Monthly Local Let Maintenance Report For Dallas District As Of Jan 10, 2018 Page 1 Of 4

Last Update: Wednesday, January 10, 2018
FTP Icon
page 1 | page 2 | page 3 | page 4

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6201-06-001
Proj IDRMC - 620106001
Work TypeREFLECTORIZED PAVEMENT MARKINGS
 
0.001191208.00162028.5784.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-11
Work Began05-18-11
Work Completed
Time Computed07-17-11
Contract Working Days730
Addl Days Granted80
Working Days Charged810
Percent Time Used100
Contractor(s)
INTERSTATE ROAD MANAGEMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6201-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04111801
Totals191208.000.00162028.5784.7

CountyKAUFMAN
HighwayMR0682
FromVARIOUS LOCATIONS AT THE
ToTERRELL STATE HOSPITAL
CSJ6207-65-001
Proj IDRMC - 620765001
Work TypeREHABILITATE ROADWAYS
 
0.001179519.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07101802
Totals179519.150.000.000.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6208-46-001
Proj IDRMC - 620846001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
88.77750652.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRAXTON TRANSPORTATION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6208-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09101801
Totals50652.700.000.000.0

CountyROCKWALL
HighwayIH0030
FromIH30 AT PARKER CREEK, PARKER CREEK
ToBRANCH, FM551 HACKBERRY CREEK, US175
CSJ6259-42-001
Proj IDBPM - 625942001
Work TypeREPLACE WINGWALLS & REPAIR SPALLING
 
0.001130385.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11131801
Totals130385.000.000.000.0

CountyCOLLIN
HighwaySH0078
FromAT PRICE CREEK
ToIN COLLIN COUNTY
CSJ6274-02-001
Proj IDBPM - 627402001
Work TypeREPAIR OF ABUTMENT SLOPES
 
0.00149292.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days18
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11141803
Totals49292.000.000.000.0

CountyDALLAS
HighwayIH0030
FromIH 30 AT ST PAUL UNDERPASS IN THE
ToNORTHEAST DALLAS MAINTENANCE SECTION
CSJ6286-56-001
Proj IDRMC - 628656001
Work TypeINSTALL FENCE
 
0.001102710.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151804
Totals102710.000.000.000.0

CountyKAUFMAN
HighwayIH0020
FromVARIOUS LOCATION IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6291-42-001
Proj IDRMC - 629142001
Work TypeRAISED PAVEMENT MARKERS
 
0.001133279.7053337.0040.0
Work Order12-01-16
Work Began12-08-16
Work Completed
Time Computed12-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged380
Percent Time Used52
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6291-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161801
Totals133279.70624.4053337.0040.0

CountyNAVARRO
HighwaySH0022
FromVARIOUS ROADWAYS IN THE NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6292-76-001
Proj IDRMC - 629276001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001163060.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161805
Totals163060.000.000.000.0

CountyELLIS
HighwayFM0813
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6296-95-001
Proj IDRMC - 629695001
Work TypeREMOVAL AND DISPOSAL OF DRIFTWOOD
 
0.001274500.00157770.0057.4
Work Order02-22-16
Work Began01-26-16
Work Completed
Time Computed02-29-16
Contract Working Days730
Addl Days Granted0
Working Days Charged669
Percent Time Used91
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6296-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161801
Totals274500.000.00157770.0057.4

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6297-44-001
Proj IDRMC - 629744001
Work TypeSPECIALTY MARKINGS
 
0.001273952.00121625.0744.3
Work Order06-27-16
Work Began07-06-16
Work Completed
Time Computed07-05-16
Contract Working Days730
Addl Days Granted0
Working Days Charged538
Percent Time Used73
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161805
Totals273952.0032642.56121625.0744.3

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6299-11-001
Proj IDRMC - 629911001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.00139801.0039795.9099.9
Work Order03-08-17
Work Began03-15-17
Work Completed
Time Computed03-15-17
Contract Working Days63
Addl Days Granted0
Working Days Charged26
Percent Time Used41
Contractor(s)
A&O GENERAL CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161803
Totals39801.000.0039795.9099.9

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN THE NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6299-12-001
Proj IDRMC - 629912001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001248800.00233580.8093.8
Work Order02-07-17
Work Began02-15-17
Work Completed
Time Computed02-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged309
Percent Time Used84
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161804
Totals248800.000.00233580.8093.8

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6301-23-001
Proj IDRMC - 630123001
Work TypeRAISED PAVEMENT MARKERS
 
0.001111857.94108044.7396.5
Work Order09-23-16
Work Began09-30-16
Work Completed
Time Computed09-30-16
Contract Working Days365
Addl Days Granted300
Working Days Charged453
Percent Time Used68
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161802
Totals111857.940.00108044.7396.5

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6301-24-001
Proj IDRMC - 630124001
Work TypeCALL OUT REFLECTORIZED PAVEMENT MARKINGS
 
0.001171011.4484912.4049.6
Work Order09-13-16
Work Began09-20-16
Work Completed
Time Computed09-20-16
Contract Working Days730
Addl Days Granted0
Working Days Charged463
Percent Time Used63
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161803
Totals171011.440.0084912.4049.6

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-00-001
Proj IDRMC - 630200001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001253810.00233834.2092.1
Work Order02-03-17
Work Began02-10-17
Work Completed
Time Computed01-17-17
Contract Working Days365
Addl Days Granted0
Working Days Charged319
Percent Time Used87
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 6302-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161806
Totals253810.0026345.05233834.2092.1

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN THE NORTHEAST DALLAS
ToCOUNTY MAINTENANCE SECTION
CSJ6302-02-001
Proj IDRMC - 630202001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.00152200.0050800.0097.3
Work Order04-05-17
Work Began04-17-17
Work Completed
Time Computed04-17-17
Contract Working Days63
Addl Days Granted0
Working Days Charged45
Percent Time Used71
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6302-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161807
Totals52200.000.0050800.0097.3

CountyDALLAS
HighwaySL0012
FromVARIOUS ROADWAYS IN THE NORTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-03-001
Proj IDRMC - 630203001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.0010.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-03-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161802
Totals0.000.000.000.0

CountyDALLAS
HighwayUS0067
FromVARIOUS ROADWAYS IN THE SOUTHWEST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-04-001
Proj IDRMC - 630204001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.00155500.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-04-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #10161803
Totals55500.000.000.000.0

CountyDALLAS
HighwayIH0030
FromVARIOUS LOCATIONS IN NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-37-001
Proj IDRMC - 630237001
Work TypeRAISED PAVEMENT MARKERS
 
0.001121982.34113042.3492.6
Work Order02-07-17
Work Began02-15-17
Work Completed
Time Computed02-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged309
Percent Time Used84
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6302-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161808
Totals121982.340.00113042.3492.6

CountyNAVARRO
HighwayIH0045
FromVARIOUS ROADWAYS IN THE NAVARRO
ToCOUNTY MAINTENANCE SECTION
CSJ6302-47-001
Proj IDSUP - 630247001
Work TypeLITTER REMOVAL
 
0.00148732.2446576.4495.5
Work Order06-18-16
Work Began09-01-16
Work Completed
Time Computed09-01-16
Contract Working Days730
Addl Days Granted0
Working Days Charged474
Percent Time Used64
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6302-47-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06161830
Totals48732.24501.3246576.4495.5

page 1 | page 2 | page 3 | page 4