| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | TARRANT |
| Highway |
IH0820 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
NORTH TARRANT COUNTY |
| CSJ |
6221-51-001 |
| Proj ID |
RMC - 622151001 |
| Work Type |
GUARDRAIL INSTALLATION AND REPAIR |
| |
|
0.010 |
361644.75 |
22089.50 |
386074.60 |
99.9 |
| Work Order |
07-25-11 |
| Work Began |
08-01-11 |
| Work Completed |
|
| Time Computed |
08-01-11 |
| Contract Working Days |
730 |
| Addl Days Granted |
0 |
| Working Days Charged |
639 |
| Percent Time Used |
87 |
| Contractor(s) |
| LONE STAR BARRIER SERVICES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6221-51-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05114002 |
|
Totals |
361644.75 |
22089.50 |
386074.60 |
99.9 |
|
| County | TARRANT |
| Highway |
IH0035W |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
SOUTH TARRANT & JOHNSON COUNTY |
| CSJ |
6222-87-001 |
| Proj ID |
RMC - 622287001 |
| Work Type |
GUARDRAIL INSTALLATION & REPAIR |
| |
|
0.010 |
1301984.00 |
41101.37 |
641803.04 |
49.2 |
| Work Order |
01-03-12 |
| Work Began |
01-03-12 |
| Work Completed |
|
| Time Computed |
01-10-12 |
| Contract Working Days |
730 |
| Addl Days Granted |
0 |
| Working Days Charged |
477 |
| Percent Time Used |
65 |
| Contractor(s) |
| CKORP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6222-87-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09114003 |
|
Totals |
1301984.00 |
41101.37 |
641803.04 |
49.2 |
|
| County | TARRANT |
| Highway |
IH0030 |
| From |
VARIOUS BRIDGES IN THE |
| To |
FORT WORTH DISTRICT |
| CSJ |
6223-65-001 |
| Proj ID |
BPM - 622365001 |
| Work Type |
STRUCTURAL BRIDGE REPAIR |
| |
|
0.010 |
820383.80 |
0.00 |
745909.37 |
99.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
01-30-12 |
| Work Began |
04-16-12 |
| Work Completed |
|
| Time Computed |
02-06-12 |
| Contract Working Days |
213 |
| Addl Days Granted |
0 |
| Working Days Charged |
330 |
| Percent Time Used |
154 |
| Contractor(s) |
| RESTEK, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6223-65-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12114021 |
|
Totals |
820383.80 |
0.00 |
745909.37 |
99.6 |
|
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
SOUTH TARRANT COUNTY |
| CSJ |
6228-92-001 |
| Proj ID |
RMC - 622892001 |
| Work Type |
ROADSIDE MOWING |
| |
|
0.010 |
537897.00 |
0.00 |
216018.50 |
40.1 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
05-15-12 |
| Work Began |
05-15-12 |
| Work Completed |
|
| Time Computed |
05-22-21 |
| Contract Working Days |
144 |
| Addl Days Granted |
0 |
| Working Days Charged |
59 |
| Percent Time Used |
40 |
| Contractor(s) |
| SIGNATURE CONTRACTING SERVICES, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 6228-92-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11114014 |
|
Totals |
537897.00 |
0.00 |
216018.50 |
40.1 |
|
| County | PARKER |
| Highway |
US0180 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
PARKER & PALO PINTO COUNTY |
| CSJ |
6230-18-001 |
| Proj ID |
RMC - 623018001 |
| Work Type |
CALL - OUT REFLECTORIZED PAV MRKING & MRKS |
| |
|
0.010 |
339707.50 |
0.00 |
209014.89 |
61.5 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-29-12 |
| Work Began |
02-29-12 |
| Work Completed |
|
| Time Computed |
03-03-12 |
| Contract Working Days |
103 |
| Addl Days Granted |
0 |
| Working Days Charged |
11 |
| Percent Time Used |
10 |
| Contractor(s) |
| TRP CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6230-18-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09114010 |
|
Totals |
339707.50 |
0.00 |
209014.89 |
61.5 |
|
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
FORT WORTH DISTRICT |
| CSJ |
6230-50-001 |
| Proj ID |
RMC - 623050001 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.010 |
