Monthly State Let Construction Report For Childress District As Of Aug 12, 2014 Page 1 Of 2

Last Update: Tuesday, August 12, 2014
FTP Icon
page 1 | page 2

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWHEELER
Highway US 83 ETC
From FM 1046, S
To SH 152
CSJ 0030-08-033
Proj ID STP 2014(004)
Work Type SEAL COAT
 
147.938 5038371.89 2235402.76 4312862.26 85.6
Work Order 10-10-13
Work Began 06-25-14
Work Completed  
Time Computed 10-26-13
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 21
Percent Time Used 42
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-08-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09133237
Totals 5038371.89 2235402.76 4312862.26 85.6

CountyKING
Highway US 83
From COTTLE C/L, S
To GUTHRIE
CSJ 0032-05-038
Proj ID C 32-5-38
Work Type MISCELLANEOUS WORK
 
15.270 77364.00 0.00 0.00 0.0
CountyKING
Highway US 83
From US 82, S
To STONEWALL C/L
CSJ 0032-06-036
Proj ID C 32-6-36
Work Type MISCELLANEOUS WORK
 
14.440 8596.00 0.00 0.00 0.0
CountyHALL
Highway SH 256
From 0.3 MILES E OF SH 70, E
To FM 2361
CSJ 0541-02-030
Proj ID C 541-2-30
Work Type REPLACE BRIDGERAIL
 
30.323 581853.35 0.00 119526.24 20.5
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-12
Work Began 00-00-00
Work Completed  
Time Computed 09-05-12
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0541-02-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06123013
Totals 667813.35 0.00 119526.24 17.8

CountyDONLEY
Highway US 287
From ARMSTRONG C/L
To CLARENDON WCL (SBL)
CSJ 0042-06-067
Proj ID NH 2014(061)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
11.635 2248102.73 0.00 193911.65 8.6
Work Order 01-17-14
Work Began 00-00-00
Work Completed  
Time Computed 02-02-14
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-06-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10133207
Totals 2248102.73 0.00 193911.65 8.6

CountyHALL
Highway US 287
From RED RIVER BRIDGE, SE
To CHILDRESS C/L (NBL)
CSJ 0042-09-120
Proj ID NH 2014(752)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
3.350 1106400.71 0.00 0.00 0.0
CountyCHILDRESS
Highway US 287
From HALL C/L, SE
To 0.36 MILES WEST OF FM 164(NBL)
CSJ 0042-12-063
Proj ID NH 2014(752)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
9.172 3136409.13 0.00 0.00 0.0
Work Order 05-09-14
Work Began 00-00-00
Work Completed  
Time Computed 05-25-14
Contract Working Days 73
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-12-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143032
Totals 4242809.84 0.00 0.00 0.0

CountyHARDEMAN
Highway US 287
From FM 1166, SE
To LP 285 (SBL)
CSJ 0043-02-071
Proj ID NH 2014(062)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
5.395 1474832.91 117667.18 117667.18 7.9
Work Order 01-06-14
Work Began 07-31-14
Work Completed  
Time Computed 07-31-14
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 1
Percent Time Used 2
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-02-071
COTHRAN TRUCKING, LLC(5.12%)
DUSTROL, INC.(2.81%)
RICE ENVIRONMENTAL SERVICES(0.69%)
SCR CONSTRUCTION CO., INC. (4.05%)
TOTAL HIGHWAY MAINTENANCE, LLC (2.30%)
WEST TEXAS RUMBLE STRIP(0.64%)
Contract # 10133011
Totals 1474832.91 117667.18 117667.18 7.9

CountyHARDEMAN
Highway SH 6
From @ BNSF RR OVERPASS
To .
CSJ 0097-02-037
Proj ID BR 2014(756)
Work Type MISCELLANEOUS WORK
 
0.453 2936931.42 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 197
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
COPPELL CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0097-02-037
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143217
Totals 2936931.42 0.00 0.00 0.0

CountyHARDEMAN
Highway SH 6
From US 287, S
To 6 MILES
CSJ 0098-01-036
Proj ID STP 2014(757)
Work Type REHABILITATION OF EXISTING ROADWAY
 
6.000 4804257.07 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 103
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0098-01-036
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143019
Totals 4804257.07 0.00 0.00 0.0

CountyFOARD
Highway SH 6
From @ RAGGEDY CREEK
To .
CSJ 0098-02-025
Proj ID BR 1102(556)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.094 1135621.40 0.00 0.00 0.0
CountyFOARD
Highway FM 267
From @ BEAVER CREEK
To .
CSJ 2164-02-017
Proj ID BR 1102(557)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.114 644822.40 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 176
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0098-02-025
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06143215
Totals 1780443.80 0.00 0.00 0.0

