Monthly State Let Construction Report For Childress District As Of Apr 11, 2014 Page 1 Of 1

Last Update: Friday, April 11, 2014
FTP Icon
page 1

Contract Identification and Information Length Contract Amount Amount This Estimate Total Estimate To Date % Comp

CountyWHEELER
Highway US 83 ETC
From FM 1046, S
To SH 152
CSJ 0030-08-033
Proj ID STP 2014(004)
Work Type SEAL COAT
 
147.938 5038371.89 201075.00 225075.00 4.4
Work Order 10-10-13
Work Began 00-00-00
Work Completed  
Time Computed 10-26-13
Contract Working Days 50
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
LIPHAM ASPHALT AND PAVING COMPANY, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0030-08-033
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 09133237
Totals 5038371.89 201075.00 225075.00 4.4

CountyKING
Highway US 83
From COTTLE C/L, S
To GUTHRIE
CSJ 0032-05-038
Proj ID C 32-5-38
Work Type MISCELLANEOUS WORK
 
15.270 77364.00 0.00 0.00 0.0
CountyKING
Highway US 83
From US 82, S
To STONEWALL C/L
CSJ 0032-06-036
Proj ID C 32-6-36
Work Type MISCELLANEOUS WORK
 
14.440 8596.00 0.00 0.00 0.0
CountyHALL
Highway SH 256
From 0.3 MILES E OF SH 70, E
To FM 2361
CSJ 0541-02-030
Proj ID C 541-2-30
Work Type REPLACE BRIDGERAIL
 
30.323 581853.35 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 08-20-12
Work Began 00-00-00
Work Completed  
Time Computed 09-05-12
Contract Working Days 72
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
PRICE CONSTRUCTION, LTD.
SUBCONTRACTOR(S) FOR CCSJ: 0541-02-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 06123013
Totals 667813.35 0.00 0.00 0.0

CountyDONLEY
Highway US 287
From ARMSTRONG C/L
To CLARENDON WCL (SBL)
CSJ 0042-06-067
Proj ID NH 2014(061)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
11.635 2248102.73 0.00 193911.65 8.6
Work Order 01-17-14
Work Began 00-00-00
Work Completed  
Time Computed 02-02-14
Contract Working Days 48
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-06-067
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10133207
Totals 2248102.73 0.00 193911.65 8.6

CountyHALL
Highway US 287
From RED RIVER BRIDGE, SE
To CHILDRESS C/L (NBL)
CSJ 0042-09-120
Proj ID NH 2014(752)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
3.350 1106400.71 0.00 0.00 0.0
CountyCHILDRESS
Highway US 287
From HALL C/L, SE
To 0.36 MILES WEST OF FM 164(NBL)
CSJ 0042-12-063
Proj ID NH 2014(752)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
9.172 3136409.13 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 73
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0042-12-063
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143032
Totals 4242809.84 0.00 0.00 0.0

CountyHARDEMAN
Highway US 287
From FM 1166, SE
To LP 285 (SBL)
CSJ 0043-02-071
Proj ID NH 2014(062)
Work Type ASPHALTIC CONCRETE PAVEMENT OVERLAY
 
5.395 1474832.91 0.00 0.00 0.0
Work Order 01-06-14
Work Began 00-00-00
Work Completed  
Time Computed 01-22-14
Contract Working Days 35
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0043-02-071
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 10133011
Totals 1474832.91 0.00 0.00 0.0

