Monthly State Let Maintenance Report For Fort Worth District As Of Jun 10, 2015 Page 2 Of 2

Last Update: Wednesday, June 10, 2015
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyPARKER
Highway US0180
From VARIOUS ROADWAYS WITHIN
To PARKER & PALO PINTO COUNTY
CSJ 6265-50-001
Proj ID RMC - 626550001
Work Type CALL - OUT REFLEC PAV MRKINGS & MRKRS
 
0.010 333625.00 1962.00 85036.19 25.4
Work Order 11-10-14
Work Began 00-00-00
Work Completed  
Time Computed 11-17-14
Contract Working Days 189
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 10
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6265-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01144003
Totals 333625.00 1962.00 85036.19 25.4

CountyJOHNSON
Highway IH0035W
From VARIOUS INTERSECTION IN
To JOHNSON COUNTY
CSJ 6266-26-001
Proj ID RMC - 626626001
Work Type INSTALLING INTERSECTIONS
 
0.935 1188600.62 83129.80 962135.37 85.9
Work Order 04-07-14
Work Began 04-07-14
Work Completed  
Time Computed 04-14-14
Contract Working Days 80
Addl Days Granted 0
Working Days Charged 155
Percent Time Used 193
Contractor(s)
JAY MILLS CONTRACTING, INCORPORATED
SUBCONTRACTOR(S) FOR CCSJ: 6266-26-001
MARCOM"S MOWING SERVICE, LLC (1.71%)
BICK"S CONSTRUCTION, INC.( 27.77%)
STRIPING TECHNOLOGY, L.P.(2.61%)
Contract # 01144021
Totals 1188600.62 83129.80 962135.37 85.9

CountyTARRANT
Highway IH0035W
From VARIOUS ROADWAYS WITHIN
To SOUTH TARRANT AND JOHNSON COUNTY
CSJ 6267-35-001
Proj ID RMC - 626735001
Work Type GUARDRAIL INSTALLATION AND REPAIR
 
0.010 523090.00 120759.80 755398.10 99.9
Work Order 07-01-14
Work Began 07-01-14
Work Completed  
Time Computed 07-08-14
Contract Working Days 365
Addl Days Granted 62
Working Days Charged 319
Percent Time Used 74
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-35-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05144002
Totals 523090.00 120759.80 755398.10 99.9

CountyTARRANT
Highway US0287
From VARIOUS ROADWAYS WITHIN
To SOUTH TARRANT AND JOHNSON COUNTY
CSJ 6267-39-001
Proj ID RMC - 626739001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 1223500.00 0.00 1800602.24 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-01-14
Work Began 06-01-14
Work Completed  
Time Computed 06-08-14
Contract Working Days 50
Addl Days Granted 25
Working Days Charged 27
Percent Time Used 36
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6267-39-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144001
Totals 1223500.00 0.00 1800602.24 99.9

CountyTARRANT
Highway SH0199
From VARIOUS ROADWAYS WITHIN
To NORTH TARRANT COUNTY
CSJ 6267-46-001
Proj ID RMC - 626746001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 735500.00 0.00 788117.00 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-28-14
Work Began 05-22-14
Work Completed  
Time Computed 06-04-14
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 15
Percent Time Used 30
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6267-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03144019
Totals 735500.00 0.00 788117.00 99.9

CountyTARRANT
Highway IH0020
From VARIOUS ROADWAYS IN THE
To FORT WORTH DISTRICT
CSJ 6269-74-001
Proj ID BPM - 626974001
Work Type STRUCTURAL BRIDGE REPAIR
 
0.010 987908.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 216
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6269-74-001
S & S BRIDGE PAINTING, INC.(5.87%)
CROSSROADS, L.P. (5.17%)
Contract # 02154010
Totals 987908.00 0.00 0.00 0.0

CountyTARRANT
Highway FM0157
From VARIOUS ROADWAYS WITHIN
To SOUTH TARRANT & JOHNSON COUNTY
CSJ 6270-73-001
Proj ID RMC - 627073001
Work Type CALL - OUT REFLEC. PAV MRKINGS & MRKS
 
0.010 371875.00 24377.95 346981.21 93.3
Work Order 10-10-14
Work Began 00-00-00
Work Completed  
Time Computed 10-13-14
Contract Working Days 140
Addl Days Granted 0
Working Days Charged 40
Percent Time Used 28
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6270-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05144023
Totals 371875.00 24377.95 346981.21 93.3