CountyKNOX
Highway SH 6
From 0.374 MILES SOUTH OF FOARD C/L
To SOUTH 8.428 MILES
CSJ 0098-04-033
Proj ID STP 2013(270)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
8.428 3689620.50 81101.96 3634727.52 98.5
Work Order 01-23-13
Work Began 04-15-13
Work Completed  
Time Computed 02-08-13
Contract Working Days 158
Addl Days Granted 0
Working Days Charged 158
Percent Time Used 100
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0098-04-033
W.S. CONSTRUCTION COMPANY(6.04%)
HIGHWAY TECHNOLOGIES, INC. (0.33%)
COWBELL TRAFFIC SERVICES, INC. (0.26%)
HJC FARMS, INC.(0.58%)
COTHRAN TRUCKING, LLC(3.45%)
FLAT LINE, INC.(0.83%)
TEXAS ALTERNATIVE GRASSER, INC.(0.96%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.24%)
Contract # 12123022
Totals 3689620.50 81101.96 3634727.52 98.5

CountyMOTLEY
Highway SH 70
From NORTH PEASE RIVER
To .
CSJ 0105-04-042
Proj ID BR 2013(663)
Work Type REPLACEMENT OF EXISTING BRIDGE
 
0.240 2085247.00 -28984.51 1978563.73 94.8
CountyMOTLEY
Highway SH 70
From @ MIDDLE PEASE RIVER
To .
CSJ 0105-04-043
Proj ID BR 2013(663)
Work Type REPLACEMENT OF EXISTING BRIDGE
 
0.315 2182953.50 635533.48 1387971.01 63.5
Work Order 07-31-13
Work Began 09-03-13
Work Completed  
Time Computed 08-16-13
Contract Working Days 275
Addl Days Granted 8
Working Days Charged 189
Percent Time Used 66
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0105-04-042
BARRICADES UNLIMITED (0.82%)
DUSTROL, INC.(0.19%)
LANCO TURF & SEEDING, INC. (0.47%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.58%)
MASTERPIECE GRINDING & GROOVING, LLC (0.13%)
ROSS GRAHAM(0.40%)
G & L REBAR(0.49%)
MCL CONTRACTING, LLC (0.71%)
Contract # 05133233
Totals 4268200.50 606548.97 3366534.74 78.8

CountyCOLLINGSWORTH
Highway SH 203
From @ SALT FORK OF RED RIVER
To .
CSJ 0230-01-018
Proj ID C 230-1-18
Work Type REHABILITATION EXIST TRUSS BRIDGE
 
0.200 2895507.75 0.00 2961616.78 99.9
Work Order 09-24-12
Work Began 10-29-12
Work Completed  
Time Computed 10-29-12
Contract Working Days 202
Addl Days Granted 29
Working Days Charged 292
Percent Time Used 126
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0230-01-018
DUSTROL, INC.(0.37%)
S & S PAINTING ( 43.37%)
HIGHWAY TECHNOLOGIES, INC. (0.24%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(0.15%)
ODUM SERVICES, L.P.(0.71%)
TEXAS ALTERNATIVE GRASSER, INC.(0.06%)
SOUTHEAST GRINDING & GROOVING, LLC (0.13%)
J.L. STEEL REINFORCING, LLC(0.87%)
L. A. FULLER & SONS CONSTRUCTION, LTD. (2.95%)
Contract # 08123215
Totals 2895507.75 0.00 2961616.78 99.9

CountyHALL
Highway SH 86
From 118 FT E OF CR 3
To SH 70
CSJ 0303-05-018
Proj ID STP 2014(473)
Work Type REHABILITATION OF EXISTING ROADWAY
 
0.616 2600383.20 95404.51 332237.31 12.7
CountyHALL
Highway SH 86
From 118 FT E OF CR 3
To SH 70
CSJ 0303-05-019
Proj ID STP 1302(074)
Work Type ROW UTL. ADJ.
 
0.616 408330.05 105216.00 111816.00 27.3
Work Order 05-01-14
Work Began 06-02-14
Work Completed  
Time Computed 07-07-14
Contract Working Days 212
Addl Days Granted 0
Working Days Charged 29
Percent Time Used 13
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0303-05-018
ALAMO BROTHERS CONCRETE( 20.20%)
BARRICADES UNLIMITED (1.08%)
WEST TEXAS UTILITY CONTRACTORS, INC. ( 12.33%)
Contract # 03143216
Totals 3008713.25 200620.51 444053.31 14.7

CountyBRISCOE
Highway SH 207
From 4538 FT NORTH OF FM146
To 1435 FT NORTH OF FM146
CSJ 0357-06-020
Proj ID STP 2014(868)HES
Work Type REALIGN INTERSECTIONS
 
1.293 1025196.80 0.00 0.00 0.0
CountyBRISCOE
Highway SH 207
From 1435 FT NORTH OF FM146
To 1222 FT SOUTH OF FM146
CSJ 0970-03-021
Proj ID STP 2014(869)HES
Work Type REALIGN INTERSECTIONS
 
0.503 169641.70 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 102
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
GILVIN-TERRILL, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0357-06-020
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143232
Totals 1194838.50 0.00 0.00 0.0