CountyKNOX
Highway SH 6
From 0.374 MILES SOUTH OF FOARD C/L
To SOUTH 8.428 MILES
CSJ 0098-04-033
Proj ID STP 2013(270)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
8.428 3689620.50 301395.46 1093665.84 29.6
Work Order 01-23-13
Work Began 04-15-13
Work Completed  
Time Computed 02-08-13
Contract Working Days 158
Addl Days Granted 0
Working Days Charged 124
Percent Time Used 78
Contractor(s)
ZACK BURKETT CO.
SUBCONTRACTOR(S) FOR CCSJ: 0098-04-033
W.S. CONSTRUCTION COMPANY(6.04%)
HIGHWAY TECHNOLOGIES, INC. (0.33%)
COWBELL TRAFFIC SERVICES, INC. (0.26%)
HJC FARMS, INC.(0.58%)
COTHRAN TRUCKING, LLC(3.45%)
FLAT LINE, INC.(0.83%)
TEXAS ALTERNATIVE GRASSER, INC.(0.96%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.24%)
Contract # 12123022
Totals 3689620.50 301395.46 1093665.84 29.6

CountyMOTLEY
Highway SH 70
From NORTH PEASE RIVER
To .
CSJ 0105-04-042
Proj ID BR 2013(663)
Work Type REPLACEMENT OF EXISTING BRIDGE
 
0.240 2085247.00 106937.56 1516983.43 72.7
CountyMOTLEY
Highway SH 70
From @ MIDDLE PEASE RIVER
To .
CSJ 0105-04-043
Proj ID BR 2013(663)
Work Type REPLACEMENT OF EXISTING BRIDGE
 
0.315 2182953.50 1869.50 407038.75 18.6
Work Order 07-31-13
Work Began 09-03-13
Work Completed  
Time Computed 08-16-13
Contract Working Days 275
Addl Days Granted 0
Working Days Charged 113
Percent Time Used 41
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0105-04-042
BARRICADES UNLIMITED (0.82%)
DUSTROL, INC.(0.19%)
LANCO TURF & SEEDING, INC. (0.47%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (8.58%)
MASTERPIECE GRINDING & GROOVING, LLC (0.13%)
ROSS GRAHAM(0.40%)
G & L REBAR(0.49%)
Contract # 05133233
Totals 4268200.50 108807.06 1924022.18 45.0

CountyCOTTLE
Highway US 62
From MOTLEY C/L, E
To PADUCAH WCL
CSJ 0146-02-031
Proj ID C 146-2-31
Work Type ASPHALTIC CONCRETE OVERLAY
 
12.629 8687349.82 5000.00 8963289.02 99.9
CountyCOTTLE
Highway US 62
From PADUCAH W.C.L, E
To US 83
CSJ 0146-03-043
Proj ID C 146-3-43
Work Type REHABILITATION OF EXISTING ROADWAY
 
0.857 558249.34 45599.05 629707.95 99.9
CountyCOTTLE
Highway US 70
From US 83, E
To FM 1037
CSJ 0146-03-044
Proj ID C 146-3-44
Work Type REHABILITATION OF EXISTING ROADWAY
 
0.920 225659.93 0.00 0.00 0.0
Work Order 09-17-12
Work Began 06-24-13
Work Completed  
Time Computed 07-08-13
Contract Working Days 211
Addl Days Granted 0
Working Days Charged 147
Percent Time Used 69
Contractor(s)
DUININCK, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0146-02-031
WEST TEXAS BARRICADES, LLC DBA BARRICADES UNLIMITED(0.20%)
GARZA CONCRETE CONSTRUCTION(2.45%)
TEXAS ALTERNATIVE GRASSER, INC.(0.03%)
TEX OP CONSTRUCTION, LP(3.57%)
TEXAS PANHANDLE CONSTRUCTION, INC. (0.86%)
DUSTY ALLEN, INC.(0.61%)
Contract # 07123012
Totals 9471259.09 50599.05 9592996.97 99.9

CountyCOLLINGSWORTH
Highway SH 203
From @ SALT FORK OF RED RIVER
To .
CSJ 0230-01-018
Proj ID C 230-1-18
Work Type REHABILITATION EXIST TRUSS BRIDGE
 