116502.50 |
0.00 |
21070.00 |
18.0 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
WICHITA FALLS DISTRICT |
| CSJ |
6230-50-002 |
| Proj ID |
RMC - 623050002 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
98976.50 |
0.00 |
36806.00 |
37.1 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
PARIS DISTRICT |
| CSJ |
6230-50-003 |
| Proj ID |
RMC - 623050003 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
185103.50 |
0.00 |
44644.00 |
24.1 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
ATLANTA DISTRICT |
| CSJ |
6230-50-004 |
| Proj ID |
RMC - 623050004 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
125618.50 |
0.00 |
64642.00 |
51.4 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
BROWNWOOD DISTRICT |
| CSJ |
6230-50-005 |
| Proj ID |
RMC - 623050005 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
157842.50 |
0.00 |
27146.00 |
17.1 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
DALLAS DISTRICT |
| CSJ |
6230-50-006 |
| Proj ID |
RMC - 623050006 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
20712.50 |
0.00 |
8274.00 |
39.9 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
TYLER DISTRICT |
| CSJ |
6230-50-007 |
| Proj ID |
RMC - 623050007 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
109001.00 |
0.00 |
53708.00 |
49.2 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
WACO DISTRICT |
| CSJ |
6230-50-008 |
| Proj ID |
RMC - 623050008 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
162689.00 |
0.00 |
6552.00 |
4.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
09-22-11 |
| Work Began |
09-27-11 |
| Work Completed |
|
| Time Computed |
09-28-11 |
| Contract Working Days |
273 |
| Addl Days Granted |
0 |
| Working Days Charged |
118 |
| Percent Time Used |
43 |
| Contractor(s) |
| MASSANA CONSTRUCTION INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6230-50-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08114014 |
|
Totals |
976446.00 |
0.00 |
262842.00 |
26.9 |
|
| County | TARRANT |
| Highway |
FM0157 |
| From |
VARIOUS SECTION FROM GREEN OAKS TO |
| To |
DEBBIE LANE IN TARRANT COUNTY |
| CSJ |
6230-93-001 |
| Proj ID |
RMC - 623093001 |
| Work Type |
PLANING & OVERLAY |
| |
|
0.010 |
2803024.88 |
0.00 |
2351963.82 |
84.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
06-04-12 |
| Work Began |
06-06-12 |
| Work Completed |
|
| Time Computed |
06-06-12 |
| Contract Working Days |
40 |
| Addl Days Granted |
10 |
| Working Days Charged |
55 |
| Percent Time Used |
110 |
| Contractor(s) |
| PEACHTREE CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6230-93-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03124003 |
|
Totals |
2803024.88 |
0.00 |
2351963.82 |
84.0 |
|
| County | TARRANT |
| Highway |
FM0730 |
| From |
VARIOUS ROADWAYS IN |
| To |
NORTH TARRANT COUNTY |
| CSJ |
6231-79-001 |
| Proj ID |
RMC - 623179001 |
| Work Type |
MILL & OVERLAY |
| |
|
0.010 |
1984578.10 |
0.00 |
1839916.20 |
92.7 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-25-12 |
| Work Began |
10-25-12 |
| Work Completed |
|
| Time Computed |
11-12-12 |
| Contract Working Days |
65 |
| Addl Days Granted |
0 |
| Working Days Charged |
57 |
| Percent Time Used |
87 |
| Contractor(s) |
| NORTHEASTERN PAVERS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6231-79-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08124041 |
|
Totals |
1984578.10 |
0.00 |
1839916.20 |
92.7 |
|
| County | WISE |
| Highway |
FM2264 |
| From |
FM 2264, SH 59, FM 730 & FM 2210 |
| To |
IN WISE AND JACK COUNTIES |
| CSJ |
6240-76-001 |
| Proj ID |
RMC - 624076001 |
| Work Type |
PAVEMENT REHAB |
| |
|
0.010 |
1779913.56 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
