|
| Contract Identification and Information |
Length |
Contract Amount |
Amount This Estimate |
Total Estimate To Date |
% Comp |
|
| County | WHEELER |
| Highway |
US 83 |
| From |
@ BRONCO CREEK |
| To |
. |
| CSJ |
0030-09-043 |
| Proj ID |
BR 2009(018) |
| Work Type |
REPLACE EXIST BRIDGE FACILITY |
| |
|
0.246 |
1250625.54 |
48058.00 |
48058.00 |
3.8 |
| Work Order |
10-16-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
11-01-08 |
| Contract Working Days |
140 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| GILVIN-TERRILL, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0030-09-043 BARRICADES UNLIMITED, INC. (LUBBOCK) (0.83%) GARY A. CRAIN, INC.(0.31%) GUAJARDO STEEL (3.12%) JAVALINA CONSTRUCTION SOUTH, INC.(0.61%) JONA CONTRACTING, INC. (2.96%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (3.71%) TEXAS ALTERNATIVE GRASSER, INC.(0.28%)
|
| Contract # |
09083209 |
|
Totals |
1250625.54 |
48058.00 |
48058.00 |
3.8 |
|
| County | COLLINGSWORTH |
| Highway |
US 83 |
| From |
3.8 MILES S OF RED RIVER BRIDGE, N |
| To |
RED RIVER BRIDGE (SBL) |
| CSJ |
0031-04-043 |
| Proj ID |
STP 2008(204) |
| Work Type |
ASPHALTIC CONCRETE OVERLAY |
| |
|
8.462 |
2990072.73 |
0.00 |
564706.77 |
18.8 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
12-31-07 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
51 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| JORDAN PAVING CORPORATION |
SUBCONTRACTOR(S) FOR CCSJ: 0031-04-043 PRIMATE CONSTRUCTION, INC. (0.51%) DUSTROL, INC.(0.84%) FLAT LINE, INC.(1.50%) TEXAS ALTERNATIVE GRASSER, INC.(0.10%) UNITED RENTALS HIGHWAY TECHNOLOGIES (DALLAS) (0.16%)
|
| Contract # |
12073015 |
|
Totals |
2990072.73 |
0.00 |
564706.77 |
18.8 |
|
| County | CHILDRESS |
| Highway |
US 62 |
| From |
US 287, N |
| To |
FM 3181 |
| CSJ |
0031-06-029 |
| Proj ID |
NH 2005(915) |
| Work Type |
REHABILITATION OF EXISTING ROADWAY |
| |
|
0.769 |
1253934.59 |
0.00 |
1253341.75 |
99.9 |
| County | CHILDRESS |
| Highway |
US 62 |
| From |
FM 164, N |
| To |
US 287 |
| CSJ |
0032-01-028 |
| Proj ID |
STP 2005(867)RGS |
| Work Type |
REPLACE EXISTING RR UNDERPASS |
| |
|
0.715 |
10049618.48 |
0.00 |
10806679.08 |
99.9 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
06-08-06 |
| Work Began |
08-14-06 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
268 |
| Addl Days Granted |
93 |
| Working Days Charged |
435 |
| Percent Time Used |
120 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0032-01-028 UNITED RENTALS HIGHWAY TECHNOLOGIES (NEWELL RD-FTWORTH)(0.32%) CEN-TEX SEEDING, INC.(0.87%) TEXAS HIGHWAY MARKINGS, LLC(0.74%) JORDAN PAVING CORPORATION( 11.89%) BREDA COMPANY, INC.(0.97%) NORTH TEXAS BOMANITE, INC. (0.33%) CAPROCK SPECIALITY CONTRACTORS (0.15%) TEX OP CONSTRUCTION, LP(1.02%) TEXAS SHAFTS, INC. (1.01%) A & M FENCE OF TEXAS (0.50%) CRAIG OLDEN, INC.(1.40%) CUSTOM STONE DESIGN, INC.(0.00%) DANIEL CONSTRUCTION SERVICES, INC. (AR DANIEL...)(0.77%) WS CONSTRUCTION CO.(2.29%) L.T. EQUIPMENT COMPANY (0.00%) FLAT LINE, INC.(0.25%) HARDSCAPE CONSTRUCTION SPECIALTIES (0.18%)
