Monthly State Let Maintenance Report For Fort Worth District As Of May 15, 2013 Page 1 Of 2

Last Update: Wednesday, May 15, 2013
FTP Icon Text Version
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyTARRANT
Highway IH0820
From VARIOUS ROADWAYS WITHIN
To NORTH TARRANT COUNTY
CSJ 6221-51-001
Proj ID RMC - 622151001
Work Type GUARDRAIL INSTALLATION AND REPAIR
 
0.010 361644.75 22089.50 386074.60 99.9
Work Order 07-25-11
Work Began 08-01-11
Work Completed  
Time Computed 08-01-11
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 639
Percent Time Used 87
Contractor(s)
LONE STAR BARRIER SERVICES, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6221-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 05114002
Totals 361644.75 22089.50 386074.60 99.9

CountyTARRANT
Highway IH0035W
From VARIOUS ROADWAYS WITHIN
To SOUTH TARRANT & JOHNSON COUNTY
CSJ 6222-87-001
Proj ID RMC - 622287001
Work Type GUARDRAIL INSTALLATION & REPAIR
 
0.010 1301984.00 41101.37 641803.04 49.2
Work Order 01-03-12
Work Began 01-03-12
Work Completed  
Time Computed 01-10-12
Contract Working Days 730
Addl Days Granted 0
Working Days Charged 477
Percent Time Used 65
Contractor(s)
CKORP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6222-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09114003
Totals 1301984.00 41101.37 641803.04 49.2

CountyTARRANT
Highway IH0030
From VARIOUS BRIDGES IN THE
To FORT WORTH DISTRICT
CSJ 6223-65-001
Proj ID BPM - 622365001
Work Type STRUCTURAL BRIDGE REPAIR
 
0.010 820383.80 0.00 745909.37 99.6
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 01-30-12
Work Began 04-16-12
Work Completed  
Time Computed 02-06-12
Contract Working Days 213
Addl Days Granted 0
Working Days Charged 330
Percent Time Used 154
Contractor(s)
RESTEK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6223-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 12114021
Totals 820383.80 0.00 745909.37 99.6

CountyTARRANT
Highway IH0020
From VARIOUS ROADWAYS WITHIN
To SOUTH TARRANT COUNTY
CSJ 6228-92-001
Proj ID RMC - 622892001
Work Type ROADSIDE MOWING
 
0.010 537897.00 0.00 216018.50 40.1
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 05-15-12
Work Began 05-15-12
Work Completed  
Time Computed 05-22-21
Contract Working Days 144
Addl Days Granted 0
Working Days Charged 59
Percent Time Used 40
Contractor(s)
SIGNATURE CONTRACTING SERVICES, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6228-92-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11114014
Totals 537897.00 0.00 216018.50 40.1

CountyPARKER
Highway US0180
From VARIOUS ROADWAYS WITHIN
To PARKER & PALO PINTO COUNTY
CSJ 6230-18-001
Proj ID RMC - 623018001
Work Type CALL - OUT REFLECTORIZED PAV MRKING & MRKS
 
0.010 339707.50 0.00 209014.89 61.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-29-12
Work Began 02-29-12
Work Completed  
Time Computed 03-03-12
Contract Working Days 103
Addl Days Granted 0
Working Days Charged 11
Percent Time Used 10
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6230-18-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09114010
Totals 339707.50 0.00 209014.89 61.5

CountyTARRANT
Highway IH0020
From VARIOUS LOCATIONS
To FORT WORTH DISTRICT
CSJ 6230-50-001
Proj ID RMC - 623050001
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS - N
 
0.010 116502.50 0.00 21070.00 18.0
CountyTARRANT
Highway IH0020
From VARIOUS LOCATIONS
To WICHITA FALLS DISTRICT
CSJ 6230-50-002
Proj ID RMC - 623050002
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS - N
 
0.001 98976.50 0.00 36806.00 37.1
CountyTARRANT
Highway IH0020
From VARIOUS LOCATIONS
To PARIS DISTRICT
CSJ 6230-50-003
Proj ID RMC - 623050003
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS - N
 
0.001 185103.50 0.00 44644.00 24.1
CountyTARRANT
Highway IH0020
From VARIOUS LOCATIONS
To ATLANTA DISTRICT
CSJ 6230-50-004
Proj ID RMC - 623050004
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS - N
 
0.001 125618.50 0.00 64642.00 51.4
CountyTARRANT
Highway IH0020
From VARIOUS LOCATIONS
To BROWNWOOD DISTRICT
CSJ 6230-50-005
Proj ID RMC - 623050005
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS - N
 
