Monthly Local Let Maintenance Report For Dallas District As Of Jul 14, 2017 Page 1 Of 5

Last Update: Monday, July 17, 2017
FTP Icon
page 1 | page 2 | page 3 | page 4 | page 5

Contract Identification and InformationLengthContract AmountAmount This EstimateTotal Estimate To Date% Comp

CountyELLIS
HighwayIH0045
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6201-06-001
Proj IDRMC - 620106001
Work TypeREFLECTORIZED PAVEMENT MARKINGS
 
0.001191208.00162028.5784.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order05-18-11
Work Began05-18-11
Work Completed
Time Computed07-17-11
Contract Working Days730
Addl Days Granted80
Working Days Charged810
Percent Time Used100
Contractor(s)
INTERSTATE ROAD MANAGEMENT CORP.
SUBCONTRACTOR(S) FOR CCSJ: 6201-06-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #04111801
Totals191208.000.00162028.5784.7

CountyKAUFMAN
HighwayMR0682
FromVARIOUS LOCATIONS AT THE
ToTERRELL STATE HOSPITAL
CSJ6207-65-001
Proj IDRMC - 620765001
Work TypeREHABILITATE ROADWAYS
 
0.001179519.150.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days25
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
APAC-TEXAS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6207-65-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07101802
Totals179519.150.000.000.0

CountyCOLLIN
HighwayUS0075
FromVARIOUS ROADWAYS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6208-46-001
Proj IDRMC - 620846001
Work TypeTREE TRIMMING AND BRUSH REMOVAL
 
88.77750652.700.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days107
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
BRAXTON TRANSPORTATION LLC
SUBCONTRACTOR(S) FOR CCSJ: 6208-46-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09101801
Totals50652.700.000.000.0

CountyROCKWALL
HighwayIH0030
FromIH30 AT PARKER CREEK, PARKER CREEK
ToBRANCH, FM551 HACKBERRY CREEK, US175
CSJ6259-42-001
Proj IDBPM - 625942001
Work TypeREPLACE WINGWALLS & REPAIR SPALLING
 
0.001130385.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days30
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 6259-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11131801
Totals130385.000.000.000.0

CountyCOLLIN
HighwaySH0078
FromAT PRICE CREEK
ToIN COLLIN COUNTY
CSJ6274-02-001
Proj IDBPM - 627402001
Work TypeREPAIR OF ABUTMENT SLOPES
 
0.00149292.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days18
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
MHB CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6274-02-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #11141803
Totals49292.000.000.000.0

CountyDENTON
HighwayUS0380
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6276-59-001
Proj IDRMC - 627659001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001325986.80255825.1878.4
Work Order09-14-15
Work Began09-14-15
Work Completed
Time Computed09-21-15
Contract Working Days365
Addl Days Granted365
Working Days Charged645
Percent Time Used88
Contractor(s)
ALTUS TRAFFIC MANAGEMENT LLC
SUBCONTRACTOR(S) FOR CCSJ: 6276-59-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03151802
Totals325986.8017406.84255825.1878.4

CountyCOLLIN
HighwayUS0075
FromVARIOUS LOCATIONS IN THE COLLIN
ToCOUNTY MAINTENANCE SECTION
CSJ6283-24-001
Proj IDRMC - 628324001
Work TypeMISCELLANEOUS CONCRETE REPAIR
 
0.001274893.80261601.5795.1
Work Order08-27-15
Work Began09-01-15
Work Completed
Time Computed09-08-15
Contract Working Days730
Addl Days Granted0
Working Days Charged660
Percent Time Used90
Contractor(s)
GHB EQUIPMENT COMPANY, L.L.C.
SUBCONTRACTOR(S) FOR CCSJ: 6283-24-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #06151801
Totals274893.8085700.00261601.5795.1

CountyDALLAS
HighwayIH0030
FromIH 30 AT ST PAUL UNDERPASS IN THE
ToNORTHEAST DALLAS MAINTENANCE SECTION
CSJ6286-56-001
Proj IDRMC - 628656001
Work TypeINSTALL FENCE
 
0.001102710.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days10
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
GIBSON & ASSOCIATES, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6286-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #07151804
Totals102710.000.000.000.0

CountyCOLLIN
HighwaySH0078
FromCOLLIN
ToCOUNTY
CSJ6288-30-001
Proj IDSUP - 628830001
Work TypePICNIC AREA AND LANDSCAPE MAINTENANCE
 
0.00188682.2869696.7178.5
Work Order07-22-15
Work Began08-01-15
Work Completed
Time Computed08-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged696
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6288-30-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151830
Totals88682.285570.1969696.7178.5

CountyCOLLIN
HighwaySH0005
FromCOLLIN COUNTY AREA OFFICE AND
ToMAINTENANCE FACILITY
CSJ6288-31-001
Proj IDSUP - 628831001
Work TypeJANITORIAL MAINTENANCE
 
0.00139490.6435181.0389.0
Work Order07-29-15
Work Began08-01-15
Work Completed
Time Computed08-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged696
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6288-31-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151834
Totals39490.641529.6135181.0389.0

CountyDENTON
HighwayFM0407
FromVARIOUS ROADWAYS IN THE DENTON
ToCOUNTY MAINTENANCE SECTION
CSJ6288-37-001
Proj IDSUP - 628837001
Work TypeLITTER REMOVAL
 
0.001182875.64158355.5886.5
Work Order08-06-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged662
Percent Time Used90
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6288-37-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151831
Totals182875.645231.21158355.5886.5