|
| Contract # |
04063020 |
|
Totals |
11303553.07 |
0.00 |
12060020.83 |
99.9 |
|
| County | COTTLE |
| Highway |
US 83 |
| From |
@ SALT CREEK |
| To |
. |
| CSJ |
0032-04-029 |
| Proj ID |
BR 2008(094) |
| Work Type |
REPLACE EXIST BRIDGE FACILITY |
| |
|
0.180 |
1121503.93 |
24267.22 |
1115962.79 |
99.5 |
| Work Order |
12-04-07 |
| Work Began |
12-20-07 |
| Work Completed |
|
| Time Computed |
12-20-07 |
| Contract Working Days |
122 |
| Addl Days Granted |
21 |
| Working Days Charged |
142 |
| Percent Time Used |
99 |
| Contractor(s) |
| COPPELL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0032-04-029 HIGHWAY TECHNOLOGIES (0.37%) CRAWFORD YANT(1.33%) JONA CONTRACTING, INC. (3.57%) ATS DRILLING, L.P. (4.37%) GARY A. CRAIN, INC.(0.62%) BARRICADES UNLIMITED, INC. (LUBBOCK) (1.19%) DUININCK BROS, INC.(2.22%) JORDAN PAVING CORPORATION(9.76%)
|
| Contract # |
10073020 |
|
Totals |
1121503.93 |
24267.22 |
1115962.79 |
99.5 |
|
| County | KING |
| Highway |
US 83 |
| From |
S INTERSECTION US 82/83, S |
| To |
1658' |
| CSJ |
0032-06-032 |
| Proj ID |
STP 2005(650) |
| Work Type |
REHABILITATION OF EXISTING ROADWAY |
| |
|
0.314 |
395896.18 |
0.00 |
110744.52 |
29.4 |
| County | KING |
| Highway |
US 82 |
| From |
2 MI W OF US 82 & 83 N INT, E |
| To |
US 82 & 83 N INT |
| CSJ |
0132-03-029 |
| Proj ID |
NH 2005(672) |
| Work Type |
NEW (NNF) LOC NON - FREEWAY FACILITY |
| |
|
2.000 |
13254138.22 |
332236.20 |
12537700.90 |
99.9 |
| County | KING |
| Highway |
US 82 |
| From |
US 82 & 83 N INT |
| To |
1 MI EAST OF US 82 & 83 S INT |
| CSJ |
0133-01-038 |
| Proj ID |
NH 2005(672) |
| Work Type |
NEW (NNF) LOC NON - FREEWAY FACILITY |
| |
|
2.080 |
3133594.14 |
208496.82 |
2474595.88 |
83.1 |
| Work Order |
09-13-05 |
| Work Began |
11-01-05 |
| Work Completed |
|
| Time Computed |
09-29-05 |
| Contract Working Days |
309 |
| Addl Days Granted |
73 |
| Working Days Charged |
456 |
| Percent Time Used |
119 |
| Contractor(s) |
| R. K. HALL CONSTRUCTION, LTD. |
SUBCONTRACTOR(S) FOR CCSJ: 0132-03-029 T-BAR FABRICATORS, INC.(1.65%) REBAR SERVICE & SUPPLY CO. (1.33%) NORTH TEXAS TRAFFIC SYSTEMS CONSTRUCTION (1.37%) JONA CONTRACTING, INC. (1.58%) TEXAS SHAFTS, INC. (1.32%) MIDWEST ASPHALT CORPORATION (GAINESVILLE)(0.03%) BARRICADES UNLIMITED, INC. (LUBBOCK) (0.29%) W.S. CONSTRUCTION COMPANY(0.39%) VELASQUEZ CONCRETE CONSTRUCTION(0.10%)
|
| Contract # |
07053007 |
|
Totals |
16783628.54 |
540733.02 |
15123041.30 |
95.4 |
|
| County | DONLEY |
| Highway |
US 287 ETC |