0.001 157842.50 0.00 27146.00 17.1
CountyTARRANT
Highway IH0020
From VARIOUS LOCATIONS
To DALLAS DISTRICT
CSJ 6230-50-006
Proj ID RMC - 623050006
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS - N
 
0.001 20712.50 0.00 8274.00 39.9
CountyTARRANT
Highway IH0020
From VARIOUS LOCATIONS
To TYLER DISTRICT
CSJ 6230-50-007
Proj ID RMC - 623050007
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS - N
 
0.001 109001.00 0.00 53708.00 49.2
CountyTARRANT
Highway IH0020
From VARIOUS LOCATIONS
To WACO DISTRICT
CSJ 6230-50-008
Proj ID RMC - 623050008
Work Type REMOVE AND REPLACE SPEED LIMIT SIGNS - N
 
0.001 162689.00 0.00 6552.00 4.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 09-22-11
Work Began 09-27-11
Work Completed  
Time Computed 09-28-11
Contract Working Days 273
Addl Days Granted 0
Working Days Charged 118
Percent Time Used 43
Contractor(s)
MASSANA CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6230-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08114014
Totals 976446.00 0.00 262842.00 26.9

CountyTARRANT
Highway FM0157
From VARIOUS SECTION FROM GREEN OAKS TO
To DEBBIE LANE IN TARRANT COUNTY
CSJ 6230-93-001
Proj ID RMC - 623093001
Work Type PLANING & OVERLAY
 
0.010 2803024.88 0.00 2351963.82 84.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 06-04-12
Work Began 06-06-12
Work Completed  
Time Computed 06-06-12
Contract Working Days 40
Addl Days Granted 10
Working Days Charged 55
Percent Time Used 110
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6230-93-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03124003
Totals 2803024.88 0.00 2351963.82 84.0

CountyTARRANT
Highway FM0730
From VARIOUS ROADWAYS IN
To NORTH TARRANT COUNTY
CSJ 6231-79-001
Proj ID RMC - 623179001
Work Type MILL & OVERLAY
 
0.010 1984578.10 0.00 1839916.20 92.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 10-25-12
Work Began 10-25-12
Work Completed  
Time Computed 11-12-12
Contract Working Days 65
Addl Days Granted 0
Working Days Charged 57
Percent Time Used 87
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6231-79-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08124041
Totals 1984578.10 0.00 1839916.20 92.7

CountyWISE
Highway FM2264
From FM 2264, SH 59, FM 730 & FM 2210
To IN WISE AND JACK COUNTIES
CSJ 6240-76-001
Proj ID RMC - 624076001
Work Type PAVEMENT REHAB
 
0.010 1779913.56 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 64
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6240-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134001
Totals 1779913.56 0.00 0.00 0.0

CountyHOOD
Highway SL0567
From LP 567, FM 4, AND BU 377H IN
To HOOD COUNTY
CSJ 6241-13-001
Proj ID RMC - 624113001
Work Type OVERLAY AND SEAL COAT
 
0.010 1288270.75 185520.00 185520.00 14.4
Work Order 04-22-13
Work Began 04-22-13
Work Completed  
Time Computed 04-29-13
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 2
Percent Time Used 5
Contractor(s)
NORTHEASTERN PAVERS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6241-13-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134004
Totals 1288270.75 185520.00 185520.00 14.4

CountyPARKER
Highway US0180
From VARIOUS ROADWAYS WITHIN
To PARKER & PALO PINTO COUNTY
CSJ 6242-99-001
Proj ID RMC - 624299001
Work Type REFLECTORIZED PAVEMENT MARKINGS
 
0.010 678854.47 142103.05 668838.27 100.0
Work Order 11-13-12
Work Began 11-13-12
Work Completed 04-15-13
Time Computed 11-20-12
Contract Working Days 39
Addl Days Granted 0
Working Days Charged 31
Percent Time Used 79
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6242-99-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08124005
Totals 678854.47 142103.05 668838.27 100.0

CountyTARRANT
Highway FM0157
From VARIOUS ROADWAYS WITHIN
To SOUTH TARRANT AND JOHNSON COUNTIES
CSJ 6243-51-001
Proj ID RMC - 624351001
Work Type CALL - OUT REFLEC.PAVEMENT MRKINGS & MRKS
 
0.010 467150.00 3326.42 167441.68 35.8
Work Order 10-26-12
Work Began 10-26-12
Work Completed  
Time Computed 10-29-12
Contract Working Days 144
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 18
Contractor(s)
TRP CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6243-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 08124025
Totals 467150.00 3326.42 167441.68 35.8