CountyJOHNSON
Highway FM1807
From IH 35W
To ELLIS CL
CSJ 6270-95-001
Proj ID RMC - 627095001
Work Type SEAL COAT OF FC 6 ROADWAYS
 
53.071 1531361.47 0.00 165918.50 10.8
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 31
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6270-95-001
TRP CONSTRUCTION GROUP, LLC( 14.10%)
FLASHER EQUIPMENT COMPANY(2.15%)
Contract # 10144002
Totals 1531361.47 0.00 165918.50 10.8

CountyTARRANT
Highway IH0820
From VARIOUS ROADWAYS WITHIN
To SOUTH TARRANT & JOHNSON COUNTY
CSJ 6272-53-001
Proj ID RMC - 627253001
Work Type REFLECTORIZED PAVEMENT MARKINGS
 
0.010 1427188.62 0.00 23265.55 1.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 98
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 3
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6272-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08144001
Totals 1427188.62 0.00 23265.55 1.6

CountyERATH
Highway US0281
From VARIOUS ROADWAYS WITHIN
To HOOD/SOMMERVELL ERATH COUNTIES
CSJ 6273-55-001
Proj ID RMC - 627355001
Work Type CLEANING & SEALING JOINTS & CRACKS
 
0.010 603719.00 42700.00 576359.68 95.4
Work Order 02-10-15
Work Began 00-00-00
Work Completed  
Time Computed 02-17-15
Contract Working Days 57
Addl Days Granted 0
Working Days Charged 25
Percent Time Used 43
Contractor(s)
BICK'S CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6273-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12144006
Totals 603719.00 42700.00 576359.68 95.4

CountyPARKER
Highway IH0020
From VARIOUS ROADWAYS IN PARKER
To AND PALO PINTO COUNTIES
CSJ 6279-92-001
Proj ID RMC - 627992001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 1510952.00 0.00 325248.26 21.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 8
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6279-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12144210
Totals 1510952.00 0.00 325248.26 21.5

CountyTARRANT
Highway US0287
From VARIOUS ROADWAYS IN
To SOUTH TARRANT COUNTY
CSJ 6281-07-001
Proj ID RMC - 628107001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 900684.00 100617.45 179240.49 19.9
Work Order 04-20-15
Work Began 00-00-00
Work Completed  
Time Computed 04-27-15
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 4
Contractor(s)
BICK'S CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-07-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12144010
Totals 900684.00 100617.45 179240.49 19.9

CountyJOHNSON
Highway SH0171
From VARIOUS ROADWAYS IN
To JOHNSON COUNTY
CSJ 6281-09-001
Proj ID RMC - 628109001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 639283.20 0.00 1403339.50 99.9
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-25-15
Work Began 00-00-00
Work Completed  
Time Computed 04-01-15
Contract Working Days 25
Addl Days Granted 25
Working Days Charged 35
Percent Time Used 70
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6281-09-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12144011
Totals 639283.20 0.00 1403339.50 99.9

CountyTARRANT
Highway IH0820
From VARIOUS ROADWAYS IN
To NORTH TARRANT COUNTY
CSJ 6281-24-001
Proj ID RMC - 628124001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 659900.00 0.00 168203.16 25.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 25
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 28
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6281-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12144211
Totals 659900.00 0.00 168203.16 25.4

CountyWISE
Highway FM2123
From FM 2123 IN WISE COUNTY
To SH 114 TO CR 3673
CSJ 6287-66-001
Proj ID RMC - 628766001
Work Type 2" HOTMIX ASPHALT OVERLAY
 
0.010 1486238.14 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
JAGOE-PUBLIC COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6287-66-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06154009
Totals 1486238.14 0.00 0.00 0.0

CountyTARRANT
Highway SH0360
From SH 360 FRONTAGE ROADS
To IN SOUTH TARRANT COUNTY
CSJ 6287-71-001
Proj ID RMC - 628771001
Work Type MILL & OVERLAY, MISC ROADWAY WORK
 
2.111 1855641.58 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
AUSTIN BRIDGE & ROAD SERVICES, LP
SUBCONTRACTOR(S) FOR CCSJ: 6287-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06154202
Totals 1855641.58 0.00 0.00 0.0

CountyTARRANT
Highway IH0030
From VARIOUS ROADWAYS IN
To SOUTH TARRANT COUNTY
CSJ 6288-08-001
Proj ID RMC - 628808001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 899300.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 60
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-08-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06154201
Totals 899300.00 0.00 0.00 0.0

page 1 | page 2