CountyROCKWALL
HighwayIH0030
FromIH, US, SH AND FM ROADWAYS IN
ToROCKWALL & COLLIN COUNTY
CSJ6289-97-001
Proj IDRMC - 628997001
Work TypeVEGETATION MANAGEMENT
 
0.001261360.00144918.5055.4
Work Order05-26-17
Work Began03-31-16
Work Completed
Time Computed06-05-17
Contract Working Days50
Addl Days Granted0
Working Days Charged48
Percent Time Used96
Contractor(s)
GANT CONTRACTORS, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6289-97-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151801
Totals261360.0038117.50144918.5055.4

CountyKAUFMAN
HighwayIH0020
FromVARIOUS LOCATION IN THE KAUFMAN/
ToROCKWALL MAINTENANCE SECTION
CSJ6291-42-001
Proj IDRMC - 629142001
Work TypeRAISED PAVEMENT MARKERS
 
0.001133279.7038836.1529.1
Work Order12-01-16
Work Began12-08-16
Work Completed
Time Computed12-08-16
Contract Working Days730
Addl Days Granted0
Working Days Charged201
Percent Time Used27
Contractor(s)
TEXAS TMA RENTAL
SUBCONTRACTOR(S) FOR CCSJ: 6291-42-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161801
Totals133279.700.0038836.1529.1

CountyCOLLIN
HighwaySH0005
FromCOLLIN COUNTY AREA OFFICE AND
ToMAINTENANCE FACILITY
CSJ6291-67-001
Proj IDSUP - 629167001
Work TypeGROUNDS MAINTENANCE
 
0.00118000.008700.0048.3
Work Order07-29-15
Work Began08-01-15
Work Completed
Time Computed08-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged696
Percent Time Used95
Contractor(s)
TIBH INDUSTRIES, INC.
LIBERTY PROCLAIMED MINISTRY
SUBCONTRACTOR(S) FOR CCSJ: 6291-67-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #08151833
Totals18000.00900.008700.0048.3

CountyDALLAS
HighwayIH0045
FromHUTCHINS TXDOT OFFICE
ToMAINTENANCE FACILITIES
CSJ6292-52-001
Proj IDSUP - 629252001
Work TypeJANITORIAL MAINTENANCE
 
0.00126700.0016500.0061.7
Work Order08-06-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged664
Percent Time Used90
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-52-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151835
Totals26700.00750.0016500.0061.7

CountyKAUFMAN
HighwaySH0034
FromKAUFMAN TXDOT
ToFACILITY
CSJ6292-54-001
Proj IDSUP - 629254001
Work TypeJANITORIAL MAINTENANCE
 
0.00136950.0029380.0079.5
Work Order08-19-15
Work Began09-01-15
Work Completed
Time Computed09-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged665
Percent Time Used90
Contractor(s)
TIBH INDUSTRIES, INC.
A LIFT FOR LIFE OUTREACH CENTER, INC.
SUBCONTRACTOR(S) FOR CCSJ: 6292-54-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #09151837
Totals36950.001400.0029380.0079.5

CountyNAVARRO
HighwaySH0022
FromVARIOUS ROADWAYS IN THE NAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6292-76-001
Proj IDRMC - 629276001
Work TypeON-CALL TRAFFIC CONTROL SERVICES
 
0.001163060.000.000.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order00-00-00
Work Began00-00-00
Work Completed
Time Computed00-00-00
Contract Working Days365
Addl Days Granted0
Working Days Charged0
Percent Time Used0
Contractor(s)
TOTAL HIGHWAY MAINTENANCE, LLC
SUBCONTRACTOR(S) FOR CCSJ: 6292-76-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #01161805
Totals163060.000.000.000.0

CountyNAVARRO
HighwaySH0031
FromNAVARRO COUNTY AREA AND MAINTENANCE
ToFACILITIES
CSJ6294-55-001
Proj IDSUP - 629455001
Work TypeJANITORIAL AND GROUNDS MAINTENANCE
 
0.00122073.9216378.5274.1
Work Order11-23-15
Work Began12-01-15
Work Completed
Time Computed12-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged575
Percent Time Used78
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6294-55-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151830
Totals22073.92999.0816378.5274.1

CountyNAVARRO
HighwaySH0031
FromNAVARRO COUNTY
ToMAINTENANCE SECTION
CSJ6294-56-001
Proj IDSUP - 629456001
Work TypePICNIC AREA MAINTENANCE
 
0.00127280.0020310.0074.4
Work Order11-23-15
Work Began12-01-15
Work Completed
Time Computed12-01-15
Contract Working Days731
Addl Days Granted0
Working Days Charged574
Percent Time Used78
Contractor(s)
TIBH INDUSTRIES, INC.
CEN-TEX ASSOCIATION FOR RETARDED CHILDREN
SUBCONTRACTOR(S) FOR CCSJ: 6294-56-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #12151832
Totals27280.001230.0020310.0074.4

CountyELLIS
HighwayIH0035E
FromVARIOUS ROADWAYS IN THE ELLIS
ToCOUNTY MAINTENANCE SECTION
CSJ6296-81-001
Proj IDRMC - 629681001
Work TypeREFLECTORIZED PAVEMENT MARKERS
 
0.00196388.4023052.1123.9
Work Order04-29-16
Work Began05-06-16
Work Completed
Time Computed05-06-16
Contract Working Days365
Addl Days Granted203
Working Days Charged416
Percent Time Used73
Contractor(s)
DEANGELO BROTHERS LLC
SUBCONTRACTOR(S) FOR CCSJ: 6296-81-001
NO SUBCONTRACTORS FOR THIS CCSJ
Contract #03161804
Totals96388.408312.5823052.1123.9

page 1 | page 2 | page 3 | page 4 | page 5