Monthly Local Let Maintenance Report For Dallas District As Of Feb 10, 2017 Page 3 Of 5

Last Update: Friday, February 10, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyDALLAS
HighwayIH0020
FromVARIOUS ROADWAYS IN THE NORTHWEST DALLAS
ToCOUNTY MAINTENANCE SECFTION
CSJ6302-48-001
Proj IDSUP - 630248001
Work TypeLITTER REMOVAL
 
0.00194310.4617970.1019.0
Work Order07-21-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged147
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-48-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161831
Totals94310.462199.0017970.1019.0

CountyDALLAS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE SOUTHEAST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-49-001
Proj IDSUP - 630249001
Work TypeLITTER REMOVAL
 
0.001212694.9443148.0620.2
Work Order07-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged152
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-49-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161832
Totals212694.947939.9343148.0620.2

CountyKAUFMAN
HighwayUS0080
FromVARIOUS ROADWAYS IN KAUFMAN
ToMAINTENANCE SECTION
CSJ6302-50-001
Proj IDSUP - 630250001
Work TypeLITTER REMOVAL
 
0.001222173.0230180.6813.5
Work Order08-02-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged147
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
P G SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6302-50-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161833
Totals222173.026597.6730180.6813.5

CountyCOLLIN
HighwayUS0380
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6302-51-001
Proj IDSUP - 630251001
Work TypeLITTER REMOVAL
 
0.001196309.7039962.5020.3
Work Order05-27-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged147
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6302-51-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161834
Totals196309.709661.5639962.5020.3

CountyDALLAS
HighwayIH0030
FromVARIOUS ROADWAYS IN THE NORTHEAST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-52-001
Proj IDSUP - 630252001
Work TypeLITTER REMOVAL
 
0.00195207.7114043.0114.7
Work Order07-25-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged147
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
P G SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6302-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161835
Totals95207.714401.3014043.0114.7

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-53-001
Proj IDSUP - 630253001
Work TypeLITTER REMOVAL
 
0.001120015.9519460.2516.2
Work Order07-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged147
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6302-53-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161836
Totals120015.952961.3219460.2516.2

CountyELLIS
HighwayIH0035E
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-54-001
Proj IDSUP - 630254001
Work TypeLITTER REMOVAL
 
0.001128893.4546021.9635.7
Work Order07-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged147
Percent Time Used40
Contractor(s)
TIBH INDUSTRIES, INC.
P G SERVICES
SUBCONTRACTOR(S) FOR CCSJ: 6302-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161837
Totals128893.4510906.8846021.9635.7

CountyDALLAS
HighwayIH0020
FromVARIOUS ROADWAYS IN THE SOUTHWEST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-55-001
Proj IDSUP - 630255001
Work TypeLITTER REMOVAL
 
0.001268527.7228791.0210.7
Work Order07-26-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged147
Percent Time Used20
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161838
Totals268527.725442.5828791.0210.7

CountyDALLAS
HighwayUS0080
FromDALLAS DISTRICT
ToCOMPLEX
CSJ6302-56-001
Proj IDSUP - 630256001
Work TypeGROUNDS MAINTENANCE
 
0.00183010.3052815.2864.1
Work Order04-28-16
Work Began05-01-16
Work Completed
Time Computed05-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged270
Percent Time Used73
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6302-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161830
Totals83010.304687.7452815.2864.1

CountyNAVARRO
HighwayFM0055
FromVARIOUS ROADS IN NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6302-64-001
Proj IDRMC - 630264001
Work TypeJOINT AND/OR CRACK SEALING
 
0.001100163.600.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order01-06-17
Work Began00-00-00
Work Completed
Time Computed02-06-17
Contract Working Days15
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GREENPAK SOLUTIONS, LIMITED LIABILITY COMPANY
SUBCONTRACTOR(S) FOR CCSJ: 6302-64-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161802
Totals100163.600.000.000.0

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-82-001
Proj IDRMC - 630282001
Work TypeFLEXIBLE PAVEMENT REPAIR
 
