Monthly Local Let Maintenance Report For Dallas District As Of Sep 21, 2017 Page 1 Of 5

Last Update: Friday, September 22, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6201-06-001
Proj IDRMC - 620106001
Work TypeREFLECTORIZED PAVEMENT MARKINGS
 
0.001191208.00162028.5784.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-11
Work Began05-18-11
Work Completed
Time Computed07-17-11
Contract Working Days730
Addl Days Granted80
Working Days Charged810
Percent Time Used100
Contractor(s)
INTERSTATE ROAD MANAGEMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6201-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04111801
Totals191208.000.00162028.5784.7

CountyKAUFMAN
HighwayMR0682
FromVARIOUS LOCATIONS AT THE
ToTERRELL STATE HOSPITAL
CSJ6207-65-001
Proj IDRMC - 620765001
Work TypeREHABILITATE ROADWAYS
 
0.001179519.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07101802
Totals179519.150.000.000.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6208-46-001
Proj IDRMC - 620846001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
88.77750652.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRAXTON TRANSPORTATION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6208-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09101801
Totals50652.700.000.000.0

CountyROCKWALL
HighwayIH0030
FromIH30 AT PARKER CREEK, PARKER CREEK
ToBRANCH, FM551 HACKBERRY CREEK, US175
CSJ6259-42-001
Proj IDBPM - 625942001
Work TypeREPLACE WINGWALLS & REPAIR SPALLING
 
0.001130385.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11131801
Totals130385.000.000.000.0

CountyCOLLIN
HighwaySH0078
FromAT PRICE CREEK
ToIN COLLIN COUNTY
CSJ6274-02-001
Proj IDBPM - 627402001
Work TypeREPAIR OF ABUTMENT SLOPES
 
0.00149292.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days18
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11141803
Totals49292.000.000.000.0

CountyDENTON
HighwayUS0380
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6276-59-001
Proj IDRMC - 627659001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001325986.80284315.4787.2
Work Order09-14-15
Work Began09-14-15
Work Completed
Time Computed09-21-15
Contract Working Days365
Addl Days Granted365
Working Days Charged710
Percent Time Used97
Contractor(s)
ALTUS TRAFFIC MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6276-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03151802
Totals325986.8013544.51284315.4787.2

CountyDALLAS
HighwayIH0030
FromIH 30 AT ST PAUL UNDERPASS IN THE
ToNORTHEAST DALLAS MAINTENANCE SECTION
CSJ6286-56-001
Proj IDRMC - 628656001
Work TypeINSTALL FENCE
 
0.001102710.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151804
Totals102710.000.000.000.0

CountyROCKWALL
HighwayIH0030
FromIH, US, SH AND FM ROADWAYS IN
ToROCKWALL & COLLIN COUNTY
CSJ6289-97-001
Proj IDRMC - 628997001
Work TypeVEGETATION MANAGEMENT
 
0.001261360.00158848.5060.7
Work Order05-26-17
Work Began03-31-16
Work Completed
Time Computed06-05-17
Contract Working Days50
Addl Days Granted0
Working Days Charged50
Percent Time Used100
Contractor(s)
GANT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151801
Totals261360.000.00158848.5060.7

CountyKAUFMAN
HighwayIH0020
FromVARIOUS LOCATION IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6291-42-001
Proj IDRMC - 629142001
Work TypeRAISED PAVEMENT MARKERS
 
0.001133279.7038836.1529.1
Work Order12-01-16
Work Began12-08-16
Work Completed
Time Computed12-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged257
Percent Time Used35
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6291-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161801
Totals133279.700.0038836.1529.1

CountyNAVARRO
HighwaySH0022
FromVARIOUS ROADWAYS IN THE NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6292-76-001
Proj IDRMC - 629276001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001163060.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161805
Totals163060.000.000.000.0

CountyNAVARRO
HighwaySH0031
FromNAVARRO COUNTY AREA AND MAINTENANCE
ToFACILITIES
CSJ6294-55-001
Proj IDSUP - 629455001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.00122073.9218182.6882.3
Work Order11-23-15
Work Began12-01-15
Work Completed
Time Computed12-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged634
Percent Time Used86
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6294-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151830
Totals22073.92902.0818182.6882.3

CountyNAVARRO
HighwaySH0031
FromNAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6294-56-001
Proj IDSUP - 629456001
Work TypePICNIC AREA MAINTENANCE
 