CountyBRISCOE
Highway SH 207
From FLOYD C/L NORTH
To SH 86
CSJ 0453-06-011
Proj ID STP 2014(229)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
11.022 4243800.64 281030.87 521386.17 12.2
Work Order 01-06-14
Work Began 05-12-14
Work Completed  
Time Computed 05-12-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 33
Percent Time Used 33
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0453-06-011
ALTUS TRAFFIC MANAGEMENT LLC (0.32%)
FLAT LINE, INC.(0.73%)
SURFACE PREPARATION TECHNOLOGIES, LLC(0.17%)
TEXAS ALTERNATIVE GRASSER, INC.(0.59%)
HJC FARMS, INC.(0.69%)
TEX OP CONSTRUCTION, LP(0.16%)
WILLIS ELECTRIC CO., LP(0.92%)
Contract # 11133023
Totals 4243800.64 281030.87 521386.17 12.2

CountyKING
Highway SH 222
From US 82, SE
To KNOX C/L
CSJ 0496-03-010
Proj ID STP 2013(813)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
6.983 2445663.33 0.00 1115673.98 45.6
CountyKNOX
Highway SH 222
From KING C/L, SE
To 4.015 MILES
CSJ 0496-04-031
Proj ID STP 2013(813)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
4.015 1217352.66 0.00 425024.27 34.9
Work Order 08-19-13
Work Began 09-23-13
Work Completed  
Time Computed 09-04-13
Contract Working Days 203
Addl Days Granted 4
Working Days Charged 163
Percent Time Used 78
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0496-03-010
W.S. CONSTRUCTION COMPANY(6.00%)
CONTRACTORS SERVICE COMPANY(0.51%)
HJC FARMS, INC.(2.35%)
TEXAS ALTERNATIVE GRASSER, INC.(0.42%)
WEST TEXAS RUMBLE STRIP(0.15%)
ZACK BURKETT CO. ( 42.81%)
BARRICADES UNLIMITED (1.67%)
Contract # 06133026
Totals 3663015.99 0.00 1540698.25 42.0

CountyHALL
Highway FM 1547
From US 287
To 0.23 MILES EAST OF US 287
CSJ 0844-05-008
Proj ID STP 1402(008)RGS
Work Type CONSTRUCT RR GRADE SEPARATION STR
 
0.438 5436253.20 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 247
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0844-05-008
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 07143048
Totals 5436253.20 0.00 0.00 0.0

CountyCHILDRESS
Highway VA
From DISTRICT WIDE
To .
CSJ 0925-00-061
Proj ID STP 2014(474)
Work Type DISTRICT WIDE STRIPING AND RPM
 
200.000 975240.10 367694.58 1013144.65 99.9
Work Order 04-15-14
Work Began 05-12-14
Work Completed  
Time Computed 05-01-14
Contract Working Days 34
Addl Days Granted 10
Working Days Charged 35
Percent Time Used 79
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-00-061
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143010
Totals 975240.10 367694.58 1013144.65 99.9

CountyHARDEMAN
Highway CR
From STAR VALLEY RD @ DEVIL'S CREEK
To .
CSJ 0925-07-013
Proj ID BR 2002(752)
Work Type REPLACE EXISTING BRIDGE FACILITY
 
0.075 403203.75 141020.00 295642.50 73.3
Work Order 03-13-14
Work Began 04-22-14
Work Completed  
Time Computed 04-21-14
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 52
Percent Time Used 66
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0925-07-013
DUSTY ALLEN, INC.(3.62%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.61%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.74%)
TEXAS ALTERNATIVE GRASSER, INC.(2.07%)
MCL CONTRACTING, LLC (0.53%)
Contract # 02143013
Totals 403203.75 141020.00 295642.50 73.3

CountyHALL
Highway CR
From CR D @ POLECAT CREEK
To .
CSJ 0925-09-030
Proj ID BR 2011(863)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.080 202931.08 3250.00 96919.96 47.7
Work Order 03-25-14
Work Began 05-28-14
Work Completed  
Time Computed 05-23-14
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 27
Percent Time Used 39
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-09-030
ALTUS TRAFFIC MANAGEMENT LLC (1.61%)
HJC FARMS, INC.(7.99%)
GARZA CONCRETE CONSTRUCTION( 27.26%)
Contract # 02143223
Totals 202931.08 3250.00 96919.96 47.7

CountyDICKENS
Highway CR
From 5TH STREET @ J2 CREEK
To .
CSJ 0925-15-007
Proj ID BR 2013(892)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.054 277834.00 42907.54 82907.54 29.8
CountyDICKENS
Highway CR
From CR 222 @ COTTONWOOD CREEK
To .
CSJ 0925-15-008
Proj ID BR 2013(892)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.109 419578.00 78000.00 96000.00 22.8
CountyDICKENS
Highway CR
From CR 386 @ WILSON DRAW
To .
CSJ 0925-15-009
Proj ID BR 2014(790)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.065 218564.00 0.00 0.00 0.0
Work Order 05-29-14
Work Began 06-26-14
Work Completed  
Time Computed 06-14-14
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 20
Percent Time Used 15
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-15-007
DUSTY ALLEN, INC.(4.59%)
BARRICADES UNLIMITED (1.31%)
TEXAS ALTERNATIVE GRASSER, INC.(1.70%)
Contract # 04143230
Totals 915976.00 120907.54 178907.54 19.5

page 1 | page 2