Monthly State Let Construction Report For Childress District As Of May 10, 2016 Page 2 Of 2

Last Update: Tuesday, May 10, 2016
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyCHILDRESS
Highway VA
From DISTRICT WIDE STRIPING
To .
CSJ 0925-00-064
Proj ID NH 1602(030)
Work Type DISTRICT WIDE STRIPING
 
0.100 774832.38 0.00 73739.20 9.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 04-13-16
Work Began 04-21-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 6
Percent Time Used 12
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-00-064
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03163025
Totals 774832.38 0.00 73739.20 9.5

CountyHARDEMAN
Highway CR
From GOODLET ROAD @ N GROESBECK CREEK
To .
CSJ 0925-07-029
Proj ID BR 2013(295)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.085 757526.00 0.00 562122.74 74.2
CountyHALL
Highway CR
From CR 24 ., @ DRAW
To .
CSJ 0925-09-034
Proj ID BR 2013(294)
Work Type REPLACEMNET OF BRIDGE
 
0.061 189175.00 0.00 185975.00 98.3
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 11-02-15
Work Began 12-05-15
Work Completed  
Time Computed 00-00-00
Contract Working Days 136
Addl Days Granted 0
Working Days Charged 71
Percent Time Used 52
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-07-029
CONTRACTORS SERVICE COMPANY(0.92%)
DUSTIN ALLEN, INC. (5.63%)
LANCO TURF & SEEDING, INC. (3.83%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. ( 11.77%)
MCL CONTRACTING, LLC (0.48%)
Contract # 08153026
Totals 946701.00 0.00 748097.74 79.0

CountyCOTTLE
Highway PW
From MATADOR WILDLIFE AREA
To .
CSJ 0925-14-008
Proj ID C 0925-14-008
Work Type REPLACEMENT OF LOW WATER CROSSING
 
0.066 142752.00 0.00 1000.00 0.7
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 02-03-16
Work Began 04-07-16
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 7
Percent Time Used 13
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0925-14-008
WOLFE CONSTRUCTION GROUP, INC. (1.91%)
ALTUS TRAFFIC MANAGEMENT LLC (2.72%)
Contract # 11153210
Totals 142752.00 0.00 1000.00 0.7

CountyDICKENS
Highway CR
From @ WILSON DRAW
To .
CSJ 0925-15-013
Proj ID BR 2016(927)
Work Type BRIDGE REPLACEMENT
 
0.063 299045.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 51
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
CDM HOLDINGS, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0925-15-013
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04163214
Totals 299045.00 0.00 0.00 0.0

CountyWHEELER
Highway FM 2697
From 1 MI WEST OF FM 592, EAST
To END OF PAVEMENT
CSJ 2632-01-009
Proj ID STP 1502(082)
Work Type WIDENING OF A NON - FREEWAY FACILITY
 
4.009 3144808.05 961980.50 1478312.75 47.0
Work Order 07-14-15
Work Began 12-09-15
Work Completed  
Time Computed 01-18-16
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 44
Percent Time Used 43
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 2632-01-009
BARRICADES UNLIMITED (1.57%)
DUSTROL, INC.(0.30%)
HJC FARMS, INC.(3.89%)
Contract # 05153049
Totals 3144808.05 961980.50 1478312.75 47.0

page 1 | page 2