0.00127280.0022560.0082.6
Work Order11-23-15
Work Began12-01-15
Work Completed
Time Computed12-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged637
Percent Time Used87
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6294-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151832
Totals27280.001230.0022560.0082.6

CountyELLIS
HighwayIH0035E
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6296-81-001
Proj IDRMC - 629681001
Work TypeREFLECTORIZED PAVEMENT MARKERS
 
0.00196388.4067048.8569.5
Work Order04-29-16
Work Began05-06-16
Work Completed
Time Computed05-06-16
Contract Working Days365
Addl Days Granted203
Working Days Charged483
Percent Time Used85
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161804
Totals96388.4034843.6867048.8569.5

CountyELLIS
HighwayFM0813
FromVARIOUS ROADWAYS IN THE
ToELLIS COUNTY MAINTENANCE SECTION
CSJ6296-95-001
Proj IDRMC - 629695001
Work TypeREMOVAL AND DISPOSAL OF DRIFTWOOD
 
0.001274500.00157770.0057.4
Work Order02-22-16
Work Began01-26-16
Work Completed
Time Computed02-29-16
Contract Working Days730
Addl Days Granted0
Working Days Charged543
Percent Time Used74
Contractor(s)
TEXAS TREE & LANDSCAPE, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 6296-95-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161801
Totals274500.000.00157770.0057.4

CountyELLIS
HighwayUS0287
FromVARIOUS ROADWAYS IN ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6297-44-001
Proj IDRMC - 629744001
Work TypeSPECIALTY MARKINGS
 
0.001273952.0060713.5122.1
Work Order06-27-16
Work Began07-06-16
Work Completed
Time Computed07-05-16
Contract Working Days730
Addl Days Granted0
Working Days Charged422
Percent Time Used57
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6297-44-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #05161805
Totals273952.0015376.4360713.5122.1

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6299-11-001
Proj IDRMC - 629911001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
0.00139801.0037184.9093.4
Work Order03-08-17
Work Began03-15-17
Work Completed
Time Computed03-15-17
Contract Working Days63
Addl Days Granted0
Working Days Charged26
Percent Time Used41
Contractor(s)
A&O GENERAL CONTRACTORS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6299-11-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161803
Totals39801.000.0037184.9093.4

CountyDALLAS
HighwaySH0078
FromVARIOUS ROADWAYS IN THE NORTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6299-12-001
Proj IDRMC - 629912001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001248800.00120640.8048.4
Work Order02-07-17
Work Began02-15-17
Work Completed
Time Computed02-15-17
Contract Working Days365
Addl Days Granted0
Working Days Charged192
Percent Time Used52
Contractor(s)
WEST TEXAS REBAR PLACERS INC.
SUBCONTRACTOR(S) FOR CCSJ: 6299-12-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161804
Totals248800.0024900.00120640.8048.4

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6301-23-001
Proj IDRMC - 630123001
Work TypeRAISED PAVEMENT MARKERS
 
0.001111857.94108044.7396.5
Work Order09-23-16
Work Began09-30-16
Work Completed
Time Computed09-30-16
Contract Working Days365
Addl Days Granted0
Working Days Charged334
Percent Time Used91
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6301-23-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161802
Totals111857.942233.00108044.7396.5

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6301-24-001
Proj IDRMC - 630124001
Work TypeCALL OUT REFLECTORIZED PAVEMENT MARKINGS
 
0.001171011.4484912.4049.6
Work Order09-13-16
Work Began09-20-16
Work Completed
Time Computed09-20-16
Contract Working Days730
Addl Days Granted0
Working Days Charged340
Percent Time Used46
Contractor(s)
STRIPE-A-ZONE, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6301-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07161803
Totals171011.440.0084912.4049.6

CountyDALLAS
HighwayUS0080
FromVARIOUS ROADWAYS IN THE SOUTHEAST
ToDALLAS COUNTY MAINTENANCE SECTION
CSJ6302-00-001
Proj IDRMC - 630200001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001253810.00117992.3046.4
Work Order02-03-17
Work Began02-10-17
Work Completed
Time Computed01-17-17
Contract Working Days365
Addl Days Granted0
Working Days Charged197
Percent Time Used53
Contractor(s)
IOWA BRIDGE & CULVERT, LC
SUBCONTRACTOR(S) FOR CCSJ: 6302-00-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11161806
Totals253810.0042005.00117992.3046.4

page 1 | page 2 | page 3 | page 4 | page 5