0.001208052.000.000.0
Work Order11-08-16
Work Began00-00-00
Work Completed
Time Computed12-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged56
Percent Time Used15
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-82-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161812
Totals208052.000.000.000.0

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-85-001
Proj IDRMC - 630285001
Work TypeJOINT AND/OR CRACK SEALING
 
0.001145109.480.000.0
Work Order12-21-16
Work Began00-00-00
Work Completed
Time Computed01-23-17
Contract Working Days28
Addl Days Granted0
Working Days Charged3
Percent Time Used10
Contractor(s)
KEGLEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-85-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161813
Totals145109.480.000.000.0

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-86-001
Proj IDRMC - 630286001
Work TypeJOINT AND/OR CRACK SEALING
 
0.001145465.140.000.0
Work Order12-20-16
Work Began01-23-17
Work Completed
Time Computed01-23-17
Contract Working Days25
Addl Days Granted0
Working Days Charged3
Percent Time Used12
Contractor(s)
KEGLEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-86-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161814
Totals145465.140.000.000.0

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-87-001
Proj IDRMC - 630287001
Work TypeJOINT AND/OR CRACK SEALING
 
0.001159306.2741601.5026.1
Work Order12-16-16
Work Began01-22-17
Work Completed
Time Computed01-09-17
Contract Working Days29
Addl Days Granted0
Working Days Charged4
Percent Time Used13
Contractor(s)
KEGLEY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-87-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161815
Totals159306.2741601.5041601.5026.1

CountyDALLAS
HighwayUS0080
FromDALLAS DISTRICT COMPLEX - 4777 E. HWY 80
ToMESQUITE, TEXAS 75150 AT SITES A THRU E
CSJ6303-16-001
Proj IDRMC - 630316001
Work TypeDISTRICT GROUNDS TREE TRIMMING &
 
0.001117050.00104750.0089.4
Work Order12-06-16
Work Began01-02-17
Work Completed
Time Computed01-02-17
Contract Working Days730
Addl Days Granted0
Working Days Charged24
Percent Time Used3
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6303-16-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161804
Totals117050.00104750.00104750.0089.4

CountyDALLAS
HighwayIH0030
FromVARIOUS LOCATIONS IN NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6304-56-001
Proj IDRMC - 630456001
Work TypeSPECIALTY MARKINGS
 
0.001216052.500.000.0
Work Order11-08-16
Work Began00-00-00
Work Completed
Time Computed12-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged56
Percent Time Used15
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6304-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161816
Totals216052.500.000.000.0

CountyDALLAS
HighwayIH0030
FromVARIOUS LOCATIONS IN NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6304-58-001
Proj IDRMC - 630458001
Work TypeVEGETATION MANAGEMENT
 
0.001245175.0017459.007.1
Work Order11-22-16
Work Began12-05-16
Work Completed
Time Computed12-05-16
Contract Working Days68
Addl Days Granted16
Working Days Charged2
Percent Time Used2
Contractor(s)
JASCO
SUBCONTRACTOR(S) FOR CCSJ: 6304-58-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161803
Totals245175.000.0017459.007.1

CountyDALLAS
HighwayIH0035E
FromVARIOUS LOCATIONS IN NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6304-59-001
Proj IDRMC - 630459001
Work TypeRAISED PAVEMENT MARKERS
 
0.001158233.400.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6304-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161809
Totals158233.400.000.000.0

CountyDALLAS
HighwayIH0030
FromVARIOUS LOCATIONS IN SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6305-37-001
Proj IDRMC - 630537001
Work TypeSPECIALTY MARKINGS
 
0.001167772.820.000.0
Work Order11-10-16
Work Began00-00-00
Work Completed
Time Computed12-01-16
Contract Working Days365
Addl Days Granted0
Working Days Charged56
Percent Time Used15
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6305-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161805
Totals167772.820.000.000.0

CountyDALLAS
HighwayIH0020
FromVARIOUS LOCATIONS IN SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6305-54-001
Proj IDRMC - 630554001
Work TypeSPECIALTY MARKINGS
 
0.001210597.320.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order02-03-17
Work Began00-00-00
Work Completed
Time Computed02-10-17
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6305-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09161806
Totals210597.320.000.000.0