0.200 2895507.75 168997.97 2550409.66 89.2
Work Order 09-24-12
Work Began 10-29-12
Work Completed  
Time Computed 10-29-12
Contract Working Days 202
Addl Days Granted 19
Working Days Charged 263
Percent Time Used 119
Contractor(s)
SCR CONSTRUCTION CO., INC.
SUBCONTRACTOR(S) FOR CCSJ: 0230-01-018
DUSTROL, INC.(0.37%)
S & S PAINTING ( 43.37%)
HIGHWAY TECHNOLOGIES, INC. (0.24%)
WEST TEXAS BARRICADES, LTD DBA BARRICADES UNLIMITED(0.15%)
ODUM SERVICES, L.P.(0.71%)
TEXAS ALTERNATIVE GRASSER, INC.(0.06%)
SOUTHEAST GRINDING & GROOVING, LLC (0.13%)
J.L. STEEL REINFORCING, LLC(0.87%)
Contract # 08123215
Totals 2895507.75 168997.97 2550409.66 89.2

CountyHALL
Highway SH 86
From 118 FT E OF CR 3
To SH 70
CSJ 0303-05-018
Proj ID STP 2014(473)
Work Type REHABILITATION OF EXISTING ROADWAY
 
0.616 2600383.20 0.00 0.00 0.0
CountyHALL
Highway SH 86
From 118 FT E OF CR 3
To SH 70
CSJ 0303-05-019
Proj ID STP 1302(074)
Work Type ROW UTL. ADJ.
 
0.616 408330.05 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 212
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
J. LEE MILLIGAN, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0303-05-018
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143216
Totals 3008713.25 0.00 0.00 0.0

CountyBRISCOE
Highway SH 207
From FLOYD C/L NORTH
To SH 86
CSJ 0453-06-011
Proj ID STP 2014(229)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
11.022 4243800.64 0.00 0.00 0.0
Work Order 01-06-14
Work Began 00-00-00
Work Completed  
Time Computed 01-22-14
Contract Working Days 100
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0453-06-011
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11133023
Totals 4243800.64 0.00 0.00 0.0

CountyKING
Highway SH 222
From US 82, SE
To KNOX C/L
CSJ 0496-03-010
Proj ID STP 2013(813)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
6.983 2445663.33 295098.86 697493.02 28.5
CountyKNOX
Highway SH 222
From KING C/L, SE
To 4.015 MILES
CSJ 0496-04-031
Proj ID STP 2013(813)
Work Type WIDENING OF NON - FREEWAY FACILITY
 
4.015 1217352.66 25440.00 50840.00 4.1
Work Order 08-19-13
Work Began 09-23-13
Work Completed  
Time Computed 09-04-13
Contract Working Days 203
Addl Days Granted 0
Working Days Charged 98
Percent Time Used 48
Contractor(s)
A. L. HELMCAMP, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0496-03-010
W.S. CONSTRUCTION COMPANY(6.00%)
CONTRACTORS SERVICE COMPANY(0.51%)
HJC FARMS, INC.(2.35%)
TEXAS ALTERNATIVE GRASSER, INC.(0.42%)
WEST TEXAS RUMBLE STRIP(0.15%)
ZACK BURKETT CO. ( 42.81%)
BARRICADES UNLIMITED (1.67%)
Contract # 06133026
Totals 3663015.99 320538.86 748333.02 20.4

CountyCHILDRESS
Highway VA
From DISTRICT WIDE
To .
CSJ 0925-00-061
Proj ID STP 2014(474)
Work Type DISTRICT WIDE STRIPING AND RPM
 
200.000 975240.10 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 34
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
TEXAS PANHANDLE CONSTRUCTION, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-00-061
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 03143010
Totals 975240.10 0.00 0.00 0.0

CountyHARDEMAN
Highway CR
From STAR VALLEY RD @ DEVIL'S CREEK
To .
CSJ 0925-07-013
Proj ID BR 2002(752)
Work Type REPLACE EXISTING BRIDGE FACILITY
 