| From |
ARMSTRONG C/L_(NBL) |
| To |
CLARENDON WCL |
| CSJ |
0042-06-063 |
| Proj ID |
CPM 42-6-63 |
| Work Type |
SEALCOAT TYPE WORK |
| |
|
330.746 |
7692371.11 |
200904.70 |
6782245.85 |
91.8 |
| Work Order |
10-12-07 |
| Work Began |
08-05-08 |
| Work Completed |
|
| Time Computed |
10-28-07 |
| Contract Working Days |
80 |
| Addl Days Granted |
0 |
| Working Days Charged |
36 |
| Percent Time Used |
45 |
| Contractor(s) |
| RONALD R. WAGNER & CO., LP |
SUBCONTRACTOR(S) FOR CCSJ: 0042-06-063 FLASHER EQUIPMENT COMPANY(4.97%)
|
| Contract # |
09073206 |
|
Totals |
7692371.11 |
200904.70 |
6782245.85 |
91.8 |
|
| County | FOARD |
| Highway |
SH 6 |
| From |
@ NORTH WICHITA RIVER |
| To |
. |
| CSJ |
0098-03-033 |
| Proj ID |
BR 2008(095) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
1.270 |
4368544.38 |
1375.00 |
2370046.40 |
54.2 |
| County | FOARD |
| Highway |
FM 267 |
| From |
@ NORTH WICHITA RIVER |
| To |
. |
| CSJ |
2164-02-015 |
| Proj ID |
BR 2008(095) |
| Work Type |
REPLACE BRIDGE |
| |
|
0.240 |
1817560.15 |
46847.94 |
1832850.88 |
99.9 |
| Work Order |
11-13-07 |
| Work Began |
12-13-07 |
| Work Completed |
|
| Time Computed |
11-29-07 |
| Contract Working Days |
289 |
| Addl Days Granted |
0 |
| Working Days Charged |
207 |
| Percent Time Used |
71 |
| Contractor(s) |
| COPPELL CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0098-03-033 ATS DRILLING, L.P. (5.64%) BARRICADES UNLIMITED, INC. (LUBBOCK) (0.15%) CONTRACTORS SERVICE COMPANY(0.39%) CRAWFORD YANT(0.27%) DUININCK BROS, INC.( 36.82%) GARY A. CRAIN, INC.(0.53%) JONA CONTRACTING, INC. (0.84%) LANCO TURF & SEEDING, INC. (0.26%)
|
| Contract # |
10073008 |
|
Totals |
6186104.53 |
48222.94 |
4202897.28 |
67.9 |
|
| County | DONLEY |
| Highway |
SH 70 |
| From |
HOWARDWICK, S |
| To |
US 287 |
| CSJ |
0310-01-038 |
| Proj ID |
STP 2008(205) |
| Work Type |
ASPHALTIC CONCRETE PAVEMENT OVERLAY |
| |
|
5.980 |
1540381.72 |
0.00 |
179012.35 |
11.6 |
| Work Order |
01-02-08 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
01-18-08 |
| Contract Working Days |
35 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| J. LEE MILLIGAN, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0310-01-038 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
12073024 |
|
Totals |
1540381.72 |
0.00 |
179012.35 |
11.6 |
|
| County | CHILDRESS |
| Highway |
US 62 ETC |
| From |
US 62/83, E |
| To |
OKLAHOMA S/L |
| CSJ |
0381-01-015 |
| Proj ID |
NH 2009(128) |
| Work Type |
SEALCOAT TYPE WORK |
| |
|
150.604 |
4832006.40 |
0.00 |
0.00 |
0.0 |
| NO CURRENT ESTIMATE AT TIME OF THIS RUN |
| Work Order |
00-00-00 |
| Work Began |
00-00-00 |
| Work Completed |
|
| Time Computed |
00-00-00 |
| Contract Working Days |
44 |
| Addl Days Granted |
0 |
| Working Days Charged |
0 |
