contract # 12154218
Totals 368879.50 0.00 370980.00 99.9

CountyTARRANT
Highway IH0030
From VARIOUS ROADWAYS IN
To SOUTH TARRANT COUNTY
CSJ 6287-56-001
Proj ID RMC - 628756001
Work Type SWEEPING AND DEBRIS REMOVAL
 
0.010 738774.11 37558.13 306937.41 46.1
Work Order 02-08-16
Work Began 02-08-16
Work Completed  
Time Computed 02-16-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 231
Percent Time Used 63
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6287-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12154002
Totals 738774.11 37558.13 306937.41 46.1

CountyTARRANT
Highway IH0820
From VARIOUS ROADWAYS IN
To NORTH TARRANT COUNTY
CSJ 6287-57-001
Proj ID RMC - 628757001
Work Type SWEEPING & DEBRIS REMOVAL
 
0.010 421504.75 0.00 184018.20 43.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-01-16
Work Began 03-02-16
Work Completed  
Time Computed 03-01-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 239
Percent Time Used 65
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6287-57-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12154214
Totals 421504.75 0.00 184018.20 43.6

CountyTARRANT
Highway SH0360
From SH 360 FRONTAGE ROADS
To IN SOUTH TARRANT COUNTY
CSJ 6287-71-001
Proj ID RMC - 628771001
Work Type MILL & OVERLAY, MISC ROADWAY WORK
 
2.111 1855641.58 0.00 1814228.62 97.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-08-15
Work Began 09-22-15
Work Completed  
Time Computed 09-15-15
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 78
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 6287-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06154202
Totals 1855641.58 0.00 1814228.62 97.7

CountyTARRANT
Highway IH0030
From VARIOUS ROADWAYS IN
To SOUTH TARRANT COUNTY
CSJ 6288-08-001
Proj ID RMC - 628808001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 899300.00 192266.55 846841.71 94.5
Work Order 09-28-15
Work Began 09-30-15
Work Completed  
Time Computed 10-05-15
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 65
Percent Time Used 108
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06154201
Totals 899300.00 192266.55 846841.71 94.5

CountyERATH
Highway FM2156
From VARIOUS ROADWAYS IN ERATH, HOOD, WISE,
To SOMERVELL, PARKER, & PALO PINTO CONTIES
CSJ 6288-80-001
Proj ID RMC - 628880001
Work Type SEAL COAT
 
0.010 1589066.92 0.00 1430729.42 90.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-15-16
Work Began 06-15-16
Work Completed  
Time Computed 06-22-16
Contract Working Days 30
Addl Days Granted 0
Working Days Charged 22
Percent Time Used 73
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-80-001
BARRICADES PLUS, LLC (1.88%)
FLAT LINE, INC.( 15.08%)
BRYDL CONTRACTING, INC.(0.83%)
Contract # 10154216
Totals 1589066.92 0.00 1430729.42 90.0

CountyTARRANT
Highway IH0035W
From VARIOUS ROADWAYS IN
To SOUTH TARRANT COUNTY
CSJ 6289-08-001
Proj ID RMC - 628908001
Work Type GUARDRAIL INSTALLATION / REPAIR
 
0.010 4024750.00 273860.00 2602474.50 64.6
Work Order 02-01-16
Work Began 01-07-16
Work Completed  
Time Computed 01-14-16
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 293
Percent Time Used 80
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11154210
Totals 4024750.00 273860.00 2602474.50 64.6

CountyTARRANT
Highway IH0030
From VARIOUS ROADWAYS IN
To SOUTH TARRANT COUNTY
CSJ 6291-02-001
Proj ID RMC - 629102001
Work Type FLEXIBLE PAVEMENT REPAIR
 
0.010 1301700.00 429249.92 429249.92 32.9
Work Order 10-01-16
Work Began 10-03-16
Work Completed  
Time Computed 10-07-16
Contract Working Days 75
Addl Days Granted 0
Working Days Charged 16
Percent Time Used 21
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6291-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10154016
Totals 1301700.00 429249.92 429249.92 32.9

CountyTARRANT
Highway IH0820
From VARIOUS ROADWAYS IN
To NORTH TARRANT COUNTY
CSJ 6291-15-001
Proj ID RMC - 629115001
Work Type FULL - DEPTH CONCRETE PAEVMENT REPAIR
 
0.010 385403.19 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 52
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6291-15-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08164202
Totals 385403.19 0.00 0.00 0.0

CountyJOHNSON
Highway US0067
From VARIOUS ROADWAYS WITHIN
To JOHNSON COUNTY
CSJ 6293-58-001
Proj ID RMC - 629358001
Work Type VEGETATION MGMT RURAL
 
0.010 1029409.00 69681.00 211592.00 20.5
Work Order 04-07-16
Work Began 05-04-16
Work Completed  
Time Computed 04-14-16
Contract Working Days 214
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 26
Contractor(s)
CEN-TEX IRRIGATION SYSTEMS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6293-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12154213
Totals 1029409.00 69681.00 211592.00 20.5

CountyTARRANT
Highway IH0020
From VARIOUS ROADWAYS IN
To SOUTH TARRANT COUNTY
CSJ 6296-04-001
Proj ID RMC - 629604001
Work Type FULL - WIDTH MOWING
 
0.010 690320.00 0.00 223596.00 33.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-19-16
Work Began 05-23-16
Work Completed  
Time Computed 05-26-16
Contract Working Days 120
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 43
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12154014
Totals 690320.00 0.00 223596.00 33.4

CountyTARRANT
Highway SH0114
From VARIOUS ROADWAYS IN
To NORTH TARRANT COUNTY
CSJ 6296-23-001
Proj ID RMC - 629623001
Work Type ROADSIDE MOWING
 
0.010 857304.00 0.00 185667.00 21.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 07-27-16
Work Began 05-17-16
Work Completed  
Time Computed 07-27-16
Contract Working Days 184
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 17
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12154015
Totals 857304.00 0.00 185667.00 21.6

CountyPALO PINTO
Highway US0281
From VARIOUS ROADWAYS IN PALO PINTO
To AND ERATH COUNTIES
CSJ 6296-64-001
Proj ID RMC - 629664001
Work Type MOWING AND HERBICIDE
 
0.010 604371.40 48956.20 183226.50 30.3
Work Order 06-16-16
Work Began 05-10-16
Work Completed  
Time Computed 06-20-16
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 22
Contractor(s)
LONESTAR HAWK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12154201
Totals 604371.40 48956.20 183226.50 30.3

CountyPARKER
Highway IH0020
From VARIOUS ROADWAYS IN
To PARKER COUNTY
CSJ 6296-65-001
Proj ID RMC - 629665001
Work Type MOWING AND HERBICIDE
 
0.010 663779.48 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-05-16
Work Began 00-00-00
Work Completed  
Time Computed 05-13-16
Contract Working Days 144
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
FMWB, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6296-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12154202
Totals 663779.48 0.00 0.00 0.0