| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | TARRANT |
| Highway |
IH0820 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
NORTH TARRANT COUNTY |
| CSJ |
6221-51-001 |
| Proj ID |
RMC - 622151001 |
| Work Type |
GUARDRAIL INSTALLATION AND REPAIR |
| |
|
0.010 |
361644.75 |
19890.50 |
167461.72 |
46.3 |
| Work Order |
07-25-11 |
| Work Began |
08-01-11 |
| Work Completed |
|
| Time Computed |
08-01-11 |
| Contract Working Days |
730 |
| Addl Days Granted |
0 |
| Working Days Charged |
274 |
| Percent Time Used |
37 |
| Contractor(s) |
| LONE STAR BARRIER SERVICES, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6221-51-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05114002 |
|
Totals |
361644.75 |
19890.50 |
167461.72 |
46.3 |
|
| County | TARRANT |
| Highway |
IH0035W |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
SOUTH TARRANT & JOHNSON COUNTY |
| CSJ |
6222-87-001 |
| Proj ID |
RMC - 622287001 |
| Work Type |
GUARDRAIL INSTALLATION & REPAIR |
| |
|
0.010 |
1301984.00 |
46658.30 |
136996.58 |
10.5 |
| Work Order |
01-03-12 |
| Work Began |
01-03-12 |
| Work Completed |
|
| Time Computed |
01-10-12 |
| Contract Working Days |
730 |
| Addl Days Granted |
0 |
| Working Days Charged |
112 |
| Percent Time Used |
15 |
| Contractor(s) |
| CKORP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6222-87-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09114003 |
|
Totals |
1301984.00 |
46658.30 |
136996.58 |
10.5 |
|
| County | TARRANT |
| Highway |
IH0030 |
| From |
VARIOUS BRIDGES IN THE |
| To |
FORT WORTH DISTRICT |
| CSJ |
6223-65-001 |
| Proj ID |
BPM - 622365001 |
| Work Type |
STRUCTURAL BRIDGE REPAIR |
| |
|
0.010 |
820383.80 |
0.00 |
0.00 |
0.0 |
| Work Order |
01-30-12 |
| Work Began |
04-16-12 |
| Work Completed |
|
| Time Computed |
02-06-12 |
| Contract Working Days |
213 |
| Addl Days Granted |
0 |
| Working Days Charged |
55 |
| Percent Time Used |
25 |
| Contractor(s) |
| RESTEK, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6223-65-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12114021 |
|
Totals |
820383.80 |
0.00 |
0.00 |
0.0 |
|
| County | TARRANT |
| Highway |
FM0157 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
SOUTH TARRANT & JOHNSON COUNTY |
| CSJ |
6225-35-001 |
| Proj ID |
RMC - 622535001 |
| Work Type |
CALL - OUT REFLEC PAV MRKINGS & MRKS |
| |
|
0.010 |
504479.10 |
14282.58 |
212020.52 |
42.0 |
| Work Order |
10-13-11 |
| Work Began |
09-06-11 |
| Work Completed |
|
| Time Computed |
10-19-11 |
| Contract Working Days |
149 |
| Addl Days Granted |
0 |
| Working Days Charged |
24 |
| Percent Time Used |
16 |
| Contractor(s) |
| HIGHWAY TECHNOLOGIES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6225-35-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
07114018 |
|
Totals |
504479.10 |
14282.58 |
212020.52 |
42.0 |
|
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
SOUTH TARRANT COUNTY |
| CSJ |
6228-92-001 |
| Proj ID |
RMC - 622892001 |
| Work Type |
ROADSIDE MOWING |
| |
|
0.010 |
537897.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
144 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| SIGNATURE CONTRACTING SERVICES, L.L.C. |
SUBCONTRACTOR(S) FOR CCSJ: 6228-92-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11114014 |
|
Totals |
537897.00 |
0.00 |
0.00 |
0.0 |
|
| County | PARKER |
| Highway |
US0180 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
PARKER & PALO PINTO COUNTY |
| CSJ |
6230-18-001 |
| Proj ID |
RMC - 623018001 |
| Work Type |
CALL - OUT REFLECTORIZED PAV MRKING & MRKS |
| |
|
0.010 |
339707.50 |
0.00 |
15879.64 |
4.6 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
02-29-12 |
| Work Began |
02-29-12 |
| Work Completed |
|
| Time Computed |
03-03-12 |
| Contract Working Days |
103 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| TRP CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6230-18-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09114010 |
|
Totals |
339707.50 |
0.00 |
15879.64 |
4.6 |
|
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
FORT WORTH DISTRICT |
| CSJ |
6230-50-001 |
| Proj ID |
RMC - 623050001 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.010 |
116502.50 |
0.00 |
14280.00 |
12.2 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
WICHITA FALLS DISTRICT |
| CSJ |
6230-50-002 |
| Proj ID |