64 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| PEACHTREE CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6240-76-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03134001 |
|
Totals |
1779913.56 |
0.00 |
0.00 |
0.0 |
|
| County | HOOD |
| Highway |
SL0567 |
| From |
LP 567, FM 4, AND BU 377H IN |
| To |
HOOD COUNTY |
| CSJ |
6241-13-001 |
| Proj ID |
RMC - 624113001 |
| Work Type |
OVERLAY AND SEAL COAT |
| |
|
0.010 |
1288270.75 |
185520.00 |
185520.00 |
14.4 |
| Work Order |
04-22-13 |
| Work Began |
04-22-13 |
| Work Completed |
|
| Time Computed |
04-29-13 |
| Contract Working Days |
35 |
| Addl Days Granted |
0 |
| Working Days Charged |
2 |
| Percent Time Used |
5 |
| Contractor(s) |
| NORTHEASTERN PAVERS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6241-13-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01134004 |
|
Totals |
1288270.75 |
185520.00 |
185520.00 |
14.4 |
|
| County | PARKER |
| Highway |
US0180 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
PARKER & PALO PINTO COUNTY |
| CSJ |
6242-99-001 |
| Proj ID |
RMC - 624299001 |
| Work Type |
REFLECTORIZED PAVEMENT MARKINGS |
| |
|
0.010 |
678854.47 |
142103.05 |
668838.27 |
100.0 |
| Work Order |
11-13-12 |
| Work Began |
11-13-12 |
| Work Completed |
04-15-13 |
| Time Computed |
11-20-12 |
| Contract Working Days |
39 |
| Addl Days Granted |
0 |
| Working Days Charged |
31 |
| Percent Time Used |
79 |
| Contractor(s) |
| TOTAL HIGHWAY MAINTENANCE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6242-99-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08124005 |
|
Totals |
678854.47 |
142103.05 |
668838.27 |
100.0 |
|
| County | TARRANT |
| Highway |
FM0157 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
SOUTH TARRANT AND JOHNSON COUNTIES |
| CSJ |
6243-51-001 |
| Proj ID |
RMC - 624351001 |
| Work Type |
CALL - OUT REFLEC.PAVEMENT MRKINGS & MRKS |
| |
|
0.010 |
467150.00 |
3326.42 |
167441.68 |
35.8 |
| Work Order |
10-26-12 |
| Work Began |
10-26-12 |
| Work Completed |
|
| Time Computed |
10-29-12 |
| Contract Working Days |
144 |
| Addl Days Granted |
0 |
| Working Days Charged |
27 |
| Percent Time Used |
18 |
| Contractor(s) |
| TRP CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6243-51-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08124025 |
|
Totals |
467150.00 |
3326.42 |
167441.68 |
35.8 |
|
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS ROADWAYS IN TARRANT |
| To |
AND PARKER COUNTIES |
| CSJ |
6244-73-001 |
| Proj ID |
BPM - 624473001 |
| Work Type |
STRUCTURAL BRIDGE REPAIR |
| |
|
0.010 |
441825.08 |
0.00 |
112979.40 |
28.4 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-11-13 |
| Work Began |
02-25-13 |
| Work Completed |
|
| Time Computed |
02-18-13 |
| Contract Working Days |
91 |
| Addl Days Granted |
0 |
| Working Days Charged |
50 |
| Percent Time Used |
54 |
| Contractor(s) |
| TEXAS HIGHWAY MAINTENANCE, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6244-73-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11124009 |
|
Totals |
441825.08 |
0.00 |
112979.40 |
28.4 |
|
| County | PARKER |
| Highway |
FM2257 |
| From |
JENNINGS LANE |
| To |
FM 730 |
| CSJ |
6247-64-001 |
| Proj ID |
RMC - 624764001 |
| Work Type |
FULL - DPETH HMAC REPAIR |
| |
|
2.216 |
1482289.56 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
70 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| THE LANE CONSTRUCTION CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 6247-64-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03134002 |
|
Totals |
1482289.56 |
0.00 |
0.00 |
0.0 |
|
| County | TARRANT |
| Highway |
IH0030 |
| From |
VARIOUS ROADS WITHIN S. TARRANT, JOHNSON |
| To |
PARKER, PALO PINTO & ERATH COUNTIES |
| CSJ |
6247-70-001 |
| Proj ID |
RMC - 624770001 |