CountyTARRANT
Highway IH0020
From VARIOUS ROADWAYS IN TARRANT
To AND PARKER COUNTIES
CSJ 6244-73-001
Proj ID BPM - 624473001
Work Type STRUCTURAL BRIDGE REPAIR
 
0.010 441825.08 0.00 112979.40 28.4
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-11-13
Work Began 02-25-13
Work Completed  
Time Computed 02-18-13
Contract Working Days 91
Addl Days Granted 0
Working Days Charged 50
Percent Time Used 54
Contractor(s)
TEXAS HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6244-73-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11124009
Totals 441825.08 0.00 112979.40 28.4

CountyPARKER
Highway FM2257
From JENNINGS LANE
To FM 730
CSJ 6247-64-001
Proj ID RMC - 624764001
Work Type FULL - DPETH HMAC REPAIR
 
2.216 1482289.56 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 70
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6247-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03134002
Totals 1482289.56 0.00 0.00 0.0

CountyTARRANT
Highway IH0030
From VARIOUS ROADS WITHIN S. TARRANT, JOHNSON
To PARKER, PALO PINTO & ERATH COUNTIES
CSJ 6247-70-001
Proj ID RMC - 624770001
Work Type ROUTINE SWEEPING & DEBRIS REMOVAL
 
0.010 679802.45 64822.38 159730.64 23.4
Work Order 02-01-13
Work Began 02-04-13
Work Completed  
Time Computed 02-08-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 22
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6247-70-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11124010
Totals 679802.45 64822.38 159730.64 23.4

CountyTARRANT
Highway IH0820
From VARIOUS ROADWAYS WITHIN
To NORTH TARRANT COUNTY
CSJ 6247-71-001
Proj ID RMC - 624771001
Work Type ROUTINE SWEEPING AND DEBRIS REMOVAL
 
0.010 383656.81 32037.32 97774.92 25.4
Work Order 02-01-13
Work Began 02-04-13
Work Completed  
Time Computed 02-08-13
Contract Working Days 365
Addl Days Granted 0
Working Days Charged 82
Percent Time Used 22
Contractor(s)
SWEEPING SERVICES OF TEXAS - OPERATING, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 6247-71-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11124001
Totals 383656.81 32037.32 97774.92 25.4

CountyTARRANT
Highway US0287
From VARIOUS ROADWAYS WITHIN
To SOUTH TARRANT AND JOHNSON COUNTY
CSJ 6250-37-001
Proj ID RMC - 625037001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 646152.50 364242.60 364242.60 56.3
Work Order 04-15-13
Work Began 04-19-13
Work Completed  
Time Computed 04-22-13
Contract Working Days 44
Addl Days Granted 0
Working Days Charged 3
Percent Time Used 6
Contractor(s)
PEACHTREE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6250-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134022
Totals 646152.50 364242.60 364242.60 56.3

CountyTARRANT
Highway SH0360
From VARIOUS ROADWAYS WITHIN
To SOUTH TARRANT AND JOHNSON COUNTY
CSJ 6250-38-001
Proj ID RMC - 625038001
Work Type FULL - DEPTH REPAIR OF EXIST. CONCRETE PAV
 
0.010 285496.19 158906.63 278692.82 97.6
Work Order 03-11-13
Work Began 03-11-13
Work Completed  
Time Computed 03-18-13
Contract Working Days 37
Addl Days Granted 0
Working Days Charged 28
Percent Time Used 75
Contractor(s)
O. TREVINO CONSTRUCTION, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6250-38-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 01134003
Totals 285496.19 158906.63 278692.82 97.6

CountyTARRANT
Highway SH0199
From VARIOUS ROADWAYS WITHIN
To NORTH TARRANT COUNTY
CSJ 6251-53-001
Proj ID RMC - 625153001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 565400.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 167
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
VANN/ELLI, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6251-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02134034
Totals 565400.00 0.00 0.00 0.0

CountyPARKER
Highway FM0051
From WITHIN PARKER COUNTY
To ON ROADWAYS FM 51 & FM 730
CSJ 6253-16-001
Proj ID RMC - 625316001
Work Type FLEXIBLE PAVEMENT STRUCTURE REPAIR
 
0.010 369281.25 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 9
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
THE LANE CONSTRUCTION CORPORATION
SUBCONTRACTOR(S) FOR CCSJ: 6253-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02134018
Totals 369281.25 0.00 0.00 0.0