RMC - 623050002 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
98976.50 |
3108.00 |
21780.00 |
22.0 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
PARIS DISTRICT |
| CSJ |
6230-50-003 |
| Proj ID |
RMC - 623050003 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
185103.50 |
0.00 |
13604.00 |
7.3 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
ATLANTA DISTRICT |
| CSJ |
6230-50-004 |
| Proj ID |
RMC - 623050004 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
125618.50 |
0.00 |
17500.00 |
13.9 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
BROWNWOOD DISTRICT |
| CSJ |
6230-50-005 |
| Proj ID |
RMC - 623050005 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
157842.50 |
0.00 |
20356.00 |
12.8 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
DALLAS DISTRICT |
| CSJ |
6230-50-006 |
| Proj ID |
RMC - 623050006 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
20712.50 |
0.00 |
1484.00 |
7.1 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
TYLER DISTRICT |
| CSJ |
6230-50-007 |
| Proj ID |
RMC - 623050007 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
109001.00 |
0.00 |
18788.00 |
17.2 |
| County | TARRANT |
| Highway |
IH0020 |
| From |
VARIOUS LOCATIONS |
| To |
WACO DISTRICT |
| CSJ |
6230-50-008 |
| Proj ID |
RMC - 623050008 |
| Work Type |
REMOVE AND REPLACE SPEED LIMIT SIGNS - N |
| |
|
0.001 |
162689.00 |
0.00 |
6552.00 |
4.0 |
| Work Order |
09-22-11 |
| Work Began |
09-27-11 |
| Work Completed |
|
| Time Computed |
09-28-11 |
| Contract Working Days |
273 |
| Addl Days Granted |
0 |
| Working Days Charged |
85 |
| Percent Time Used |
31 |
| Contractor(s) |
| MASSANA CONSTRUCTION, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6230-50-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
08114014 |
|
Totals |
976446.00 |
3108.00 |
114344.00 |
11.7 |
|
| County | TARRANT |
| Highway |
SH0183 |
| From |
SH 183 IN |
| To |
SOUTH TARRANT COUNTY |
| CSJ |
6230-91-001 |
| Proj ID |
RMC - 623091001 |
| Work Type |
PLANING & OVERLAY |
| |
|
0.010 |
3163524.28 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
38 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| APAC-TEXAS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6230-91-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03124002 |
|
Totals |
3163524.28 |
0.00 |
0.00 |
0.0 |
|
| County | TARRANT |
| Highway |
BF1187C |
| From |
BF 1187C FROM CONCRETE PAVEMENT TO |
| To |
FM 1187 BYPASS IN SOUTH TARRANT COUNTY |
| CSJ |
6230-92-001 |
| Proj ID |
RMC - 623092001 |
| Work Type |
HMAC OVERLAY |
| |
|
2.229 |
984699.20 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
34 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| PEACHTREE CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6230-92-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03124021 |
|
Totals |
984699.20 |
0.00 |
0.00 |
0.0 |
|
| County | TARRANT |
| Highway |
FM0157 |
| From |
VARIOUS SECTION FROM GREEN OAKS TO |
| To |
DEBBIE LANE IN TARRANT COUNTY |
| CSJ |
6230-93-001 |
| Proj ID |
RMC - 623093001 |
| Work Type |
PLANING & OVERLAY |
| |
|
0.010 |
2803024.88 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
40 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| PEACHTREE CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 6230-93-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03124003 |
|
Totals |
2803024.88 |
0.00 |
0.00 |
0.0 |
|
| County | TARRANT |
| Highway |
US0377 |
| From |
VARIOUS ROADWAYS IN THE |
| To |
FORT WORTH DISTRICT |
| CSJ |
6231-28-001 |
| Proj ID |
RMC - 623128001 |
| Work Type |
THERMOPLASTIC STRIPING |
| |
|
0.010 |
1238599.09 |
0.00 |
1538928.12 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
10-24-11 |
| Work Began |
10-26-11 |
| Work Completed |
|
| Time Computed |
10-24-11 |
| Contract Working Days |
36 |
| Addl Days Granted |
11 |
| Working Days Charged |
41 |
| Percent Time Used |
87 |
| Contractor(s) |
| TRP CONSTRUCTION GROUP, LLC |
SUBCONTRACTOR(S) FOR CCSJ: 6231-28-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
09114017 |
|
Totals |
1238599.09 |
0.00 |
1538928.12 |
99.9 |
|
| County | TARRANT |
| Highway |
SH0360 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
SOUTH TARRANT & JOHNSON COUNTY |
| CSJ |
6231-63-001 |
| Proj ID |
RMC - 623163001 |
| Work Type |
REFLECTORIZED PAVEMENT MARKINGS |
| |
|
0.010 |
298194.63 |