| Work Type |
ROUTINE SWEEPING & DEBRIS REMOVAL |
| |
|
0.010 |
679802.45 |
64822.38 |
159730.64 |
23.4 |
| Work Order |
02-01-13 |
| Work Began |
02-04-13 |
| Work Completed |
|
| Time Computed |
02-08-13 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
82 |
| Percent Time Used |
22 |
| Contractor(s) |
| SWEEPING SERVICES OF TEXAS - OPERATING, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6247-70-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11124010 |
|
Totals |
679802.45 |
64822.38 |
159730.64 |
23.4 |
|
| County | TARRANT |
| Highway |
IH0820 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
NORTH TARRANT COUNTY |
| CSJ |
6247-71-001 |
| Proj ID |
RMC - 624771001 |
| Work Type |
ROUTINE SWEEPING AND DEBRIS REMOVAL |
| |
|
0.010 |
383656.81 |
32037.32 |
97774.92 |
25.4 |
| Work Order |
02-01-13 |
| Work Began |
02-04-13 |
| Work Completed |
|
| Time Computed |
02-08-13 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
82 |
| Percent Time Used |
22 |
| Contractor(s) |
| SWEEPING SERVICES OF TEXAS - OPERATING, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6247-71-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11124001 |
|
Totals |
383656.81 |
32037.32 |
97774.92 |
25.4 |
|
| County | TARRANT |
| Highway |
US0287 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
SOUTH TARRANT AND JOHNSON COUNTY |
| CSJ |
6250-37-001 |
| Proj ID |
RMC - 625037001 |
| Work Type |
FLEXIBLE PAVEMENT STRUCTURE REPAIR |
| |
|
0.010 |
646152.50 |
364242.60 |
364242.60 |
56.3 |
| Work Order |
04-15-13 |
| Work Began |
04-19-13 |
| Work Completed |
|
| Time Computed |
04-22-13 |
| Contract Working Days |
44 |
| Addl Days Granted |
0 |
| Working Days Charged |
3 |
| Percent Time Used |
6 |
| Contractor(s) |
| PEACHTREE CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6250-37-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01134022 |
|
Totals |
646152.50 |
364242.60 |
364242.60 |
56.3 |
|
| County | TARRANT |
| Highway |
SH0360 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
SOUTH TARRANT AND JOHNSON COUNTY |
| CSJ |
6250-38-001 |
| Proj ID |
RMC - 625038001 |
| Work Type |
FULL - DEPTH REPAIR OF EXIST. CONCRETE PAV |
| |
|
0.010 |
285496.19 |
158906.63 |
278692.82 |
97.6 |
| Work Order |
03-11-13 |
| Work Began |
03-11-13 |
| Work Completed |
|
| Time Computed |
03-18-13 |
| Contract Working Days |
37 |
| Addl Days Granted |
0 |
| Working Days Charged |
28 |
| Percent Time Used |
75 |
| Contractor(s) |
| O. TREVINO CONSTRUCTION, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6250-38-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
01134003 |
|
Totals |
285496.19 |
158906.63 |
278692.82 |
97.6 |
|
| County | TARRANT |
| Highway |
SH0199 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
NORTH TARRANT COUNTY |
| CSJ |
6251-53-001 |
| Proj ID |
RMC - 625153001 |
| Work Type |
FLEXIBLE PAVEMENT STRUCTURE REPAIR |
| |
|
0.010 |
565400.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
167 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| VANN/ELLI, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6251-53-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02134034 |
|
Totals |
565400.00 |
0.00 |
0.00 |
0.0 |
|
| County | PARKER |
| Highway |
FM0051 |
| From |
WITHIN PARKER COUNTY |
| To |
ON ROADWAYS FM 51 & FM 730 |
| CSJ |
6253-16-001 |
| Proj ID |
RMC - 625316001 |
| Work Type |
FLEXIBLE PAVEMENT STRUCTURE REPAIR |
| |
|
0.010 |
369281.25 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
9 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| THE LANE CONSTRUCTION CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 6253-16-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02134018 |
|
Totals |
369281.25 |
0.00 |
0.00 |
0.0 |
|