0.075 403203.75 0.00 0.00 0.0
Work Order 03-13-14
Work Began 00-00-00
Work Completed  
Time Computed 03-29-14
Contract Working Days 78
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
RK HALL, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0925-07-013
DUSTY ALLEN, INC.(3.62%)
TOTAL HIGHWAY MAINTENANCE, LLC (0.61%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (6.74%)
TEXAS ALTERNATIVE GRASSER, INC.(2.07%)
Contract # 02143013
Totals 403203.75 0.00 0.00 0.0

CountyHALL
Highway CR
From CR D @ POLECAT CREEK
To .
CSJ 0925-09-030
Proj ID BR 2011(863)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.080 202931.08 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 03-25-14
Work Began 00-00-00
Work Completed  
Time Computed 04-10-14
Contract Working Days 68
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
EASTER CONSTRUCTION INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-09-030
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 02143223
Totals 202931.08 0.00 0.00 0.0

CountyBRISCOE
Highway PW
From @ CAPROCK CANYON STATE PARK
To .
CSJ 0925-12-014
Proj ID C 925-12-14
Work Type REPAIR DRAINAGE FACILITIES
 
0.100 162224.16 58730.00 113332.00 69.8
Work Order 01-06-14
Work Began 02-24-14
Work Completed  
Time Computed 01-22-14
Contract Working Days 28
Addl Days Granted 0
Working Days Charged 12
Percent Time Used 42
Contractor(s)
OMEGA CONSTRUCTION GROUP, LLC
SUBCONTRACTOR(S) FOR CCSJ: 0925-12-014
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 11133018
Totals 162224.16 58730.00 113332.00 69.8

CountyDICKENS
Highway CR
From 5TH STREET @ J2 CREEK
To .
CSJ 0925-15-007
Proj ID BR 2013(892)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.054 277834.00 0.00 0.00 0.0
CountyDICKENS
Highway CR
From CR 222 @ COTTONWOOD CREEK
To .
CSJ 0925-15-008
Proj ID BR 2013(892)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.109 419578.00 0.00 0.00 0.0
CountyDICKENS
Highway CR
From CR 386 @ WILSON DRAW
To .
CSJ 0925-15-009
Proj ID BR 2014(790)
Work Type REPLACEMENT OF EXISTING BRIDGE FACI
 
0.065 218564.00 0.00 0.00 0.0
NO CURRENT ESTIMATE AT TIME OF THIS RUN
Work Order 00-00-00
Work Began 00-00-00
Work Completed  
Time Computed 00-00-00
Contract Working Days 129
Addl Days Granted 0
Working Days Charged 0
Percent Time Used 0
Contractor(s)
HODGES AND SON CONSTRUCTION COMPANY, INC.
SUBCONTRACTOR(S) FOR CCSJ: 0925-15-007
NO SUBCONTRACTORS FOR THIS CCSJ
Contract # 04143230
Totals 915976.00 0.00 0.00 0.0

CountyKING
Highway FM 193
From COTTONWOOD CREEK
To .
CSJ 0950-02-012
Proj ID BR 2013(979)
Work Type UPGRADE BRIDGE RAILING AND APPROACH
 
0.172 727863.84 155345.10 456997.22 62.7
Work Order 11-25-13
Work Began 02-12-14
Work Completed  
Time Computed 12-11-13
Contract Working Days 90
Addl Days Granted 0
Working Days Charged 55
Percent Time Used 61
Contractor(s)
EARTH BUILDERS, L.P.
SUBCONTRACTOR(S) FOR CCSJ: 0950-02-012
SOUTHEAST GRINDING & GROOVING, LLC (0.44%)
BARRICADES UNLIMITED (0.71%)
CONTRACTORS SERVICE COMPANY(0.74%)
LANCO TURF & SEEDING, INC. (2.43%)
M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.29%)
G & L REBAR(0.18%)
ROSS GRAHAM(1.40%)
Contract # 08133047
Totals 727863.84 155345.10 456997.22 62.7

page 1