| Percent Time Used |
0 |
| Contractor(s) |
| LIPHAM CONSTRUCTION CO., INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0381-01-015 NO SUBCONTRACTORS FOR THIS CCSJ
|
| Contract # |
11083216 |
|
Totals |
4832006.40 |
0.00 |
0.00 |
0.0 |
|
| County | HALL |
| Highway |
SH 256 |
| From |
US 287 |
| To |
0.3 MILES EAST OF SH 70 |
| CSJ |
0541-02-028 |
| Proj ID |
STP 2008(575)HES |
| Work Type |
MODERNIZE BRIDGERAIL & SAFETY TREAT |
| |
|
21.300 |
501972.00 |
58983.49 |
402108.45 |
80.1 |
| Work Order |
07-02-08 |
| Work Began |
07-18-08 |
| Work Completed |
|
| Time Computed |
10-01-08 |
| Contract Working Days |
102 |
| Addl Days Granted |
0 |
| Working Days Charged |
51 |
| Percent Time Used |
50 |
| Contractor(s) |
| ENCINO LANDSCAPE, INC. |
SUBCONTRACTOR(S) FOR CCSJ: 0541-02-028 W.S. CONSTRUCTION COMPANY( 33.45%)
|
| Contract # |
05083217 |
|
Totals |
501972.00 |
58983.49 |
402108.45 |
80.1 |
|
| County | HARDEMAN |
| Highway |
CR |
| From |
VESTAL RD @ N GROESBECK CREEK |
| To |
. |
| CSJ |
0925-07-011 |
| Proj ID |
BR 2001(695) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.001 |
427389.68 |
29974.00 |
391286.54 |
91.5 |
| County | HARDEMAN |
| Highway |
CR |
| From |
ARKANSAS RD @ SOUTH GROESBECK CREEK |
| To |
. |
| CSJ |
0925-07-020 |
| Proj ID |
BR 2006(421) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.100 |
616392.79 |
52931.00 |
585551.30 |
94.9 |
| Work Order |
01-03-08 |
| Work Began |
03-03-08 |
| Work Completed |
|
| Time Computed |
01-19-08 |
| Contract Working Days |
170 |
| Addl Days Granted |
0 |
| Working Days Charged |
142 |
| Percent Time Used |
83 |
| Contractor(s) |
| AUSTIN BRIDGE & ROAD, LP |
SUBCONTRACTOR(S) FOR CCSJ: 0925-07-020 S & S BRIDGE PAINTING, INC.(0.16%) WIMS ENVIRONMENTAL CONSTRUCTION, LTD.(4.68%) ODUM SERVICES, L.P.(4.84%) SD TRUCKING(2.13%) GUAJARDO STEEL (1.20%) HIGHWAY TECHNOLOGIES, L.P. (0.68%) CAPROCK SPECIALITY CONTRACTORS (0.19%) ATS DRILLING, L.P. (8.92%)
|
| Contract # |
12073029 |
|
Totals |
1043782.47 |
82905.00 |
976837.84 |
93.5 |
|
| County | DONLEY |
| Highway |
CR |
| From |
CR 28 @ BUCK CREEK |
| To |
. |
| CSJ |
0925-10-022 |
| Proj ID |
BR 2001(696) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.331 |
1068679.70 |
232104.40 |
685878.84 |
64.1 |
| Work Order |
05-12-08 |
| Work Began |
06-23-08 |
| Work Completed |
|
| Time Computed |
05-28-08 |
| Contract Working Days |
201 |
| Addl Days Granted |
0 |
| Working Days Charged |
72 |
| Percent Time Used |
35 |
| Contractor(s) |
| EARTH BUILDERS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 0925-10-022 JUST GROOVING, LTD.(0.11%) JONA CONTRACTING, INC. (3.36%) M & D FOUNDATION DRILLING INDUSTRIES, INC. (4.77%) LANCO TURF & SEEDING, INC. (0.17%) BARRICADES UNLIMITED, INC. (LUBBOCK) (0.91%)
|
| Contract # |
04083022 |
|