24166.45 |
24166.45 |
8.1 |
| Work Order |
04-18-12 |
| Work Began |
04-18-12 |
| Work Completed |
|
| Time Computed |
04-25-12 |
| Contract Working Days |
74 |
| Addl Days Granted |
0 |
| Working Days Charged |
4 |
| Percent Time Used |
5 |
| Contractor(s) |
| INTERSTATE ROAD MANAGEMENT CORP. |
SUBCONTRACTOR(S) FOR CCSJ: 6231-63-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
10114020 |
|
Totals |
298194.63 |
24166.45 |
24166.45 |
8.1 |
|
| County | TARRANT |
| Highway |
US0287 |
| From |
VARIOUS RAODWAYS WITHIN |
| To |
S. TARRANT AND JOHNSON COUNTY |
| CSJ |
6233-33-001 |
| Proj ID |
RMC - 623333001 |
| Work Type |
FLEXIBLE PAVEMENT STRUCTURE REPAIR |
| |
|
0.010 |
882339.50 |
80840.34 |
80840.34 |
9.1 |
| Work Order |
04-16-12 |
| Work Began |
04-16-12 |
| Work Completed |
|
| Time Computed |
04-23-12 |
| Contract Working Days |
177 |
| Addl Days Granted |
0 |
| Working Days Charged |
6 |
| Percent Time Used |
3 |
| Contractor(s) |
| VANN/ELLI, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6233-33-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12114001 |
|
Totals |
882339.50 |
80840.34 |
80840.34 |
9.1 |
|
| County | TARRANT |
| Highway |
IH0820 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
NORTH TARRANT COUNTY |
| CSJ |
6234-40-001 |
| Proj ID |
RMC - 623440001 |
| Work Type |
FULL - DEPTH REP. OF EXIST. CONC. PAV. |
| |
|
0.010 |
375654.30 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
46 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ROY JORGENSEN ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6234-40-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
05124001 |
|
Totals |
375654.30 |
0.00 |
0.00 |
0.0 |
|
| County | TARRANT |
| Highway |
IH0030 |
| From |
VARIOUS ROADWAYS WITHIN S. TARRANT, |
| To |
JOHNSON, PARKER, PALO PINTO & ERATH CO. |
| CSJ |
6234-95-001 |
| Proj ID |
RMC - 623495001 |
| Work Type |
ROUTINE SWEEPING & DEBRIS REMOVAL |
| |
|
0.010 |
679399.25 |
63721.88 |
169119.77 |
24.8 |
| Work Order |
02-28-12 |
| Work Began |
02-01-12 |
| Work Completed |
|
| Time Computed |
02-29-12 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
83 |
| Percent Time Used |
22 |
| Contractor(s) |
| SWEEPING SERVICES OF TEXAS - OPERATING, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6234-95-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12114002 |
|
Totals |
679399.25 |
63721.88 |
169119.77 |
24.8 |
|
| County | TARRANT |
| Highway |
IH0820 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
NORTH TARRANT COUNTY |
| CSJ |
6234-96-001 |
| Proj ID |
RMC - 623496001 |
| Work Type |
ROUTINE SWEEPING & DEBRIS REMOVAL |
| |
|
0.010 |
369383.94 |
31277.90 |
105317.09 |
28.5 |
| Work Order |
01-16-12 |
| Work Began |
01-16-12 |
| Work Completed |
|
| Time Computed |
01-23-12 |
| Contract Working Days |
365 |
| Addl Days Granted |
0 |
| Working Days Charged |
99 |
| Percent Time Used |
27 |
| Contractor(s) |
| SWEEPING SERVICES OF TEXAS - OPERATING, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 6234-96-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12114003 |
|
Totals |
369383.94 |
31277.90 |
105317.09 |
28.5 |
|
| County | TARRANT |
| Highway |
SH0199 |
| From |
VARIOUS ROADWAYS WITHIN |
| To |
NORTH TARRANT COUNTY |
| CSJ |
6236-54-001 |
| Proj ID |
RMC - 623654001 |
| Work Type |
FLEXIBLE PAVEMENT STRUCTURE REPAIR |
| |
|
0.010 |
579820.00 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
125 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| ROY JORGENSEN ASSOCIATES, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6236-54-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
03124020 |
|
Totals |
579820.00 |
0.00 |
0.00 |
0.0 |
|
| County | PALO PINTO |
| Highway |
FM0129 |
| From |
VARIOUS ROADWAYS IN PALO PINTO, PARKER, |
| To |
SOMERVELL & JOHNSON COUNTIES |
| CSJ |
6239-26-001 |
| Proj ID |
RMC - 623926001 |
| Work Type |
SEAL COAT |
| |
|
0.010 |
1101691.63 |
0.00 |
0.00 |
4.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
04-24-12 |
| Work Began |
04-24-12 |
| Work Completed |
|
| Time Computed |
04-24-12 |
| Contract Working Days |
15 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| NORTHEASTERN PAVERS, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 6239-26-001 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
02124036 |
|
Totals |
1101691.63 |
0.00 |
0.00 |
4.9 |
|