Totals |
1068679.70 |
232104.40 |
685878.84 |
64.1 |
|
| County | DICKENS |
| Highway |
FM 193 |
| From |
@ COTTONWOOD CREEK |
| To |
. |
| CSJ |
0950-01-026 |
| Proj ID |
BR 2008(192) |
| Work Type |
REPLACEMENT OF EXISTING BRIDGE FACI |
| |
|
0.091 |
467623.90 |
41168.00 |
215385.40 |
46.0 |
| County | DICKENS |
| Highway |
FM 193 |
| From |
@ NORTH WICHITA RIVER |
| To |
. |
| CSJ |
0950-05-011 |
| Proj ID |
BR 2008(192) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.227 |
741984.00 |
18366.84 |
131834.34 |
17.7 |
| County | DICKENS |
| Highway |
FM 193 |
| From |
@ NORTH WICHITA RIVER |
| To |
. |
| CSJ |
0950-05-013 |
| Proj ID |
BR 2008(192) |
| Work Type |
REPLACEMENT OF EXISTING BRIDGE FACI |
| |
|
0.097 |
662731.50 |
72542.50 |
135167.50 |
20.3 |
| County | COTTLE |
| Highway |
FM 2278 |
| From |
@ BUCK CREEK |
| To |
. |
| CSJ |
2143-01-008 |
| Proj ID |
BR 2008(192) |
| Work Type |
REPLACEMENT OF AN EXISTING BRIDGE |
| |
|
0.089 |
518065.10 |
0.00 |
203235.49 |
39.2 |
| Work Order |
02-20-08 |
| Work Began |
03-07-08 |
| Work Completed |
|
| Time Computed |
03-07-08 |
| Contract Working Days |
218 |
| Addl Days Granted |
0 |
| Working Days Charged |
137 |
| Percent Time Used |
62 |
| Contractor(s) |
| AMARILLO ROAD COMPANY, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 2143-01-008 BARRICADES UNLIMITED, INC. (LUBBOCK) (0.69%) CAPROCK SPECIALITY CONTRACTORS (0.12%) HIGHWAY TECHNOLOGIES, L.P. (0.62%) JONA CONTRACTING, INC. (3.70%) SHINN & GREGORY, INC.(3.83%) TEXAS ALTERNATIVE GRASSER, INC.(0.43%) TEXAS SHAFTS, INC. (4.52%) APEX TECHNICAL SERVICES, INC.(0.00%)
|
| Contract # |
12073221 |
|
Totals |
2390404.50 |
132077.34 |
685622.73 |
28.6 |
|
| County | DICKENS |
| Highway |
FM 1868 |
| From |
@ COTTONWOOD CREEK |
| To |
. |
| CSJ |
1773-01-009 |
| Proj ID |
BR 2008(093) |
| Work Type |
REPLACE BRIDGE AND APPROACHES |
| |
|
0.095 |
776348.78 |
39494.66 |
668395.00 |
86.0 |
| County | DICKENS |
| Highway |
FM 1868 |
| From |
@ DUCK CREEK |
| To |
. |
| CSJ |
1773-01-011 |
| Proj ID |
BR 2008(093) |
| Work Type |
REPLACEMENT OF EXISTING BRIDGE FACI |
| |
|
0.102 |
700566.88 |
36376.00 |
512622.90 |
73.1 |
| Work Order |
12-04-07 |
| Work Began |
03-01-08 |
| Work Completed |
|
| Time Computed |
12-20-07 |
| Contract Working Days |
180 |
| Addl Days Granted |
0 |
| Working Days Charged |
153 |
| Percent Time Used |
85 |
| Contractor(s) |
| EARTH BUILDERS, L.P. |
SUBCONTRACTOR(S) FOR CCSJ: 1773-01-009 ATS DRILLING, L.P. ( 11.60%) BARRICADES UNLIMITED, INC. (LUBBOCK) (0.35%) CAPROCK SPECIALITY CONTRACTORS (0.17%) CRAWFORD YANT(1.34%) HIGHWAY TECHNOLOGIES, L.P. (0.39%) JONA CONTRACTING, INC. (2.35%) RAYMOND PAINTING, INC. (0.07%) SD TRUCKING(1.63%)
|
| Contract # |
10073221 |
|
Totals |
1476915.66 |
75870.66 |
1181017.90 |
79.9 |
|